Pond Permits & Regulations by State

Which permits a new pond needs depends on how big it is, where it sits, and which state it is in. Every statement in this guide links to the statute, regulation, court decision or agency page it comes from.

Under federal law, discharging dredged or fill material into waters of the United States needs a Clean Water Act Section 404 permit (a nationwide, regional or individual permit) unless the discharge is exempt, and the discharge of fill material generally includes building dams and dikes. An activity outside those waters, or one that involves no discharge, does not need a Section 404 permit. EPA says a Clean Water Act permit is required for stormwater discharges from construction activity, such as clearing, grading and excavating, that disturbs 1 acre or more (or less than 1 acre as part of a common plan of development or sale that will ultimately disturb 1 acre or more). FEMA says a permit is required before construction or development begins within any Special Flood Hazard Area, and the National Flood Insurance Program counts excavation, filling and grading as development. On dam safety, the Corps says most dams in the National Inventory of Dams are regulated by state agencies. State definitions of a jurisdictional dam differ. In Pennsylvania, for example, Chapter 105 regulates a dam on a natural or artificial watercourse (other than one licensed under the Federal Power Act) if one or more of these apply: its contributory drainage area exceeds 100 acres; the greatest depth of water, measured at the upstream toe at maximum storage elevation, exceeds 15 feet; or its impounding capacity at maximum storage elevation exceeds 50 acre-feet. [1][2][3][4][5][6][7]

Each state page below sorts that state's rules into four tiers, from projects that usually need no state permit to embankments large enough to be regulated as dams. Use a state's page to see which agencies a project is likely to involve before you commit to a size or a site, then confirm with those agencies.

How the permit tiers work

The tiers are our way of summarizing each state's rules; the agencies do not use these labels. A single project can land in more than one tier, for example a pond that needs an erosion and sediment control plan (tier 1) and also a stream or wetland permit (tier 2). When that happens, the rules behind each of those tiers apply.

Tier 0

Usually no state permit

The pond is below every state threshold and away from streams, wetlands and floodplains. General duties such as erosion control and local ordinances may still apply.

Tier 1

Plan, registration or notice

The steps in this tier need no agency approval before work starts: you must prepare a plan (such as an erosion and sediment control plan), register, notify an agency, or qualify under a waiver or a general authorization that needs no such approval. If another part of the project does need an agency's approval before work starts, Tier 2 applies as well.

Tier 2

Permit or approval required

An agency must approve the project before work starts, for example for work in a stream or wetland, construction stormwater, or a water right. If the pond's dam also meets the state's dam-safety thresholds, Tier 3 applies as well.

Tier 3

Regulated dam

The embankment meets the state's dam-safety thresholds, which can turn on height or water depth, storage, drainage area or hazard, so the state's dam-safety rules apply. Each state page sets out what those rules require, such as a dam permit, engineered plans, or inspection and maintenance duties.

Choose your state

States are being researched and published in batches, and each page shows the date its sources were last checked. States marked “coming soon” are still being researched and checked.

AlabamaComing soon
AlaskaComing soon
ArizonaComing soon
ArkansasComing soon
CaliforniaComing soon
ColoradoComing soon
ConnecticutComing soon
DelawareComing soon
District of ColumbiaComing soon
FloridaComing soon
GeorgiaComing soon
HawaiiComing soon
IdahoComing soon
IllinoisComing soon
IndianaComing soon
IowaComing soon
KansasComing soon
KentuckyComing soon
LouisianaComing soon
MaineComing soon
MarylandComing soon
MassachusettsComing soon
MichiganComing soon
MinnesotaComing soon
MississippiComing soon
MissouriComing soon
MontanaComing soon
NebraskaComing soon
NevadaComing soon
New HampshireComing soon
New JerseyComing soon
New MexicoComing soon
New YorkComing soon
North CarolinaComing soon
North DakotaComing soon
OhioComing soon
OklahomaComing soon
OregonComing soon
Pennsylvania
Rhode IslandComing soon
South CarolinaComing soon
South DakotaComing soon
TennesseeComing soon
TexasComing soon
UtahComing soon
VermontComing soon
VirginiaComing soon
WashingtonComing soon
West VirginiaComing soon
WisconsinComing soon
WyomingComing soon

