Repairing, Sealing or Draining a Pond: Federal Rules and NRCS Standards

Sources checked September 28, 2026

EPA says many Clean Water Act programs apply only to "waters of the United States." The Act makes the discharge of any pollutant unlawful except in compliance with its listed sections, including section 402 (NPDES) and section 404 (dredged or fill material), and defines a "discharge of a pollutant" as any addition of any pollutant to navigable waters (defined as the waters of the United States, including the territorial seas) from any point source. Corps regulations require a Department of the Army permit for discharges of dredged or fill material into waters of the United States except those exempted by 33 CFR 323.4. Certain discharges are permitted by nationwide permits, others may be authorized by regional permits, and a discharge that is neither exempt nor covered by a nationwide permit needs an individual or regional section 404 permit. [1][2][3][4]

As of EPA's page last updated September 9, 2026, the agencies implement the January 2023 rule defining "waters of the United States", as amended by the conforming rule, in 24 states, the District of Columbia and the U.S. Territories, and in the other 26 states interpret the term consistent with the pre-2015 regulatory regime and the Supreme Court's Sackett decision; an updated definition has only been proposed (November 2025, supplemented September 9, 2026). Where the amended 2023 rule applies, artificial ponds created by excavating or diking dry land to collect and retain water and used exclusively for such purposes as stock watering, irrigation, settling basins or rice growing are not waters of the United States, but the exclusion does not cover impoundments of waters of the United States, such as a pond made by damming a jurisdictional stream. Describing the pre-2015 regulatory regime, which the agencies apply consistent with Sackett in the other 26 states, the 2023 preamble says such ponds were "generally not considered" waters of the United States, but that the Corps reserved the right to decide case by case that a particular one is. [1][5][6]

The agencies' 2023 preamble addresses such a pond that is initially used exclusively for one of those purposes and later used for a different purpose: a previously excluded feature that no longer meets the terms of the exclusion is no longer excluded, and it would be jurisdictional if it otherwise meets the definition. The same preamble notes that artificial lakes and ponds are often used for more than one purpose and can have other beneficial purposes, such as animal habitat, water retention or recreation, and says the agencies' historic practice, which they intend to continue, is to treat these ponds as excluded even when there is another incidental beneficial use. [6]

For draining, the Corps' Regulatory Guidance Letter (RGL) 05-04 (August 19, 2005) says that, as a general rule, discharging substantial quantities of accumulated bottom sediment from or through a dam into downstream waters is a discharge of dredged material (and possibly fill material) that requires a section 404 permit and will rarely, if ever, qualify for the 404(f) exemption. The same guidance lists "the lowering of lake or pond levels that results in the release of only de minimis amounts of sediment" among actions that are not usually considered regulated discharges of dredged material and do not require Department of the Army permits, and it does not set a specific amount of sediment that is de minimis. [7]

In Greenfield Mills v. Macklin (2004), where Indiana DNR employees drained a 1.75-acre supply pond formed by damming the Fawn River, the Seventh Circuit held that dredged material released from the pond into the river was an "addition" of dredged spoil, so the defendants' actions were subject to the section 404 permit requirement unless an exemption applied. For the water itself, EPA's 2008 preamble to its Water Transfers Rule says releasing water from a reservoir through a dam into the river below (in EPA's example, the water on both sides of the dam is part of the same water of the United States) needs no NPDES permit, because EPA and the federal courts have determined that a discharge from a dam is not an "addition" of a pollutant unless the dam itself discharges a pollutant such as grease (EPA adds that section 401 certification may be needed in some instances). Whether draining a pond that is not itself a water of the United States, or pumping water out of a pond that is one into a different water (for example, with a temporary pump), needs NPDES coverage is listed as not confirmed under draining, below. [8][9]

For sealing or lining, the Corps' definition of "discharge of fill material" mentions a liner only as infrastructure for solid waste landfills, while "fill material" is defined by its effect (replacing any portion of a water with dry land or changing its bottom elevation) with examples that include soil, clay and plastics; whether sealing or lining a pond is a section 404 discharge is listed below as not confirmed. The statute exempts discharges of dredged or fill material for the construction or maintenance of farm or stock ponds from regulation under sections 404, 301(a) and 402, except for effluent standards or prohibitions under section 307 and unless recaptured under section 404(f)(2); EPA tells people to contact their local Corps district office or EPA regional office to find out whether specific activities are exempt. [4][10][11]

As retrieved September 28, 2026, NRCS's national practice standards index lists three pond sealing or lining standards, Codes 520 (compacted soil treatment), 521 (geomembrane or geosynthetic clay liner) and 522 (concrete), with version dates given below. On September 1, 2026 NRCS proposed revising 520 and 522 (Docket NRCS-2026-0100) and will consider comments received by October 1, 2026; the revisions are proposed, not final. [12][13]

Key points

  • ProcessEPA says many Clean Water Act programs apply only to 'waters of the United States'. As of its page last updated September 9, 2026, EPA says the agencies are implementing the January 2023 rule, as amended by the conforming rule, in 24 states, the District of Columbia, and the U.S. Territories, and in the other 26 states are interpreting 'waters of the United States' consistent with the pre-2015 regulatory regime and the Supreme Court's decision in Sackett. On September 9, 2026 the agencies published a supplemental notice of proposed rulemaking for an updated definition of 'waters of the United States', supplementing their November 2025 proposal (proposed only; not in effect).

    EPA, About Waters of the United States (last updated Sept. 9, 2026), introductory notice and 'What are' / 'Current Implementation' sections [1]
    Show the source text
    On September 9, 2026, ... published a supplemental notice of proposed rulemaking for the Updated Definition of "Waters of the United States." The notice supplements the agencies' November 2025 proposal. ... Many Clean Water Act programs apply only to “waters of the United States.” ... implementing the January 2023 Rule, as amended by the conforming rule, in 24 states, the District of Columbia, and the U.S. Territories. In the other 26 states, the agencies are interpreting "waters of the United States" consistent with the pre-2015 regulatory regime and the Supreme Court's decision in Sackett
    Open U.S. EPA (opens in a new tab)
  • ExemptionWhere the Amended 2023 Rule applies, 'artificial lakes or ponds created by excavating or diking dry land to collect and retain water and which are used exclusively for such purposes as stock watering, irrigation, settling basins, or rice growing' are not waters of the United States even if they would otherwise meet paragraphs (a)(2) through (a)(5) of the definition. Also excluded are artificial reflecting or swimming pools or other small ornamental bodies of water created by excavating or diking dry land to retain water for primarily aesthetic reasons.

    Applies when: States where the agencies implement the Amended 2023 Rule (24 states, the District of Columbia and the U.S. Territories per EPA's About WOTUS page, claim 051); in the other 26 states the agencies interpret 'waters of the United States' consistent with the pre-2015 regime and Sackett. 33 CFR 328.3(b)(5)-(6) (88 FR 3142, Jan. 18, 2023, as amended 88 FR 61968, Sept. 8, 2023) [5]
    Show the source text
    (b) The following are not “waters of the United States” even where they otherwise meet the terms of paragraphs (a)(2) through (5) of this section: ... (5) Artificial lakes or ponds created by excavating or diking dry land to collect and retain water and which are used exclusively for such purposes as stock watering, irrigation, settling basins, or rice growing; (6) Artificial reflecting or swimming pools or other small ornamental bodies of water created by excavating or diking dry land to retain water for primarily aesthetic reasons;
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • The artificial lakes and ponds exclusion applies only to features excavated in dry land or diked in dry land; paragraph (a)(2) impoundments of waters of the United States (e.g., a pond made by damming a jurisdictional stream) are not covered. Ponds that satisfy the exclusion are not jurisdictional even if they have a hydrologic surface connection to waters of the United States, and non-jurisdictional conveyances created in dry land that are physically connected to and part of the excluded feature remain excluded.

    Applies when: Relevant to embankment ponds built across a drainage: an on-stream impoundment of a jurisdictional water is not an excluded artificial pond. 88 FR 3004, 3116 (Jan. 18, 2023) (preamble) [6]
    Show the source text
    Paragraph (a)(2) impoundments are not covered under this exclusion. This exclusion only applies to features that were excavated in dry land or were diked in dry land. Paragraph (a)(2) impoundments are not excavated in dry land or diked in dry land. ... Artificial lakes and ponds that satisfy the terms of the exclusion would not be jurisdictional under this rule even if they have a hydrologic surface connection to ``waters of the United States.'' Non-jurisdictional conveyances created in dry land that are physically connected to and are a part of the excluded feature remain excluded.
    Open Federal Register (govinfo) (opens in a new tab)
  • StatusThe 2023 preamble says that under the pre-2015 regulatory regime, the features it lists, including artificial ponds dug or diked in dry land and used exclusively for stock watering, irrigation, settling basins or rice growing, were 'generally not considered' waters of the United States, but the Corps reserved the right to decide on a case-by-case basis that a particular waterbody in these categories is a water of the United States. The 2023 rule codified the exclusions and removed that case-by-case possibility (only where the 2023 rule is operative).

    Applies when: Background for the 26 states where the agencies interpret 'waters of the United States' consistent with the pre-2015 regime and Sackett (EPA's About WOTUS page, claim 051); the removal of case-by-case review applies only where the 2023 rule is implemented. 88 FR 3004, 3111 (Jan. 18, 2023) (preamble, describing 51 FR 41217, Nov. 13, 1986) [6]
    Show the source text
    artificial lakes or ponds created by excavating or diking dry land ... used exclusively for such purposes as stock watering, irrigation, settling basins, or rice growing; ... Under the pre-2015 regulatory regime, the features listed above were generally not considered ``waters of the United States'' ... the Corps reserves the right on a case-by-case basis to determine that a particular waterbody within these categories of waters is a water of the United States. ... removing the possibility that these waters could be found jurisdictional on a case-by-case basis.
    Open Federal Register (govinfo) (opens in a new tab)
  • StatusWhen excluded status ends: the agencies' 2023 rule preamble says that if an artificial pond excavated to collect and retain water is initially used exclusively for stock watering, irrigation, settling basins, or rice growing but is later used for a different purpose, then, consistent with longstanding practice, a previously excluded feature that no longer meets the terms of the exclusion is no longer excluded, and it would be jurisdictional if it otherwise meets the definition of 'waters of the United States'.

    88 FR 3004, 3116 (Jan. 18, 2023) (preamble, sec. IV.C.7.b(3) Implementation) [6]
    Show the source text
    if an artificial pond created by excavating land to collect and retain water is initially used exclusively for stock watering, irrigation, settling basins, or rice growing but is subsequently used for a different purpose, ... Consistent with the agencies' longstanding practice, if a previously excluded feature no longer meets the terms of the exclusion, it is no longer excluded. If it no longer satisfies the terms of an exclusion, it would be jurisdictional if it otherwise meets the definition of ``waters of the United States'' under this rule.
    Open Federal Register (govinfo) (opens in a new tab)
  • RequirementExcept as in compliance with the listed Clean Water Act sections, including section 402 (33 U.S.C. 1342, NPDES) and section 404 (33 U.S.C. 1344, dredged or fill material), the discharge of any pollutant by any person is unlawful.

    33 U.S.C. 1311(a) [2]
    Show the source text
    Except as in compliance with this section and sections 1312, 1316, 1317, 1328, 1342, and 1344 of this title, the discharge of any pollutant by any person shall be unlawful.
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • ProcessExcept as provided in 33 CFR 323.4 (discharges not requiring permits), Department of the Army permits are required for discharges of dredged or fill material into waters of the United States. Certain discharges are permitted by the nationwide permits in 33 CFR part 330, others may be authorized by district or division engineers on a regional basis (regional permits), and a discharge that is neither exempted by 323.4 nor permitted by part 330 requires an individual or regional section 404 permit.

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. 33 CFR 323.3(a) [4]
    Show the source text
    (a) General. Except as provided in § 323.4 of this part, DA permits will be required for the discharge of dredged or fill material into waters of the United States. Certain discharges specified in 33 CFR part 330 are permitted by that regulation (“nationwide permits”). Other discharges may be authorized by district or division engineers on a regional basis (“regional permits”). If a discharge of dredged or fill material is not exempted by § 323.4 of this part or permitted by 33 CFR part 330, an individual or regional section 404 permit will be required
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • RequirementRGL 05-04 policy: as a general rule, discharging substantial quantities of accumulated bottom sediment from or through a dam into downstream waters is a discharge of dredged material (and possibly fill material) that requires a CWA section 404 permit, and will rarely, if ever, qualify for the 404(f) exemption; a Section 10 (Rivers and Harbors Act) permit may also be required in navigable waters of the United States, where no statutory exemptions apply.

    USACE RGL 05-04 (Aug. 19, 2005), para. 4.a [7]
    Show the source text
    As a general rule, the discharge of substantial quantities of accumulated bottom sediment from or through a dam into downstream waters constitutes a discharge of dredged material (and possibly of fill material) that requires a CWA Section 404 permit. The discharge of substantial quantities of sediment through a dam will rarely, if ever, qualify as exempt under 404(f). Such activities may also require a DA Section 10 permit if they occur in “navigable waters of the United States”, and no statutory exemptions apply to Section 10 for such discharges into navigable waters.
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • ExemptionRGL 05-04 lists activities that are not usually considered regulated discharges of dredged material and do not require DA permits, including: operation of continuously sluicing structures that mimic the natural increase and decrease of sediment in a stream (sediment discharged comparable to the amount entering the reservoir from upstream); breaching or removal of a dam that moves only de minimis amounts of material or results solely from an act of nature; releases during high water or flood stages to pass flood waters; and 'the lowering of lake or pond levels that results in the release of only de minimis amounts of sediment.' The RGL does not set a specific amount of sediment that is de minimis.

    Applies when: Pond drawdowns that release only de minimis sediment USACE RGL 05-04 (Aug. 19, 2005), para. 4.b [7]
    Show the source text
    not usually considered regulated discharges of dredged material and do not require DA permits include actions such as the operation of continuously sluicing structures that mimic the natural increase and decrease of sediment in a stream ... comparable to the amount of material entering the reservoir from upstream); breaching or removal of a dam that results in the movement of only de minimis amounts of material ... flood stages ... the lowering of lake or pond levels that results in the release of only de minimis amounts of sediment. ... not propose to set a specific amount of sediment
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • ExemptionClean Water Act section 404(f)(1)(C) provides that the discharge of dredged or fill material for the purpose of construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance of drainage ditches, is not prohibited by or otherwise subject to regulation under section 404, section 301(a) or section 402 (except for effluent standards or prohibitions under section 307), unless recaptured under section 404(f)(2).

    Applies when: Farm or stock ponds that are waters of the United States (an excluded pond needs no exemption). 33 U.S.C. 1344(f)(1)(C) and closing text [10]
    Show the source text
    (1) Except as provided in paragraph (2) of this subsection, the discharge of dredged or fill material- ... (C) for the purpose of construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance of drainage ditches; ... is not prohibited by or otherwise subject to regulation under this section or section 1311(a) or 1342 of this title (except for effluent standards or prohibitions under section 1317 of this title).
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • AgencyEPA's section 404 exemptions page lists 'construction and maintenance of farm or stock ponds' and 'maintenance of structures such as dams, dikes, and levees' among activities exempt under section 404(f)(1), and explains that if an activity listed as exempt represents a new use of the water and the activity would result in a reduction in reach or impairment of flow or circulation of regulated waters, including wetlands, the activity is not exempt; both conditions must be met for the activity to be considered non-exempt. It directs people to their local Corps district office or EPA regional office to find out whether specific activities are exempt.

    EPA, Exemptions to Permit Requirements under CWA Section 404 (last updated March 10, 2026) [11]
    Show the source text
    Construction and maintenance of farm or stock ponds ... Maintenance of structures such as dams, dikes, and levees ... If an activity listed above as exempt represents a new use of the water, and the activity would result in a reduction in reach or impairment of flow or circulation of regulated waters, including wetlands, the activity is not exempt. Both conditions must be met in order for the activity to be considered non-exempt. ... To find out whether specific activities are exempt, contact your local U.S. Army Corps District office or EPA regional office.
    Open U.S. Environmental Protection Agency (opens in a new tab)

Draining or drawing down a pond

RGL 05-04 tells Corps districts which sediment releases through dams need Department of the Army permits, and the "dams" it covers include barriers that create impoundments of water. It is not intended to require a permit for routine high-water-flow dam operations that let sediment-laden water flow from or through a dam, and it treats sediment released incidentally to normal dam operations (its examples include releasing water through the dam to provide irrigation or drinking water) as de minimis, generally not triggering a permit so long as it is consistent with the sediment loads entering the reservoir; deviations from normal operations that discharge bottom sediment may require a permit. In deciding whether a release is de minimis or exempt as dam maintenance, the RGL says district engineers should consider whether the discharge is necessary for dam maintenance and proportional to the activity and the size of the facility, along with factors that include the time of year, the intended release volume, the speed of the drawdown and the potential for environmental harm. [7]

The RGL says opening a dam's lower gates so that substantial quantities of sediment travel downstream is a discharge of dredged material (and possibly fill material) from a point source requiring a permit regardless of whether the operator intended to discharge sediment, and that sediment releases raising the bottom elevation of downstream waters to a discernible, substantial degree generally require permits. Section 404(f)(1) exempts discharges of dredged or fill material for maintenance of currently serviceable structures such as dikes and dams from regulation under sections 404, 301(a) and 402, except for effluent standards or prohibitions under section 307 and unless recaptured under section 404(f)(2). On that dam-maintenance exemption, the RGL says sediment released through a dam can be exempt only if it must be released for the purpose of dam maintenance, "and not for any other purpose such as maintenance of the reservoir pool," and only if the release is both necessary for essential dam maintenance and proportional to it; the Corps' regulation on the exemption says maintenance does not include any modification that changes the character, scope or size of the original fill design. In Greenfield Mills the Seventh Circuit said the discharger bears the burden of proving both that a 404(f)(1) exemption applies and that the activity is not recaptured, and read the dam-maintenance exemption to cover only dredging that is reasonably necessary to the proposed maintenance. [4][7][8][10]

For releases that need authorization, the RGL describes these routes: district engineers may, case by case, consider it an emergency, subject to the emergency permitting procedures at 33 CFR 325.2(e)(1), to lower a reservoir through one or more flood gates (with the resulting downstream discharge of dredged material) to avoid potential catastrophic dam failure; sluicing less than 25 cubic yards of material through a dam may be authorized under Nationwide Permit (NWP) 18 if all its other conditions are met; and districts may consider developing regional general permits for larger amounts of sediment. The 2026 NWP 18 (the 2026 nationwide permits took effect March 15, 2026 and expire March 15, 2031) authorizes minor discharges where the discharged material and the volume excavated do not exceed 25 cubic yards below the ordinary high water mark, the loss of waters of the United States does not exceed 1/10 acre and the material is not placed for a stream diversion, and it requires a pre-construction notification if the discharge or the excavated volume exceeds 10 cubic yards or the discharge is in a special aquatic site, including wetlands. The 2026 NWP 3 (maintenance) also authorizes removing accumulated sediment and debris within, and in the immediate vicinity of, a previously authorized, currently serviceable structure or fill being maintained. [7][14]

The RGL lists reasonable measures to reduce downstream harm, including dewatering beforehand by pumping or by releasing water from upper control structures, mechanically dredging or excavating the sediment with appropriate disposal, timing releases to coincide with high water for dilution, more frequent flushing to keep discharges small, releasing an amount of sediment that depends on the amount of water flow, and temporary barriers to keep exposed sediment from washing out in later storms. For work authorized by a 2026 nationwide permit, the general conditions require appropriate soil erosion and sediment controls, do not authorize activities that physically destroy an important spawning area (for example by downstream smothering with substantial turbidity), and encourage work during low-flow or no-flow periods; they are general conditions, not drawdown-rate standards. [7][14]