Federal rules that apply in every state

Section 404 of the Clean Water Act: Corps regulations require a Department of the Army permit to discharge dredged or fill material into waters of the United States, except for exempt discharges, and some discharges are authorized by nationwide or regional permits. The discharge of fill material into those waters generally includes building dams and dikes and any impoundment requiring rock, sand, dirt or other material. An activity outside waters of the United States, or one that involves no discharge, does not need a Section 404 permit. According to EPA, only Michigan and New Jersey currently run their own Section 404 programs, for assumable waters; the Corps is primarily responsible for Section 404 permits everywhere else, including non-assumable waters in those two states. [1][8]

The farm-pond exemption: the Act says a discharge of dredged or fill material for the construction or maintenance of farm or stock ponds is not prohibited by or otherwise subject to regulation under Section 404, except for section 307 effluent standards or prohibitions and except as its recapture paragraph, 404(f)(2), provides. Under Corps regulations a permit is still required if the discharge contains a toxic pollutant listed under section 307, or if it is part of an activity whose purpose is to convert an area of waters of the United States to a use to which it was not previously subject, where flow or circulation may be impaired or reach reduced. Farm ponds that lose the exemption because of recapture may be authorized by Nationwide Permit 40, which authorizes the construction of farm ponds in non-tidal waters of the United States, excluding perennial streams, provided the pond is used solely for agricultural purposes; the discharge must not cause the loss of more than 1/2 acre of non-tidal waters of the United States, and a pre-construction notification to the district engineer is required before work starts. The current nationwide permits took effect March 15, 2026 and expire March 15, 2031. [1][9][10]

Construction stormwater: EPA says a Clean Water Act permit is required for stormwater discharges from construction activity, including clearing, grading and excavating, that disturbs 1 acre or more, or less than 1 acre if it is part of a common plan of development or sale that will ultimately disturb 1 acre or more. EPA's August 3, 2026 notice on its draft 2027 Construction General Permit lists areas where EPA, not a state, is the construction stormwater permitting authority, including Massachusetts, New Hampshire, New Mexico, most Indian country lands, the District of Columbia, U.S. territories and protectorates except the U.S. Virgin Islands, Lands of Exclusive Federal Jurisdiction, and certain other federal areas. A state can run its own EPA-approved NPDES permit program; EPA lists Pennsylvania's, for example, as authorized on June 30, 1978. [2][11][12][13]

Floodplains: under the National Flood Insurance Program (NFIP), dredging, filling, grading and excavation count as “development,” and FEMA says a permit is required before construction or development begins within any Special Flood Hazard Area, the land subject to a 1 percent or greater chance of flooding in any given year. State and local governments enforce these rules through their own floodplain regulations. FEMA's criteria are minimum standards that any community may exceed. Participation in the NFIP is voluntary, and FEMA says more than 22,000 communities have agreed to adopt and enforce floodplain management ordinances. [3][4][14][15][16]

Dam safety: the Corps says most dams in the National Inventory of Dams are regulated by state agencies through construction permits, inspections and/or enforcement, and federal agencies own or regulate five percent of them. FEMA's Federal Guidelines for Dam Safety (December 2023) apply to federal practices for dams with a direct federal interest and are not intended to supplant or conflict with state, tribal or local responsibilities for the safety of dams under their jurisdiction. [5][17]