EPA's Water Transfers Rule (40 CFR 122.3(i), effective August 12, 2008) says discharges from an activity that conveys or connects waters of the United States without subjecting the water to an intervening industrial, municipal or commercial use do not require NPDES permits, except for pollutants the transfer activity itself introduces. EPA's preamble says the release through a dam described above is not a water transfer, because the water on both sides of the dam is part of the same water of the United States (it needs no NPDES permit for the separate reason given above), and that conveying water that is not a water of the United States before it is discharged is also not a "water transfer." EPA said nothing in the rule stops a state from regulating, under state law, water transfers not subject to section 402, and reported in 2008 that Pennsylvania was the only NPDES permitting authority that regularly issued NPDES permits for water transfers. [9][15]

EPA's 2022 Construction General Permit (CGP), as modified, expires at 11:59 pm on February 16, 2027. Its eligibility conditions include disturbing one or more acres (or less than one acre as part of a common plan of development or sale that will ultimately disturb one or more acres) or being designated by EPA as needing coverage, and being in an area where EPA is the permitting authority. Where a site is covered, dewatering water must be routed through a sediment control designed to prevent discharges with visual turbidity. Sites discharging dewatering water to "sensitive waters" (such as waters impaired for sediment or a sediment-related parameter) must take at least one turbidity sample each day a discharge occurs and compare the weekly average to the standard 50 NTU benchmark (or an alternate benchmark EPA has approved); EPA says the benchmark is not an effluent limitation. The permit defines dewatering as draining accumulated stormwater and/or ground water from building foundations, vaults, trenches or similar points of accumulation, with examples that include water pumped from sediment basins or similar impoundments for maintenance or decommissioning; the definition does not mention draining an existing pond or lake. EPA's proposed 2027 CGP, which is not final, would keep the same dewatering definition. [16][17][18]

Official sources disagree

  • RGL 05-04 (August 19, 2005) says sluicing "less than 25 cubic yards" of material through a dam may be authorized under Nationwide Permit 18 if all its other conditions are met. The 2026 NWP 18 described above is worded differently: the discharged material and the excavated volume must not exceed 25 cubic yards below the ordinary high water mark, and the permit carries its own 1/10-acre loss limit and pre-construction notification triggers. [7][14]
  • AgencyCorps Regulatory Guidance Letter 05-04 (Aug. 19, 2005), 'Guidance on the Discharge of Sediments From or Through a Dam and the Breaching of Dams', tells Corps districts which sediment releases through dams need Department of the Army permits. It does not require a permit for routine high-water-flow dam operations that let sediment-laden water pass, but deviations from normal dam operations resulting in the discharge of bottom sediment may require a DA permit. 'Dams' include barriers that create impoundments of water.

    USACE RGL 05-04 (Aug. 19, 2005), paras. 1.a-1.b [7]
    Show the source text
    Nothing in this guidance is intended to require a DA permit for routine high water flow dam operations that allow sediment-laden waters to flow from or through a dam; however deviations from normal dam operations resulting in the discharge of bottom sediment may require a DA permit. ... Dams, as used in this guidance include, but are not limited to, barriers that create impoundments of water.
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • Corps RGL 05-04 on water releases: the guidance says it is not intended to require a Department of the Army (DA) permit for routine high-water-flow dam operations that let sediment-laden water flow from or through a dam. Sediment released incidentally to normal dam operations (the RGL's examples include releasing water through the dam to provide irrigation or drinking water) is treated as de minimis and generally does not trigger a DA permit so long as it is consistent with the sediment loads entering the reservoir. Deviations from normal operations that discharge bottom sediment may require a DA permit.

    USACE RGL 05-04 (Aug. 19, 2005), paras. 1.a, 3.a [7]
    Show the source text
    Nothing in this guidance is intended to require a DA permit for routine high water flow dam operations ... however deviations from normal dam operations resulting in the discharge of bottom sediment may require a DA permit. ... the release of sediments that are incidental to normal dam operations (i.e., the release of water through the dam to provide irrigation water or drinking water ... are considered de minimis discharges of dredged material. ... generally do not trigger the need for a DA permit so long as they are consistent with those sediment loads entering the reservoir
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • RGL 05-04 sets no numeric drawdown rate or sediment amount: it states it does not propose a specific amount of sediment that is de minimis or 'more than de minimis'. In deciding whether a release is de minimis or exempt for dam maintenance, District Engineers should consider whether the discharge through the dam is necessary for dam maintenance and proportional to the proposed activity and the size of the facility, and other factors should include the time of year and normal seasonality of high-volume flows, the size of the incoming and outgoing stream/river and the intended release volume, the natural hydrograph, the speed of the drawdown, the normal amount of sediment in the watershed, and the potential for environmental harm.

    USACE RGL 05-04 (Aug. 19, 2005), para. 4.b [7]
    Show the source text
    does not propose to set a specific amount of sediment ... District Engineers should consider whether the discharge ... is necessary for dam maintenance, and proportional to the proposed activity and the size of the facility ... Other factors in this consideration should include the time of year and normal seasonality of high volume flows, the size of incoming and outgoing stream/river and the intended release volume, the natural hydrograph of the system, the speed of the drawdown, the normal amount of sediment in the watershed, and the potential for environmental harm.
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementRGL 05-04: opening a dam's lower gates so that substantial sediment travels downstream is a discharge of dredged material (and possibly fill) from a point source requiring a DA permit regardless of whether the operator intended to discharge sediment; and sediment releases that raise the bottom elevation of downstream waters to a discernible, substantial degree generally require permits as discharges of fill material.

    USACE RGL 05-04 (Aug. 19, 2005), paras. 2.e, 3.c [7]
    Show the source text
    DA permits are generally required for the discharge of sediments from dams when such activities would have the effect of raising the bottom elevation of the downstream waters to a discernible, substantial degree. ... Regardless of whether the dam operators had the intent to discharge sediment through the dam ... the opening of the lower gates of the dam has the effect of allowing substantial quantities of sediment material to travel downstream, thereby constituting the discharge of dredged material (and possibly fill material, as well) from a point source, thereby requiring a DA permit.
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementRGL 05-04 on the 404(f) dam-maintenance exemption: sediment released through a dam can be exempt only if it must be released for the purpose of dam maintenance - 'and not for any other purpose such as maintenance of the reservoir pool' - and the release must be both necessary for essential dam maintenance and proportional to it.

    USACE RGL 05-04 (Aug. 19, 2005), para. 3.b [7]
    Show the source text
    Consequently, the discharge of sediments through a dam cannot be exempted from CWA regulation under Subsection 404(f)(1) unless those sediments must be released for the purpose of dam maintenance, and not for any other purpose such as maintenance of the reservoir pool. ... such discharges of sediments through a dam would have to be both necessary to allow essential dam maintenance to occur, and would have to be proportional to the dam maintenance activities that necessitate the release of sediments.
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • ExemptionCorps regulation on the dam-maintenance exemption: maintenance (including emergency reconstruction of recently damaged parts) of currently serviceable structures such as dikes and dams does not include any modification that changes the character, scope, or size of the original fill design, and emergency reconstruction must occur within a reasonable period of time after the damage to qualify.

    33 CFR 323.4(a)(2) [4]
    Show the source text
    Maintenance, including emergency reconstruction of recently damaged parts, of currently serviceable structures such as dikes, dams, levees, groins, riprap, breakwaters, causeways, bridge abutments or approaches, and transportation structures. Maintenance does not include any modification that changes the character, scope, or size of the original fill design. Emergency reconstruction must occur within a reasonable period of time after damage occurs in order to qualify for this exemption.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • ProcessRGL 05-04 authorization routes: on a case-by-case basis, District Engineers may consider lowering a reservoir through one or more flood gates (and the resulting downstream discharge of dredged material) to avoid potential catastrophic dam failure to be an emergency subject to the emergency permitting procedures at 33 CFR 325.2(e)(1); sluicing less than 25 cubic yards of material through a dam may be authorized under Nationwide Permit 18 if all other conditions of that NWP are met; and districts may consider developing Regional General Permits for larger amounts of sediment.

    USACE RGL 05-04 (Aug. 19, 2005), para. 4.c [7]
    Show the source text
    On a case-by case basis, District Engineers may consider the need to reduce the level of the reservoir through one or more flood gates and the resultant discharge of dredged material downstream, to ... avoid potential catastrophic dam failure, to be an emergency subject to the emergency permitting procedures found at 33 CFR 325.2(e)(1). Sluicing through a dam of less than 25 cubic yards of material may be authorized under Nationwide Permit 18, if all other conditions of that nationwide permit are met. Districts may also consider developing Regional General Permits
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • Size cutoffCurrent Nationwide Permit 18 (Minor Discharges), 2026 NWPs: authorizes minor discharges of dredged or fill material into all waters of the United States if the discharged material and the volume excavated do not exceed 25 cubic yards below the ordinary high water mark, the loss of waters of the United States does not exceed 1/10 acre, and the material is not placed for stream diversion; a pre-construction notification is required if the discharge or excavation exceeds 10 cubic yards or is in a special aquatic site including wetlands.

    NWP 18 (2026), 91 FR 768, 862 (Jan. 8, 2026); DATES [14]
    Show the source text
    Minor discharges of dredged or fill material into all waters of the United States, provided ... (a) The quantity of discharged dredged or fill material and the volume of area excavated do not exceed 25 cubic yards below the plane of the ordinary high water mark ... will not cause the loss of more than \1/10\-acre of waters of the United States; and (c) ... not placed for the purpose of a stream diversion. ... or the volume of area excavated exceeds 10 cubic yards ... or (2) the discharge of dredged or fill material is in a special aquatic site, including wetlands.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessCurrent Nationwide Permit 3 (Maintenance), 2026: paragraph (a) also authorizes removal of accumulated sediment and debris within, and in the immediate vicinity of, the previously authorized, currently serviceable structure or fill being maintained. Paragraph (b) authorizes removal of accumulated sediments and debris outside the immediate vicinity of existing structures (the NWP's examples are bridges, culverted road crossings and water intake structures), limited to the minimum necessary to restore the waterway near the structure to its approximate as-built dimensions and no farther than 200 feet in any direction from the structure (the 200-foot limit does not apply to maintenance dredging of accumulated sediments blocking or restricting outfall and intake structures, or canals associated with them); dredged or excavated material must be deposited and retained in an area with no waters of the United States unless the district engineer specifically approves otherwise under separate authorization. Paragraph (b) work requires a pre-construction notification to the district engineer, which must include the original design capacities and configurations of the outfalls, intakes, small impoundments, and canals.