The NRCS pond standard is a design standard: NRCS policy requires low-hazard earth dams whose storage times effective height is less than 3,000 acre-feet times feet, and whose effective height is 35 feet or less, to meet or exceed the requirements of Conservation Practice Standard Pond (Code 378). The standard applies to all excavated ponds, and to embankment ponds only if they meet all of its low-hazard criteria. The standard itself requires ponds to be planned, designed and built to comply with all Federal, State and local laws, and requires the landowner to obtain all necessary permits before construction. NRCS's national page lists the Pond standard document as July 2022 but says national standards should not be used to plan, design or install a practice; each state adapts them in its Field Office Technical Guide, and state versions may be more restrictive but cannot be less stringent. Under the Environmental Quality Incentives Program (EQIP) regulation, practices in an EQIP plan of operations must be approved by NRCS and developed and carried out in accordance with the applicable NRCS planning and Field Office Technical Guide technical requirements. [18][19][20][21][22]

How this guide is researched

We use only primary sources: state statutes and administrative codes, state agency pages and guidance, U.S. Army Corps of Engineers, EPA, eCFR, the Federal Register, NRCS, FEMA, interstate river basin commissions, and the official text of court decisions. Secondary summaries are used only to find those sources, never cited.

Every statement carries the exact passage it is based on; expand “Show the source text” under any statement to read it. Each statement is checked by a second reviewer against the source in context, looking for misread numbers, missing exceptions, and rules that are proposed, expired or superseded. Anything we could not confirm is listed as not confirmed, with the agency to ask, rather than guessed.

Laws and agency practice change. Each page shows the date its sources were last checked; check that date before you rely on a page.

Frequently asked questions

Do I need a permit to build a pond?

It depends on the site, the size of the work and the state. Under federal law, discharging dredged or fill material into waters of the United States needs a Section 404 permit (a nationwide, regional or individual permit) unless the discharge is exempt, while an activity outside those waters, or one that involves no discharge, does not need one. EPA says a Clean Water Act permit is required for stormwater discharges from construction activity that disturbs 1 acre or more, or less than 1 acre as part of a common plan of development or sale that will ultimately disturb 1 acre or more, and FEMA says a permit is required before construction or development begins within any Special Flood Hazard Area. State rules can also apply. In Pennsylvania, for example, DEP says a Dam Permit is needed to build a dam across a watercourse if any one of DEP's limits on contributory drainage area (100 acres), water depth (15 feet) or impounding capacity (50 acre-feet) is exceeded. DEP adds that when a dam is below those limits, either a Water Obstruction and Encroachment Permit or an approved Environmental Assessment is still required if the dam is proposed across (or impacts) a stream or impacts a wetland, or if a stream or wetland is to be excavated or a wetland impounded. DEP also says Chapter 102 erosion and sediment control requirements apply whether or not the pond work needs Chapter 105 authorization. For construction such as pond excavation, the Chapter 102 regulation requires erosion and sediment control best management practices even for disturbance under 5,000 square feet, and a written erosion and sediment control plan when disturbance will be 5,000 square feet or more or in other listed cases. [1][2][3][7][23][24]

When does a pond become a regulated dam?

It depends on the state. The Corps says most dams in the National Inventory of Dams are regulated by state agencies through construction permits, inspections and/or enforcement. State definitions of a jurisdictional dam differ; the data dictionary for the Corps' National Inventory of Dams (August 2024) gives New Mexico as an example, where a jurisdictional dam is one that exceeds 10 feet in height regardless of storage, or stores more than 10 acre-feet regardless of height. In Pennsylvania, for example, Chapter 105 regulates a dam on a natural or artificial watercourse (other than one licensed under the Federal Power Act) if one or more of these apply: its contributory drainage area exceeds 100 acres; the greatest depth of water, measured at the upstream toe at maximum storage elevation, exceeds 15 feet; or its impounding capacity at maximum storage elevation exceeds 50 acre-feet. A Pennsylvania water-storage dam that is not on a watercourse and has no contributory drainage is regulated only if both the depth and the capacity limits are exceeded. FEMA notes that hazard potential classification systems vary between state and federal agencies, and that state dam safety regulators use them for purposes including assigning design requirements and determining the frequency of operation, maintenance and inspection activities. [5][6][7][25]

Are farm ponds exempt from federal permits?

Only from certain Clean Water Act requirements, and only if the exemption's conditions are met. The Act says a discharge of dredged or fill material for the construction or maintenance of farm or stock ponds is not prohibited by or otherwise subject to regulation under Section 404 or sections 301(a) or 402, except for section 307 effluent standards or prohibitions and except as its recapture paragraph, 404(f)(2), provides. Under Corps regulations a permit is still required if the discharge contains a toxic pollutant listed under section 307, or if it is part of an activity whose purpose is to convert an area of waters of the United States to a use to which it was not previously subject, where flow or circulation may be impaired or reach reduced. EPA says both conditions must be met for an otherwise exempt activity to lose its exemption this way: the activity represents a new use of the water, and it would reduce the reach or impair the flow or circulation of regulated waters, including wetlands. Farm ponds that lose the exemption because of recapture may be authorized by Nationwide Permit 40, which covers farm ponds in non-tidal waters of the United States, excluding perennial streams, provided the pond is used solely for agricultural purposes; the discharge must not cause the loss of more than 1/2 acre of non-tidal waters of the United States, and a pre-construction notification to the district engineer is required before work starts. The current nationwide permits took effect March 15, 2026 and expire March 15, 2031. EPA directs people to their local Corps District office or EPA regional office to find out whether a specific activity is exempt. State rules can also apply: in Pennsylvania, for example, DEP says Chapter 102 erosion and sediment control requirements apply whether or not the pond work needs Chapter 105 authorization, and for construction such as pond excavation the Chapter 102 regulation requires erosion and sediment control best management practices even for disturbance under 5,000 square feet. [1][9][10][23][24][26]

Do I need a permit if the pond is not near a stream?

Not necessarily a Section 404 permit, but other permits can still apply. Corps regulations say an activity that takes place outside waters of the United States, or that does not involve a discharge, does not need a Section 404 permit. According to EPA's rule status page (last updated September 9, 2026), EPA and the Army are implementing the Amended 2023 Rule in 24 states, including Pennsylvania, plus the District of Columbia and the U.S. territories; under that rule, artificial lakes or ponds created by excavating or diking dry land to collect and retain water, and used exclusively for purposes such as stock watering, irrigation, settling basins or rice growing, are not waters of the United States, even where they would otherwise meet paragraphs (a)(2) through (5) of the rule's definition. In the other 26 states, EPA and the Army interpret waters of the United States consistent with the pre-2015 regulatory regime and the Supreme Court's Sackett decision until further notice. The pre-2015 rules do not codify that exclusion; in the 2023 rule's preamble, the agencies say such ponds were generally not considered waters of the United States, although the Corps and EPA each reserved the right to find, case by case, that a particular one is a water of the United States. Construction stormwater rules are separate: EPA's Construction General Permit guidance says coverage is generally needed when construction disturbs 1 acre or more and discharges stormwater to waters of the U.S., and that no permit is needed if all of the construction stormwater is captured on site and not discharged to a receiving water, with on-site controls that are effective under any size storm. State rules can also apply. In Pennsylvania, for example, DEP says Chapter 105 approval for water obstructions and encroachments is not required for an off-stream pond that is not built in a floodway, wetland or other body of water, but a dam permit may be required if its dam meets the regulated-dam criteria. Under Chapter 105, a water-storage dam that is not on a watercourse and has no contributory drainage is regulated only if the greatest depth of water at its upstream toe exceeds 15 feet and its impounding capacity exceeds 50 acre-feet, both at maximum storage elevation. [1][7][23][27][28][29][30]

Does building a pond need an erosion control or stormwater permit?