    NWP 3 (2026), 91 FR 768, 858-859 (Jan. 8, 2026) [14]
    Show the source text
    sediment and debris within, and in the immediate vicinity of, the structure or fill. ... removal of accumulated sediments and debris outside the immediate vicinity of existing structures (e.g., bridges, culverted road crossings, water intake structures, etc.). ... cannot extend farther than 200 feet in any direction from the structure. This 200 foot limit does not apply to maintenance dredging to remove accumulated sediments blocking or restricting outfall and intake structures ... unless otherwise specifically approved by the district engineer ... small impoundments, and canals.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementRGL 05-04 reasonable measures to reduce downstream harm when discharging sediment from or through a dam include prior dewatering by pumping or releasing water from the upper control structures; mechanical dredging or excavation of sediment with appropriate disposal; timing releases to coincide with high water for dilution; more frequent flushing to keep discharges small; releasing sediment in proportion to water flow; and temporary barriers to keep exposed sediments from washing out in later storms.

    USACE RGL 05-04 (Aug. 19, 2005), para. 4.d [7]
    Show the source text
    Reasonable measures include, but are not limited to, prior dewatering by pumping or by releasing water from the upper control structures on a reservoir; mechanical dredging or excavation of sediments and appropriate disposal; timing releases to coincide with high water periods for better dilution; more frequent flushing to keep the discharges small; releasing a sediment amount that is dependent on the amount of water flow; and installing temporary barriers to prevent exposed sediments from being transported by runoff from subsequent storm events.
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • ExemptionNPDES exclusion for water transfers: discharges from a 'water transfer' do not require NPDES permits. 'Water transfer' means an activity that conveys or connects waters of the United States without subjecting the transferred water to intervening industrial, municipal, or commercial use. Limit: the exclusion does not apply to pollutants introduced by the water transfer activity itself to the water being transferred. The eCFR amendment history for section 122.3 lists 73 FR 33708 (June 13, 2008), the Water Transfers Rule, which added paragraph (i).

    40 CFR 122.3(i) [15]
    Show the source text
    The following discharges do not require NPDES permits: ... (i) Discharges from a water transfer. Water transfer means an activity that conveys or connects waters of the United States without subjecting the transferred water to intervening industrial, municipal, or commercial use. This exclusion does not apply to pollutants introduced by the water transfer activity itself to the water being transferred. ... 73 FR 33708, June 13, 2008
    Open eCFR (opens in a new tab)
  • EPA's 2008 preamble dam example: releasing water from Reservoir A through a dam into River A is not a 'water transfer' because the water on both sides of the dam is part of the same water of the U.S. EPA adds (footnote 3) that the release would still not require an NPDES permit, because EPA and the federal courts have determined that a discharge from a dam does not result in an 'addition' of a pollutant unless the dam itself discharges a pollutant, such as grease, into the water passing through it (citing Gorsuch and Consumers Power). EPA also noted that CWA section 401 certification may be needed in some instances (citing S.D. Warren v. Maine Board of Environmental Protection).

    Applies when: Releasing water through a dam or outlet of an impoundment that is a water of the United States 73 FR 33697, 33699-33700 & n.3 (June 13, 2008) [9]
    Show the source text
    The first example is the release from Reservoir A to River A. This does not constitute a water transfer under EPA's definition because the water on both sides of the dam is part of the same water of the U.S. ... this release would still not require an NPDES permit because EPA and the Federal courts have determined that a discharge from a dam does not result in an ``addition'' of a pollutant unless the dam itself discharges a pollutant such as grease ... (Certification under CWA section 401 may be needed in some instances).
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • DefinitionEPA's 2008 preamble: to be a 'water transfer' (and so be exempt from NPDES), the water being conveyed must be a water of the U.S. before it is discharged to the receiving waterbody; if the conveyed water is not a water of the U.S. before discharge, the activity is not a water transfer under the rule. The water must also be conveyed from one water of the U.S. to another; conveyances within the same water of the U.S. are not water transfers, although EPA says movements of water within a single water body are also not subject to NPDES permitting.

    Applies when: Draining or pumping a pond into another water 73 FR 33697, 33699 (June 13, 2008), preamble sec. II [9]
    Show the source text
    If the water that is being conveyed is not a water of the U.S. prior to being discharged to the receiving body, then that activity does not constitute a water transfer under today's rule. Additionally, the water must be conveyed from one water of the U.S. to another water of the U.S. Conveyances that remain within the same water of the U.S., therefore, do not constitute water transfers under this rule, although movements of water within a single water body are also not subject to NPDES permitting requirements.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • RequirementCGP Part 2.4 construction dewatering requirements include: route dewatering water through a sediment control (e.g., sediment trap or basin, pumped water filter bag) designed to prevent discharges with visual turbidity (a sediment plume, or a cloudy, opaque or visibly contrasting discharge); do not discharge visible floating solids or foam; to the extent feasible, infiltrate dewatering water in well-vegetated upland areas before discharge; and do not use receiving waters as part of the treatment area.

    Applies when: Dewatering discharges authorized under the EPA CGP EPA 2022 CGP (as modified), Part 2.4.1-2.4.4 and n.56 [16]
    Show the source text
    Route dewatering water through a sediment control (e.g., sediment trap or basin, pumped water filter bag) designed to prevent discharges with visual turbidity; ... Do not discharge visible floating solids or foam; ... visual turbidity is present where there is a sediment plume in the discharge or the discharge appears cloudy, or opaque, or has a visible contrast ... use well-vegetated (e.g., grassy or wooded), upland areas of the site to infiltrate dewatering water before discharge. ... You are prohibited from using receiving waters as part of the treatment area;
    Open U.S. EPA (opens in a new tab)
  • Size cutoffCGP turbidity benchmark for dewatering: sites discharging dewatering water to 'sensitive waters' (waters impaired for sediment or a sediment-related parameter, Tier 2, 2.5 or 3 antidegradation waters, or waters within Lands of Exclusive Federal Jurisdiction) must collect at least one turbidity sample from the dewatering discharge each day a discharge occurs and compare the weekly average of the results to the standard 50 NTU benchmark (or to an alternate benchmark if EPA has approved one). EPA states the benchmark is not an effluent limitation. Separately, sites discharging dewatering water must be inspected during the discharge once per day on which the discharge occurs.

    Applies when: CGP dewatering discharges; benchmark only for discharges to sensitive waters EPA 2022 CGP (as modified), Parts 3.3, 3.3.1, 3.3.2, 3.3.3, 4.3.2 [16]
    Show the source text
    For sites discharging dewatering water to “sensitive waters” (i.e., receiving waters listed as impaired for sediment or a sediment-related parameter ... EPA notes that the benchmark threshold is not an effluent limitation ... at least one turbidity sample from your dewatering discharge each day a discharge occurs. ... unless EPA has authorized the use of an alternate benchmark ... Compare the weekly average ... of your turbidity monitoring results to the standard 50 NTU benchmark ... you must conduct an inspection ... during the discharge once per day on which the discharge occurs.
    Open U.S. EPA (opens in a new tab)
More detail: 32 more verified statements on draining a pond and releasing its water or sediment
  • ProcessRGL 05-04 factors: when deciding whether a sediment release is de minimis or exempt as dam maintenance, Corps District Engineers should consider whether the discharge through the dam is necessary for dam maintenance and proportional to the activity and the size of the facility (size of the dam and the surface acres and storage volume of the impoundment), plus time of year and seasonality of high flows, the size of the incoming and outgoing streams and intended release volume, the natural hydrograph, and the speed of the drawdown (the RGL also lists the normal amount of watershed sediment and the potential for environmental harm).

    USACE RGL 05-04 (Aug. 19, 2005), para. 4.b [7]
    Show the source text
    District Engineers should consider whether the discharge of dredged or fill material through the dam is necessary for dam maintenance, and proportional to the proposed activity and the size of the facility (i.e., size of the dam/structure and the surface acres and storage volume of the resulting impoundment). Other factors ... should include the time of year and normal seasonality of high volume flows, the size of incoming and outgoing stream/river and the intended release volume, the natural hydrograph of the system, the speed of the drawdown
    Open U.S. Army Corps of Engineers (opens in a new tab)
  • DefinitionUnder Corps regulations, 'discharge of dredged material' means any addition of dredged material into, including redeposit (other than incidental fallback) within, waters of the United States, including any addition incidental to any activity such as excavation; 'dredged material' is material excavated or dredged from waters of the United States; incidental fallback is excluded.

    33 CFR 323.2(c), (d)(1), (d)(2)(iii) [4]
    Show the source text
    (c) The term dredged material means material that is excavated or dredged from waters of the United States. ... the term discharge of dredged material means any addition of dredged material into, including redeposit of dredged material other than incidential fallback within, the waters of the United States. ... (iii) Incidental fallback.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • DefinitionCorps definitions: 'dredged material' means material that is excavated or dredged from waters of the United States; 'discharge of dredged material' means any addition of dredged material into, including redeposit (other than incidental fallback) within, the waters of the United States. That definition is expressly subject to paragraph (d)(2), which lists things the term does not include (e.g., incidental fallback), and paragraph (d)(3) lists discharges for which section 404 authorization is not required; those exclusions are not summarized here.

    33 CFR 323.2(c), (d)(1) [4]
    Show the source text
    (c) The term dredged material means material that is excavated or dredged from waters of the United States. ... (1) Except as provided below in paragraph (d)(2), the term discharge of dredged material means any addition of dredged material into, including redeposit of dredged material other than incidential fallback within, the waters of the United States. ... (2) The term discharge of dredged material does not include the following: ... (iii) Incidental fallback. (3) Section 404 authorization is not required for the following:
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • ExemptionClean Water Act section 404(f)(1) provides that, except as provided in paragraph (f)(2) (recapture), the discharge of dredged or fill material (B) for the purpose of maintenance, including emergency reconstruction of recently damaged parts, of currently serviceable structures such as dikes and dams, and (C) for the purpose of construction or maintenance of farm or stock ponds (or irrigation ditches, or maintenance of drainage ditches), is not prohibited by or otherwise subject to regulation under section 404, section 301(a) (33 U.S.C. 1311(a)) or section 402 (33 U.S.C. 1342), except for effluent standards or prohibitions under section 307 (33 U.S.C. 1317).

    Applies when: Discharges of dredged/fill material into waters of the United States 33 U.S.C. 1344(f)(1)(B)-(C) [10]
    Show the source text
    (1) Except as provided in paragraph (2) of this subsection ... (B) for the purpose of maintenance, including emergency reconstruction of recently damaged parts, of currently serviceable structures such as dikes, dams, ... (C) for the purpose of construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance of drainage ditches; ... is not prohibited by or otherwise subject to regulation under this section or section 1311(a) or 1342 of this title (except for effluent standards or prohibitions under section 1317 of this title).
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • ExemptionCWA section 404(f)(1) exempts discharges of dredged or fill material for maintenance of currently serviceable structures such as dams, and for construction or maintenance of farm or stock ponds, and provides that such exempt discharges are not prohibited by or otherwise subject to regulation under section 404, section 301(a) (33 U.S.C. 1311(a)) or section 402 (33 U.S.C. 1342), except for section 307 toxic effluent standards or prohibitions. (Exempt activities remain subject to the section 404(f)(2) recapture provision - see fed-gap2-sealing-drawdown topic.)

    33 U.S.C. 1344(f)(1)(B)-(C) [10]
    Show the source text
    (1) Except as provided in paragraph (2) of this subsection, the discharge of dredged or fill material ... (B) for the purpose of maintenance ... of currently serviceable structures such as dikes, dams, levees ... (C) for the purpose of construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance of drainage ditches; ... is not prohibited by or otherwise subject to regulation under this section or section 1311(a) or 1342 of this title (except for effluent standards or prohibitions under section 1317 of this title).
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • AgencyEPA's Section 404 exemptions page lists 'Construction and maintenance of farm or stock ponds' and 'Maintenance of structures such as dams, dikes, and levees' among activities exempt under Section 404(f)(1), but states an exempt activity is not exempt if it represents a new use of the water and would reduce reach or impair flow or circulation of regulated waters - both conditions must be met.

    EPA, 'Exemptions to Permit Requirements under CWA Section 404' [11]
    Show the source text
    Construction and maintenance of farm or stock ponds ... Maintenance of structures such as dams, dikes, and levees ... If an activity listed above as exempt represents a new use of the water, and the activity would result in a reduction in reach or impairment of flow or circulation of regulated waters, including wetlands, the activity is not exempt. Both conditions must be met in order for the activity to be considered non-exempt.
    Open U.S. Environmental Protection Agency (opens in a new tab)
  • RequirementRecapture regulation as it bears on sediment releases: a discharge incidental to an otherwise-exempt 323.4(a) activity must have a permit if it is part of an activity whose purpose is to convert an area of waters of the United States into a use to which it was not previously subject, where flow or circulation may be impaired or reach reduced. Where the proposed discharge will result in significant discernible alterations to flow or circulation, the presumption is that flow or circulation may be impaired. A discharge that elevates the bottom of waters of the United States without converting it to dry land does not thereby reduce reach, but may alter flow or circulation.

    33 CFR 323.4(c) [4]
    Show the source text
    must have a permit if it is part of an activity whose purpose is to convert an area of the waters of the United States into a use to which it was not previously subject, where the flow or circulation ... may be impaired or the reach of such waters reduced. ... significant discernible alterations to flow or circulation, the presumption is that flow or circulation may be impaired ... A discharge which elevates the bottom of waters of the United States without converting it to dry land does not thereby reduce the reach of, but may alter the flow or circulation of, waters of the United States.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • ProcessNWP 3(c) (2026) also authorizes temporary structures, fills and work (including temporary mats) necessary to conduct the maintenance, but appropriate measures must be taken to maintain normal downstream flows and minimize flooding to the maximum extent practicable, and temporary fills must be removed in their entirety. A note says NWP 3 authorizes repair of previously authorized structures or fills that do not qualify for the section 404(f) maintenance exemption.

    NWP 3(c) and Note (2026), 91 FR 858-859 (Jan. 8, 2026) [14]
    Show the source text
    (c) This NWP also authorizes temporary structures, fills, and work, including the use of temporary mats, necessary to conduct the maintenance activity. Appropriate measures must be taken to maintain normal downstream flows and minimize flooding to the maximum extent practicable ... temporary fills must be removed in their entirety ... Note: This NWP authorizes the repair, rehabilitation, or replacement of any previously authorized structure or fill that does not qualify for the Clean Water Act Section 404(f) exemption for maintenance.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessNWP 33 (Temporary Construction, Access, and Dewatering), 2026: authorizes temporary structures, work, and discharges of dredged or fill material, including cofferdams, necessary for construction activities or access fills or dewatering of construction sites, provided the associated primary activity is authorized by the Corps or the U.S. Coast Guard; it also authorizes such temporary structures, work and discharges, including cofferdams, necessary for construction activities not otherwise subject to Corps or Coast Guard permit requirements. Appropriate measures must be taken to maintain near normal downstream flows and to minimize flooding; it does not authorize using cofferdams to dewater wetlands or other aquatic areas to change their use; and a pre-construction notification is required if the activity is conducted in navigable waters of the United States (section 10 waters).

    NWP 33 (2026), 91 FR 866 (Jan. 8, 2026) [14]
    Show the source text
    Temporary structures, work, and discharges of dredged or fill material, including cofferdams, necessary for construction activities or access fills or dewatering of construction sites, provided that the associated primary activity is authorized by the Corps of Engineers or the U.S. Coast Guard. ... not otherwise subject to the Corps or U.S. Coast Guard permit requirements. ... maintain near normal downstream flows and to minimize flooding ... does not authorize the use of cofferdams to dewater wetlands ... if the activity is conducted in navigable waters of the United States
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementNationwide Permit general conditions (2026 NWPs, effective March 15, 2026) that bear on the timing and turbidity of NWP-authorized work such as a dewatering or sediment-removal activity: activities in spawning areas during spawning seasons must be avoided to the maximum extent practicable, and activities that physically destroy an important spawning area (e.g., by downstream smothering by substantial turbidity) are not authorized (GC 3); appropriate soil erosion and sediment controls must be used and maintained, and permittees are encouraged to work in waters of the United States during periods of low-flow or no-flow (GC 12). These are general conditions, not drawdown-rate standards.

    Applies when: Activities authorized under a 2026 Nationwide Permit 2026 NWP General Conditions 3 and 12, 91 FR 768, 876 (Jan. 8, 2026) [14]
    Show the source text
    3. Spawning Areas. Activities in spawning areas during spawning seasons must be avoided to the maximum extent practicable. Activities that result in the physical destruction (e.g., through excavation, fill, or downstream smothering by substantial turbidity) of an important spawning area are not authorized. ... 12. Soil Erosion and Sediment Controls. Appropriate soil erosion and sediment controls must be used and maintained in effective operating condition during construction ... Permittees are encouraged to perform work within waters of the United States during periods of low-flow or no-flow
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessEPA's Office of Water FAQ on removal of obsolete dams (December 2016) says activities potentially regulated under section 404 include the release of bottom sediment from or through a dam as a result of non-normal dam operations (citing RGL 05-04), and that factors the Corps may weigh in choosing individual versus general permit review include sediment contaminants, sediment volume and grain size, sensitive species, invasive species, and the timing of life-cycle events such as spawning or migration. It gives no numeric drawdown rate or turbidity limit. The FAQs are not legally binding.

    EPA, Frequently Asked Questions on Removal of Obsolete Dams (EPA-840-F-16-001, Dec. 2016), Q8 [19]
    Show the source text
    do not impose legally binding requirements ... potentially the release of bottom sediment from or through a dam as a result of non-normal dam operations. ... Regulatory Guidance Letter (RGL) 05-04 ... Factors that may be considered include: whether contaminants may be present in sediment held behind the dam; volume and grain size distribution of sediment held behind the dam; nature and sensitivity of aquatic species ... presence of invasive or exotic plant or animal species ... timing of life cycle events of species that may be affected (e.g., spawning or migration)
    Open U.S. EPA Office of Water (opens in a new tab)
  • ProcessThe same EPA dam-removal FAQ says turbidity may increase during and for a short time after removal, recommends that impacts be minimized and evaluated in the applicable state and federal permitting processes (e.g., section 404 and state section 401 water quality certification), and says specific monitoring or testing requirements will be set case by case during the regulatory authorization process.

    EPA, Frequently Asked Questions on Removal of Obsolete Dams (Dec. 2016), Q6 and Q10 [19]
    Show the source text
    Turbidity may increase both during and for a short time after the removal. ... EPA recommends that all potential impacts be minimized to the greatest practical extent and be thoroughly evaluated by project proponents during applicable state and federal permitting processes (e.g. Clean Water Act Section 404, state Section 401 water quality certification, etc.). ... Specific requirements for monitoring or testing for a dam removal project will vary based on the conditions of the individual project and will be determined during the regulatory authorization process
    Open U.S. EPA Office of Water (opens in a new tab)
  • ExemptionNPDES exclusion for 404 discharges: discharges of dredged or fill material into waters of the United States that are regulated under CWA section 404 do not require NPDES permits.