It can, depending on how much ground the work disturbs and which state the pond is in. EPA says a Clean Water Act permit is required for stormwater discharges from construction activity, including clearing, grading and excavating, that disturbs 1 acre or more, or less than 1 acre if it is part of a common plan of development or sale that will ultimately disturb 1 acre or more. EPA's Construction General Permit guidance adds that the earth disturbance has to be part of a project to build, demolish or replace a structure to trigger permit coverage (its examples are a building, road, pad, pipeline or transmission line), and that where clearing, grading or excavating down to bare soil takes place, coverage is required if at least one acre is disturbed, separately or as part of a larger plan of development. The same guidance says no permit is needed if all of the construction stormwater is captured on site and not discharged to a receiving water, with on-site controls that are effective under any size storm; if there is a potential for a discharge, EPA recommends obtaining coverage before any discharge occurs. According to EPA's August 3, 2026 notice on its draft 2027 Construction General Permit, EPA itself is the construction stormwater permitting authority in places including Massachusetts, New Hampshire, New Mexico, the District of Columbia and most Indian country lands. A state can run its own EPA-approved NPDES permit program. State erosion rules can reach smaller jobs. For construction such as pond excavation or embankment work, Pennsylvania, for example, requires erosion and sediment control best management practices even for disturbance under 5,000 square feet, and a written erosion and sediment control plan when disturbance will be 5,000 square feet or more or, among other listed cases, when the activity, because of its proximity to existing drainage features or patterns, has the potential to discharge to a High Quality or Exceptional Value water. Other than for agricultural plowing or tilling, animal heavy use areas, timber harvesting or road maintenance, Pennsylvania also requires an individual NPDES permit or coverage under a general NPDES permit before earth disturbance of 1 acre or more begins, including earth disturbance that is part of a larger common plan of development or sale involving 1 acre or more. [2][11][12][24][30][31]

Does a pond in a floodplain need a permit?

Where the work is in a Special Flood Hazard Area, FEMA says a permit is required before construction or development begins, and the National Flood Insurance Program (NFIP) counts dredging, filling, grading and excavation as development. A Special Flood Hazard Area is the land subject to a 1 percent or greater chance of flooding in any given year. State and local governments enforce the NFIP rules, and participation in the NFIP is voluntary; FEMA's Community Status Book shows whether a community participates, does not participate, or is suspended or sanctioned. Inside an adopted regulatory floodway, the community must prohibit fill and other encroachments unless hydrologic and hydraulic analyses, performed in accordance with standard engineering practice, show they would not result in any increase in flood levels within the community during the base flood discharge. A community may permit a floodway encroachment that would increase base flood elevations only if it first applies for a conditional Flood Insurance Rate Map (FIRM) and floodway revision, meets the requirements of 44 CFR 65.12, and receives FEMA approval. FEMA's criteria are minimums that any community may exceed, so the details depend on the state and the community; Pennsylvania's floodplain development guide (PEMA, June 2025), for example, says the municipality must issue a floodplain development permit, or its equivalent, before any development in the Special Flood Hazard Area. [3][4][14][15][16][32][33]

What is the NRCS pond standard?

Conservation Practice Standard Pond (Code 378) is the Natural Resources Conservation Service's design standard for a pond, which NRCS defines as a water impoundment made by building an embankment, digging a dugout, or both. It applies to all excavated ponds, but to embankment ponds only if they meet all of its low-hazard criteria, including storage times effective height of less than 3,000 acre-feet times feet and an effective height of 35 feet or less. NRCS policy instead requires low-hazard earth dams with storage times effective height of 3,000 acre-feet times feet or more, dams more than 35 feet in effective height, and all significant- and high-hazard dams to meet or exceed Technical Release 210-60. The standard itself requires ponds to be planned, designed and built to comply with all Federal, State and local laws, and requires the landowner to obtain all necessary permits before construction. NRCS's national page lists the standard document as July 2022 but says national standards should not be used to plan, design or install a practice; each state adapts them in its Field Office Technical Guide, and state versions may be more restrictive but cannot be less stringent. As of September 28, 2026, Pennsylvania's active version, for example, is dated October 2023. [18][19][20][21][34][35][36]

Sources

Every statement above links to one of these official sources. Expand “Show the source text” under any statement to read the exact passage it rests on.