    40 CFR 122.3(b) [15]
    Show the source text
    The following discharges do not require NPDES permits: ... (b) Discharges of dredged or fill material into waters of the United States which are regulated under section 404 of CWA.
    Open eCFR (opens in a new tab)
  • EPA's 2008 preamble says the Water Transfers Rule has no effect on the section 404 program: the statutory definition of 'pollutant' includes 'dredged spoil', which 'by its very nature comes from a waterbody', and discharges of dredged or fill material remain governed by section 404.

    73 FR 33697, 33703 (June 13, 2008), preamble sec. IV ("Public Comment") [9]
    Show the source text
    EPA believes that today's final rule will not have an effect on the 404 program. The statutory definition of ``pollutant'' includes ``dredged spoil,'' which by its very nature comes from a waterbody. ... today's rule has no effect on the 404 permit program, under which discharges of dredged or fill material may be authorized by a permit.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • StatusAdoption history of the water transfers exclusion: EPA's final 'NPDES Water Transfers Rule' was published June 13, 2008 (73 FR 33697-33708) and took effect August 12, 2008. It followed EPA's June 7, 2006 proposed rule, which was based on an August 5, 2005 EPA interpretive memorandum. EPA said the rule clarifies that water transfers are not subject to NPDES permitting and does not affect any other activity that may be subject to NPDES requirements.

    73 FR 33697 (June 13, 2008), Summary and Dates [9]
    Show the source text
    SUMMARY: EPA is issuing a regulation to clarify that water transfers are not subject to regulation under the National Pollutant Discharge Elimination System (NPDES) permitting program. ... This rule focuses exclusively on water transfers and does not affect any other activity that may be subject to NPDES permitting requirements. This rule is consistent with EPA's June 7, 2006, proposed rule, which was based on an August 5, 2005, interpretive memorandum ... DATES: This final rule is effective on August 12, 2008.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • RequirementLimit on the water-transfer exclusion: the 2008 rule requires NPDES permits for 'pollutants introduced by the water transfer activity itself to the water being transferred'. EPA said water transfers should be operated and maintained so that they do not themselves add pollutants, but where they introduce pollutants to water passing through the structure into the receiving water, NPDES permits are required - and the permit covers only those added pollutants, not pollutants already in the donor water.

    73 FR 33697, 33705 (June 13, 2008), preamble sec. IV ("When Water Transfers Introduce Pollutants") [9]
    Show the source text
    would require NPDES permits for ``pollutants introduced by the water transfer activity itself to the water being transferred.'' Water transfers should be able to be operated and maintained in a manner that ensures they do not themselves add pollutants ... where water transfers introduce pollutants to water passing through the structure into the receiving water, NPDES permits are required. ... the scope of the required NPDES permit would only be for those added pollutants. Such a permit would not require the water transfer facility to address pollutants that may have been in the donor waterbody
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • EPA's 2008 preamble, answering whether naturally occurring changes to transferred water need a permit, says changes in water temperature, pH, BOD and dissolved oxygen as water moves through dams or sits in reservoirs along a water transfer are viewed the same way as changes to water quality caused by water moving through dams (National Wildlife Federation v. Gorsuch): they are not an 'addition' of a pollutant subject to section 402 permitting.

    73 FR 33697, 33705 (June 13, 2008), preamble ("Pollutants Incidental to Water Transfers") [9]
    Show the source text
    For example, as water moves through dams or sits in reservoirs along the transfer, chemical and physical factors such as water temperature, pH, BOD, and dissolved oxygen may change. The Agency views these changes the same way it views changes to water quality caused by water moving through dams (National Wildlife Fed'n v. Gorsuch, 693 F.2d 156 (D.C. Cir. 1982)); they do not constitute an ``addition'' of pollutant subject to the permitting requirements of section 402 of the Act.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • DefinitionEPA's 2008 preamble on what counts as a water-transfer 'activity': a water transfer is an engineered activity that diverts a water of the U.S. to a second water of the U.S.; by 'activity' EPA means any system of pumping stations, canals, aqueducts, tunnels, pipes, or other such conveyances constructed to transport water from one water of the U.S. to another, which may be a single tunnel or pumping station. A pumping station, pipe, canal or other structure used solely to facilitate the transfer is not an 'intervening use'.

    73 FR 33697, 33704 (June 13, 2008), preamble sec. IV ("Definition of a Water Transfer"; "Intervening Industrial, Municipal, or Commercial Use") [9]
    Show the source text
    A water transfer is an engineered activity that diverts a water of the U.S. to a second water of the U.S. ... By ``activity,'' the Agency means any system of pumping stations, canals, aqueducts, tunnels, pipes, or other such conveyances constructed to transport water from one water of the U.S. to another water of the U.S. Such a system may consist of a single tunnel or pumping station ... In contrast, a water pumping station, pipe, canal, or other structure used solely to facilitate the transfer of the water is not an intervening use.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • ExemptionIntervening-use limit: a discharge associated with a water transfer that results from an intervening commercial, municipal or industrial use, or that is otherwise introduced by a water transfer facility itself, requires an NPDES permit like any point-source discharge. EPA's example: water withdrawn for cooling, drinking water, irrigation or any other use such that it is no longer a water of the U.S. before being returned has been subjected to an intervening use.

    73 FR 33697, 33704 (June 13, 2008), preamble sec. IV ("Intervening Industrial, Municipal, or Commercial Use") [9]
    Show the source text
    A discharge of a pollutant associated with a water transfer resulting from an intervening commercial, municipal, or industrial use, or otherwise introduced to the water by a water transfer facility itself would require an NPDES permit as any discharge of a pollutant from a point source into a water of the U.S. would. ... For example, if the water is withdrawn to be used as cooling water, drinking water, irrigation, or any other use such that it is no longer a water of the U.S. before being returned to a water of the U.S., the water has been subjected to an intervening use.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • EPA's 2008 preamble on impoundments that are excluded from 'waters of the United States': EPA said impoundments used to settle mining process water or wastewater would generally be 'waste treatment systems' excluded from the WOTUS definition, and that 'the addition of pollutants from a waste treatment system to a water of the United States triggers the permitting requirement', so the water-transfer rule does not affect permitting of such facilities.

    73 FR 33697, 33703 (June 13, 2008), preamble sec. IV ("Public Comment") [9]
    Show the source text
    the Agency believes that impoundments used to settle mining process water or waste water would generally constitute ``waste treatment systems'' designed to meet the requirements of the CWA and would be excluded from the definition of ``waters of the United States.'' See 40 CFR 122.2 (definition of ``Waters of the United States''). The addition of pollutants from a waste treatment system to a water of the United States triggers the permitting requirement, and today's rule therefore does not affect the permitting of such facilities.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • AgencyState role under the Water Transfers Rule: EPA said nothing in the rule precludes a State, under State law, from regulating water transfers that are not subject to section 402; States may not exclude from NPDES requirements sources that are point sources under federal law (including those that do not meet the water-transfer definition); and States can address in-stream and downstream effects of water transfers through their water quality standards and TMDL programs.

    73 FR 33697, 33704-33705 (June 13, 2008), preamble sec. IV [9]
    Show the source text
    However, nothing in this rule precludes a State, under State law, from regulating water transfers that are not subject to section 402 of the Clean Water Act. States may not exclude from NPDES permit requirements sources that are point sources under Federal law, including those that do not meet the definition of a water transfer in today's rule. ... States currently have the ability to address potential in-stream and/or downstream effects of water transfers through their WQS and TMDL programs.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • As of the 2008 rulemaking, EPA reported that Pennsylvania was the only NPDES permitting authority that regularly issued NPDES permits for water transfers, having begun in 1986 in response to a State court decision (DELAWARE Unlimited v. DER, 508 A.2d 348 (Pa. Cmwlth. 1986)).

    Applies when: Pennsylvania (historical statement as of 2008) 73 FR 33697, 33699 (June 13, 2008), preamble sec. II [9]
    Show the source text
    Although there have been a few isolated instances where entities responsible for water transfers have been issued NPDES permits, Pennsylvania is the only NPDES permitting authority that regularly issues NPDES permits for water transfers. Pennsylvania began issuing permits for water transfers in 1986, in response to a State court decision mandating the issuance of such permits.
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • StatusPROPOSED (not final): On September 4, 2026 EPA proposed 'Updates to the National Pollutant Discharge Elimination System Definitions and Exclusions' (91 FR 56819-56825; comments due October 19, 2026). The proposed amendatory text revises only paragraph (b) of the 40 CFR 122.2 'discharge of a pollutant' definition (contiguous zone/ocean discharges by vessels) and paragraph (a) of 40 CFR 122.3 (vessels); it does not propose any change to the 122.3(i) water-transfer exclusion.

    91 FR 56819, 56825 (Sept. 4, 2026), proposed rule, amendatory instructions 2-3 [20]
    Show the source text
    Updates to the National Pollutant Discharge Elimination System Definitions and Exclusions ... ACTION: Proposed rule. ... DATES: Comments must be received on or before October 19, 2026. ... 2. Amend Sec. 122.2 by revising the definition of ``Discharge of a pollutant'' paragraph (b) to read as follows: ... 3. Amend Sec. 122.3 by revising paragraph (a) to read as follows:
    Open U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • StatusCatskill III recounts that the Eleventh Circuit's Friends of the Everglades decision (570 F.3d 1210 (11th Cir. 2009)) accorded Chevron deference to, and upheld, the Water Transfers Rule; rehearing en banc was denied (605 F.3d 962 (2010)) and certiorari was denied (562 U.S. 1082 (2010)).

    Catskill III, 846 F.3d 492 (2d Cir. 2017), slip op. at 24 [21]
    Show the source text
    Friends I, 570 F.3d 1210 (11th Cir. 2009), rehʹg en banc denied, 605 F.3d 962 (2010), ... cert. denied, 562 U.S. 1082, and cert. denied sub nom. Miccosukee Tribe v. S. Fla. Water ... Mgmt. Dist., 562 U.S. 1082 (2010), according Chevron deference to, and upholding, ... the Water Transfers Rule.
    Open U.S. Court of Appeals for the Second Circuit (govinfo USCOURTS) (opens in a new tab)
  • StatusThe Supreme Court denied certiorari on February 26, 2018 in No. 17-418, New York, et al. v. Environmental Protection Agency, et al. (the States' petition from the Second Circuit's January 18, 2017 decision in Nos. 14-1823 et al.), leaving the Second Circuit's reinstatement of the Water Transfers Rule in place.

    Supreme Court docket No. 17-418 [22]
    Show the source text
    Docket for 17-418 ... New York, et al., Petitioners ... Environmental Protection Agency, et al. ... United States Court of Appeals for the Second Circuit ... (14-1823, 14-1909, 14-1991, 14-1997, 14-2003) ... January 18, 2017 ... Feb 26 2018 ... Petition DENIED.
    Open Supreme Court of the United States (opens in a new tab)
  • StatusThe Supreme Court also denied certiorari on February 26, 2018 in No. 17-446, Riverkeeper, Inc., et al. v. Environmental Protection Agency, et al. (petition from the same Second Circuit decision, Nos. 14-1823 et al.).

    Supreme Court docket No. 17-446 [23]
    Show the source text
    Docket for 17-446 ... Riverkeeper, Inc., et al., Petitioners ... Environmental Protection Agency, et al. ... (14-1823, 14-1909, 14-1991, 14-1997, 14-2003) ... Feb 26 2018 ... Petition DENIED.
    Open Supreme Court of the United States (opens in a new tab)
  • StatusLoper Bright (June 28, 2024): the Supreme Court overruled Chevron but said that by doing so it does not call into question prior cases that relied on the Chevron framework; the holdings of those cases that specific agency actions are lawful remain subject to statutory stare decisis despite the change in interpretive methodology.

    Loper Bright Enterprises v. Raimondo, 603 U.S. 369 (2024), slip op. at 34-35 [24]
    Show the source text
    By doing so, however, we do not call into question prior cases that relied on the Chevron framework. The holdings of those cases that specific agency actions are lawful ... are still subject to statutory stare decisis despite our change in interpretive methodology.
    Open Supreme Court of the United States (opens in a new tab)
  • Size cutoffEPA's 2022 Construction General Permit (as modified) became effective 12:00 am April 8, 2025 (for EPA Regions 1 and 3, the modified permit became effective 2:00 pm June 10, 2025) and expires 11:59 pm February 16, 2027. Among its eligibility conditions, the site's construction activities must disturb one or more acres, or less than one acre if part of a common plan of development or sale that will ultimately disturb one or more acres, or have been designated by EPA as needing coverage; and the site must be in an area where EPA is the permitting authority (Appendix B). Other eligibility conditions in Part 1.1 (e.g., endangered species criteria) also apply.

    EPA 2022 CGP (as modified), cover page and Parts 1.1.2-1.1.3 [16]
    Show the source text
    This permit becomes effective on 12:00 am, April 8, 2025. This permit and the authorization to discharge expire at 11:59pm, February 16, 2027. ... For EPA Regions 1 and 3, this modified permit becomes effective at 2:00 pm, June 10, 2025. ... Will disturb one or more acres of land, or will disturb less than one acre of land but are part of a common plan of development or sale (as defined in Appendix A) that will ultimately disturb one or more acres of land; or Have been designated by EPA as needing permit coverage ... Your site is located in an area where EPA is the permitting authority
    Open U.S. EPA (opens in a new tab)
  • DefinitionThe CGP defines 'dewatering' as the act of draining accumulated stormwater and/or ground water from building foundations, vaults, and trenches, or other similar points of accumulation. Its listed examples include 'surface area dewatering': water pumped from disturbed surface areas (e.g., trenches, sumps, excavation pits, or other excavations associated with construction where sediment-laden ground water or surface water/storm inflow must be removed) or from sediment basins or similar impoundments for maintenance or decommissioning purposes. The definition does not mention draining an existing pond or lake.

    EPA 2022 CGP Appendix A (as modified April 2025), definition of "Dewatering", p. A-3 [17]
    Show the source text
    “Dewatering” – the act of draining accumulated stormwater and/or ground water from building foundations, vaults, and trenches, or other similar points of accumulation. Examples can include, but are not limited to: • Surface area dewatering: water pumped from disturbed surface areas (e.g., trenches, sumps, excavation pits, or other excavations associated with construction where sediment-laden ground water or surface water/storm inflow must be removed) or from sediment basins or similar impoundments for maintenance or decommissioning purposes.
    Open U.S. EPA (opens in a new tab)
  • StatusPROPOSED (not final): EPA's proposed 2027 CGP Appendix A keeps the same 'dewatering' definition, including the 'surface area dewatering' example covering sediment basins or similar impoundments for maintenance or decommissioning.

    Proposed 2027 CGP, Appendix A, definition of "Dewatering" [18]
    Show the source text
    Proposed 2027 CGP ... “Dewatering” – the act of draining accumulated stormwater and/or ground water from building foundations, vaults, and trenches, or other similar points of accumulation. ... or from sediment basins or similar impoundments for maintenance or decommissioning purposes.
    Open U.S. EPA (opens in a new tab)
  • RequirementCGP authorized non-stormwater discharges include 'uncontaminated, non-turbid discharges of ground water or spring water' and 'uncontaminated construction dewatering water' discharged in accordance with Part 2.4. EPA's footnote warns that operators may need to follow additional procedures to verify a dewatering discharge is uncontaminated and should comply with any State, Tribal or local dewatering requirements.

    Applies when: Sites covered by the EPA CGP EPA 2022 CGP (as modified), Part 1.2.2 and n.7 [16]
    Show the source text
    Uncontaminated, non-turbid discharges of ground water or spring water; ... Uncontaminated construction dewatering water ... discharged in accordance with Part 2.4. ... EPA notes that operators may need to comply with additional procedures to verify that the dewatering discharge is uncontaminated. ... should ensure that they have complied with any State, Tribal, or local dewatering requirements that apply.
    Open U.S. EPA (opens in a new tab)
  • RequirementFederal construction and development effluent guidelines prohibit discharges from dewatering activities, including dewatering of trenches and excavations, unless managed by appropriate controls. The guidelines apply to discharges associated with construction activity required to obtain NPDES coverage under 40 CFR 122.26(b)(14)(x) and (b)(15).

    40 CFR 450.10(a), 450.21(c) [25]
    Show the source text
    This part applies to discharges associated with construction activity required to obtain NPDES permit coverage pursuant to 40 CFR 122.26(b)(14)(x) and (b)(15). ... (c) Dewatering. Discharges from dewatering activities, including discharges from dewatering of trenches and excavations, are prohibited unless managed by appropriate controls.
    Open eCFR / Office of the Federal Register (opens in a new tab)

Not confirmed from a primary source

We could not confirm the following from an official source. Ask the agency listed before relying on any of it.

  • Whether draining a pond that is not itself a water of the United States (for example, an excluded upland stock pond) into a downstream water can be treated as a Section 404 discharge. Greenfield Mills involved an on-stream impoundment of a river, and RGL 05-04 addresses dams generally. — ask: Corps district regulatory office (ask for a jurisdictional determination and an applicability determination under 33 CFR 320.1(a)(6))
  • Whether sediment carried out of a pond that is not a water of the United States counts as dredged material, fill material or a section 402 pollutant once it enters a downstream water of the United States. — ask: Corps district regulatory office; EPA regional wetlands and NPDES offices
  • Whether draining a pond that is not a water of the United States by pipe, siphon or pump into a water of the United States is a point-source discharge needing NPDES coverage, and whether the Clean Water Act's agricultural stormwater exclusion or EPA's non-point agricultural exclusion could apply to a farm pond. — ask: EPA regional NPDES office or the state NPDES permitting authority (ask for a written applicability determination before draining)
  • Whether pumping or siphoning water out of a pond that is a water of the United States into a different downstream water, for example with a temporary pump during repair or sealing, is an excluded water transfer, a movement within one water body, or a discharge needing NPDES coverage. — ask: EPA regional NPDES permits office, or the state NPDES permitting authority where the state is authorized
  • Whether pumping the standing water out of an existing pond during a project covered by EPA's Construction General Permit counts as dewatering subject to the permit's dewatering controls and turbidity benchmark. — ask: EPA regional stormwater coordinator (where EPA is the permitting authority) or the state construction stormwater program
  • Any EPA or Corps headquarters document that sets a numeric drawdown rate, a seasonal timing window or a turbidity limit for pond or small-reservoir drawdowns. Corps district regional conditions and state dam safety, fisheries and 401 rules were not reviewed for this federal page. — ask: Corps district regulatory office; state dam safety program; state fish and wildlife agency; state section 401 certifying agency
  • Any current national Corps or EPA guidance on mechanical sediment removal (cleanout or dredging) of existing farm, stock or recreation ponds beyond RGL 05-04, NWP 3 and the 404(f) regulations. Only regional district documents were found. — ask: Corps district regulatory office for the project location
  • Whether RGL 05-04 has been superseded or modified by later Corps guidance or regulation. The letter says it remains effective unless revised or rescinded. — ask: USACE Headquarters Regulatory Program or the local district regulatory office
  • Whether any court has re-examined the Water Transfers Rule since Loper Bright (2024) ended Chevron deference. — ask: EPA Office of Wastewater Management, Water Permits Division; EPA Office of General Counsel
  • Whether a state with its own NPDES program regulates water transfers or pond drawdowns more strictly than the federal exclusion. — ask: The state NPDES permitting authority (in Pennsylvania, DEP)

Does sealing or lining need a federal permit?