  1. 33 CFR Part 323 - Permits for Discharges of Dredged or Fill Material into Waters of the United States (opens in a new tab) — eCFR (Office of the Federal Register), document date current eCFR text; 323.2 last amended 73 FR 79645, Dec. 30, 2008, retrieved September 28, 2026
  2. Stormwater Discharges from Construction Activities (opens in a new tab) — U.S. EPA, document date Last updated August 10, 2026, retrieved September 28, 2026
  3. Permit for Floodplain Development (FEMA glossary) (opens in a new tab) — FEMA, document date Last updated July 8, 2020, retrieved September 28, 2026
  4. 44 CFR Part 59 - General Provisions (NFIP) (opens in a new tab) — eCFR (Office of the Federal Register / GPO), document date eCFR current text; Title 44 up to date as of 2026-09-24; § 59.1 source 41 FR 46968 (Oct. 26, 1976), as amended, retrieved September 28, 2026
  5. National Inventory of Dams - Mission & History (opens in a new tab) — U.S. Army Corps of Engineers, retrieved September 28, 2026
  6. National Inventory of Dams Data Dictionary (listed on NID Reference Documents as "NID Data Dictionary June 2025") (opens in a new tab) — U.S. Army Corps of Engineers, document date Document dated August 2024; uploaded to NID June/July 2025, retrieved September 28, 2026
  7. 25 Pa. Code § 105.3 (Scope) (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date Code current through 56 Pa.B. 4026 (July 4, 2026); § 105.3 last amended eff. Oct. 12, 1991, retrieved September 28, 2026
  8. Tribal and State Section 404 Assumption Efforts (opens in a new tab) — U.S. Environmental Protection Agency, document date Last updated August 14, 2026, retrieved September 28, 2026
  9. 33 U.S.C. 1344 - Permits for dredged or fill material (CWA section 404) (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, document date Text contains laws in effect on September 27, 2026, retrieved September 28, 2026
  10. Reissuance and Modification of Nationwide Permits (final rule), FR Doc. 2026-00121 (opens in a new tab) — Federal Register / U.S. Army Corps of Engineers, document date 2026-01-08; effective 2026-03-15; expires 2031-03-15, retrieved September 28, 2026
  11. NPDES 2027 Issuance of General Permit for Stormwater Discharges From Construction Activities - Notice; request for public comment (91 FR 48862, Aug. 3, 2026) (opens in a new tab) — U.S. EPA / Federal Register, document date 2026-08-03, retrieved September 28, 2026
  12. 33 U.S.C. 1342 - National pollutant discharge elimination system (CWA section 402) (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, retrieved September 28, 2026
  13. NPDES State Program Authority (opens in a new tab) — U.S. EPA, document date Last updated August 17, 2026, retrieved September 28, 2026
  14. Individuals - Floodplain Management Resources (opens in a new tab) — FEMA, document date Last updated October 2, 2024, retrieved September 28, 2026
  15. 44 CFR Part 60 - Criteria for Land Management and Use (opens in a new tab) — eCFR (Office of the Federal Register / GPO), document date eCFR current text; Title 44 up to date as of 2026-09-24; § 60.3 source 41 FR 46975 (Oct. 26, 1976), as amended, retrieved September 28, 2026
  16. Local Government Officials - Floodplain Management Resources (opens in a new tab) — FEMA, document date Last updated August 28, 2024, retrieved September 28, 2026
  17. Federal Guidelines for Dam Safety (FEMA P-93) (opens in a new tab) — FEMA / Interagency Committee on Dam Safety, document date December 2023, retrieved September 28, 2026
  18. National Engineering Manual (Title 210), Part 520, Subpart C - Dams (opens in a new tab) — USDA Natural Resources Conservation Service (eDirectives), document date 210-520-M, 4th Ed., June 2017, retrieved September 28, 2026
  19. NRCS Conservation Practice Standard, Pond (Code 378), national (NHCP) version (opens in a new tab) — USDA Natural Resources Conservation Service, document date July 2022, retrieved September 28, 2026
  20. Pond (No.) (378) Conservation Practice Standard (national page with state FOTG links) (opens in a new tab) — USDA Natural Resources Conservation Service, document date Lists standard dated 7/2022; page says "Updated in 2026", retrieved September 28, 2026
  21. Conservation Practice Standards | Natural Resources Conservation Service (opens in a new tab) — USDA NRCS, retrieved September 28, 2026
  22. 7 CFR part 1466 - Environmental Quality Incentives Program (eCFR current) (opens in a new tab) — eCFR / Office of the Federal Register, document date current eCFR text; 84 FR 69280 (Dec. 17, 2019), as amended 85 FR 67647 (Oct. 26, 2020), retrieved September 28, 2026
  23. Introduction to Ponds and Chapter 105 (opens in a new tab) — Pennsylvania Department of Environmental Protection, retrieved September 28, 2026
  24. 25 Pa. Code § 102.4. Erosion and sediment control requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
  25. Dam Awareness (fact sheet) (opens in a new tab) — FEMA, document date May 2018, retrieved September 28, 2026
  26. Exemptions to Permit Requirements under CWA Section 404 (opens in a new tab) — U.S. Environmental Protection Agency, document date Last updated March 10, 2026, retrieved September 28, 2026
  27. Definition of "Waters of the United States": Rule Status and Litigation Update (last updated September 9, 2026) (opens in a new tab) — U.S. Environmental Protection Agency, document date 2026-09-09, retrieved September 28, 2026
  28. 33 CFR 328.3 - Definitions (waters of the United States) (eCFR, current; 88 FR 3142, Jan. 18, 2023, as amended at 88 FR 61968, Sept. 8, 2023) (opens in a new tab) — eCFR / Office of the Federal Register, document date 2023-09-08, retrieved September 28, 2026
  29. Revised Definition of "Waters of the United States," 88 FR 3004 (Jan. 18, 2023), FR Doc. 2022-28595 (opens in a new tab) — Federal Register (govinfo), document date 2023-01-18, retrieved September 28, 2026
  30. Frequent Questions on EPA's Construction General Permit (updated for the 2022 CGP) (opens in a new tab) — U.S. EPA, document date 2022, retrieved September 28, 2026
  31. 25 Pa. Code § 102.5. Permit requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
  32. Community Status Book (opens in a new tab) — FEMA, document date Last updated April 8, 2026, retrieved September 28, 2026
  33. Pennsylvania Floodplain Development Guide (June 2025) (opens in a new tab) — Pennsylvania Emergency Management Agency (PEMA), document date June 2025, retrieved September 28, 2026
  34. eFOTG Pennsylvania - Pond (378) folder document listing (API listByFolderAll, folderId -173) (opens in a new tab) — USDA NRCS eFOTG, document date retrieved 2026-09-28, retrieved September 28, 2026
  35. eFOTG Pennsylvania - folder menu (API stateFolder/getMenu/42) (opens in a new tab) — USDA NRCS eFOTG, document date retrieved 2026-09-28, retrieved September 28, 2026
  36. NRCS Pennsylvania Conservation Practice Standard, Pond (Code 378) (opens in a new tab) — USDA NRCS Pennsylvania (eFOTG), document date October 2023, retrieved September 28, 2026

This is not legal advice. It is a plain-English summary of official sources. Laws, permits and agency practice change, and how they apply depends on your exact site. Confirm with the agencies named here, and with a licensed professional engineer for any dam, before you build.

Planning a pond?

Talk it through with a Natural Waterscapes pond expert before you break ground. We can help you size the project so it fits the permits you can realistically get.