The Corps and EPA define "fill material" by its effect: material placed in waters of the United States that replaces any portion of a water with dry land or changes the bottom elevation of any portion of a water, with non-exclusive examples that include rock, sand, soil, clay and plastics; the Corps' rule also says trash or garbage is not fill material. The Corps' definition of "discharge of fill material" includes building any structure, infrastructure or impoundment requiring rock, sand, dirt or other material for its construction, and its only reference to a liner is placing fill for a liner associated with solid waste landfills; whether sealing or lining a pond is a section 404 discharge is listed below as not confirmed. [4][26]

In the May 2002 joint rule that adopted this "fill material" definition, the agencies said placing berms, liners and other infrastructure for a solid waste landfill in waters of the United States replaces water with dry land or raises the bottom elevation, so under that rule those liners are fill material. The same preamble says the agencies do not consider suspended or settleable solids, which can raise a water's bottom over time as they settle, to be "fill material," and the Supreme Court held in Coeur Alaska (2009) that EPA may not issue section 402 permits for fill material that falls under the Corps' section 404 authority. [27][28]

Corps regulations say discharges of dredged or fill material from construction or maintenance of farm or stock ponds are not subject to section 404 regulation, but a section 404 permit is still required if the discharge contains a toxic pollutant listed under section 307, or if it is part of an activity whose purpose is to convert an area of waters of the United States to a use to which it was not previously subject, where flow or circulation may be impaired or reach reduced. On bottom elevation, the recapture regulation says a discharge that raises the bottom of waters of the United States without converting it to dry land "does not thereby reduce the reach of, but may alter the flow or circulation of," those waters; whether sealing or relining counts as exempt pond maintenance is listed below as not confirmed. [4]

Among the 2026 nationwide permits (effective March 15, 2026, expiring March 15, 2031), NWP 3 authorizes the repair, rehabilitation or replacement of a previously authorized, currently serviceable structure or fill, provided it is not put to uses differing from those specified or contemplated in the original permit or the most recently authorized modification, and its note says it authorizes such work on structures or fills that do not qualify for the section 404(f) maintenance exemption. NWP 18 authorizes minor discharges within its 25-cubic-yard and 1/10-acre limits (its conditions and notification triggers are described under draining, above). For nationwide permit limits, "loss of waters of the United States" counts waters permanently adversely affected by the regulated activity, including by permanent discharges of dredged or fill material that increase the bottom elevation of a waterbody, but not waters temporarily filled, flooded, excavated or drained and then restored to pre-construction contours and elevations. Whether a Corps district would authorize sealing or lining under either permit is listed below as not confirmed. [14]

The 2023 rule's preamble, explaining the term "dry land" used in the rule's exclusions, says jurisdictional and non-jurisdictional waters are not considered "dry land" just because they lack water at a given time, and a Corps regulatory note says unauthorized discharges do not eliminate Clean Water Act jurisdiction, even where they have the effect of destroying waters of the United States. How these apply to a pond drained for sealing is listed below as not confirmed. [4][6]

For products added to pond water: FIFRA bars distributing or selling an unregistered pesticide except as the Act provides. EPA's rules consider a product a pesticide requiring registration (subject to listed exceptions) if the seller claims, states or implies that it can or should be used as a pesticide, if it contains active ingredients and has no significant commercially valuable use other than pesticidal use or use to manufacture a pesticide, or if the seller has actual or constructive knowledge that it will be used, or is intended to be used, for a pesticidal purpose. EPA's rules treat algae and other plants growing where not wanted as pests when circumstances make them deleterious to man or the environment, and EPA says point-source discharges to waters of the United States from applying biological pesticides, or chemical pesticides that leave a residue, have required NPDES permits since October 31, 2011. [29][30][31]

  • DefinitionUnder the Corps' section 404 regulations, 'fill material' is material placed in waters of the United States that has the effect of (i) replacing any portion of a water of the United States with dry land, or (ii) changing the bottom elevation of any portion of a water of the United States. The regulation's non-exclusive examples include rock, sand, soil, clay, plastics, construction debris, wood chips, overburden from mining or other excavation, and materials used to create any structure. The term does not include trash or garbage.

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. 33 CFR 323.2(e)(1)-(3) [4]
    Show the source text
    the term fill material means material placed in waters of the United States where the material has the effect of: (i) Replacing any portion of a water of the United States with dry land; or (ii) Changing the bottom elevation of any portion of a water of the United States. (2) Examples of such fill material include, but are not limited to: rock, sand, soil, clay, plastics, construction debris, wood chips, overburden from mining or other excavation activities, and materials used to create any structure ... (3) The term fill material does not include trash or garbage.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • DefinitionThe Corps defines 'discharge of fill material' as the addition of fill material into waters of the United States. Its listed examples include placement of fill necessary to construct any structure or infrastructure in a water of the United States; building any structure, infrastructure, or impoundment requiring rock, sand, dirt, or other material for its construction; and 'placement of fill material for construction or maintenance of any liner, berm, or other infrastructure associated with solid waste landfills' (the only reference to a liner in the definition). The term does not include plowing, cultivating, seeding and harvesting (for the production of food, fiber, and forest products, per the full text).

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. 33 CFR 323.2(f) [4]
    Show the source text
    The term discharge of fill material means the addition of fill material into waters of the United States. ... Placement of fill that is necessary for the construction of any structure or infrastructure in a water of the United States; the building of any structure, infrastructure, or impoundment requiring rock, sand, dirt, or other material for its construction; ... placement of fill material for construction or maintenance of any liner, berm, or other infrastructure associated with solid waste landfills; ... The term does not include plowing, cultivating, seeding and harvesting
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • The 2002 preamble describes a court decision (Resource Investments v. Corps, 9th Cir. 1998) finding that neither solid waste nor a landfill liner of layers of gravel and low-permeability soil was 'fill material' under the Corps' then-current regulations. The agencies responded that fills typically serve some purpose other than just creating dry land or raising a water's bottom elevation, and stated that placing berms, liners and other infrastructure for a solid waste landfill in waters of the U.S. has the effect of replacing water with dry land or raising the bottom elevation of a water, so under the 2002 rule they constitute fill material.

    67 FR 31129, 31136-31137 (May 9, 2002), preamble sec. D ('The Final Rule and the Resource Investments Decision') [27]
    Show the source text
    Neither the solid waste itself nor the liner consisting of layers of gravel and low-permeability soil constituted ``fill material'' under Corps regulations ... fills typically serve some other purpose than just creating dry land or raising a water's bottom elevation ... The placement of berms, liners and other infrastructure (such as roads) associated with construction of a solid waste landfill in waters of the U.S. has the effect of replacing water with dry land or raising the bottom elevation of a water. Therefore, under today's rule, they constitute fill material.
    Open U.S. Army Corps of Engineers and U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • The 2002 fill-rule preamble states that the rule generally is intended to maintain the agencies' existing approach to regulating pollutants under either section 402 or section 404; that, recognizing that some discharges (such as suspended or settleable solids) can have the associated effect, over time, of raising the bottom elevation of a water due to settling of waterborne pollutants, the agencies do not consider such pollutants to be 'fill material'; and that discharges subject to an effluent limitation guideline and standards will continue to be regulated under section 402.

    67 FR 31129, 31135 (May 9, 2002), preamble sec. 'Effluent Guideline Limitations and 402 Permits' [27]
    Show the source text
    today's rule generally is intended to maintain our existing approach to regulating pollutants under either section 402 or 404 of the CWA. ... Recognizing that some discharges (such as suspended or settleable solids) can have the associated effect, over time, of raising the bottom elevation of a water due to settling of waterborne pollutants, we do not consider such pollutants to be ``fill material,'' ... discharges that are subject to an effluent limitation guideline and standards, which will continue to be regulated under section 402 of the CWA.
    Open U.S. Army Corps of Engineers and U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • ExemptionThe Corps' regulation lists 'construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance (but not construction) of drainage ditches' among discharges not requiring a section 404 permit, subject to the toxic-pollutant and recapture exceptions in 33 CFR 323.4(b) and (c).

    33 CFR 323.4(a)(3) [4]
    Show the source text
    (a) General. Except as specified in paragraphs (b) and (c) of this section, any discharge of dredged or fill material that may result from any of the following activities is not prohibited by or otherwise subject to regulation under section 404: ... (3) Construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance (but not construction) of drainage ditches.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • RequirementEven for an otherwise exempt activity (such as farm or stock pond construction or maintenance), if the discharge of dredged or fill material contains any toxic pollutant listed under CWA section 307, the discharge is subject to any applicable toxic effluent standard or prohibition and requires a section 404 permit.

    33 CFR 323.4(b); see also 40 CFR 232.3(a) [4]
    Show the source text
    (b) If any discharge of dredged or fill material resulting from the activities listed in paragraphs (a) (1) through (6) of this section contains any toxic pollutant listed under section 307 of the CWA such discharge shall be subject to any applicable toxic effluent standard or prohibition, and shall require a section 404 permit.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • RequirementThe Corps' recapture regulation requires a permit for an otherwise exempt discharge that is part of an activity whose purpose is to convert an area of waters of the United States to a use to which it was not previously subject, where flow or circulation may be impaired or reach reduced; where a discharge will result in significant discernible alterations to flow or circulation, flow or circulation is presumed to be impaired. On bottom elevation, the regulation says a discharge that elevates the bottom of waters of the United States without converting it to dry land 'does not thereby reduce the reach of, but may alter the flow or circulation of,' those waters.

    33 CFR 323.4(c) [4]
    Show the source text
    must have a permit if it is part of an activity whose purpose is to convert an area of the waters of the United States into a use to which it was not previously subject, where the flow or circulation ... may be impaired or the reach of such waters reduced. ... significant discernible alterations to flow or circulation, the presumption is that flow or circulation may be impaired by such alteration. ... A discharge which elevates the bottom of waters of the United States without converting it to dry land does not thereby reduce the reach of, but may alter the flow or circulation of,
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • ProcessNWP 3 (Maintenance, 2026) paragraph (a) authorizes the repair, rehabilitation, or replacement of any previously authorized, currently serviceable structure or fill, provided it is not put to uses differing from those specified or contemplated in the original permit (or the most recently authorized modification, per the full text); minor deviations in the structure's configuration or filled area, including those due to changes in materials, that are necessary to make the repair, rehabilitation, or replacement are authorized. A Note states that NWP 3 authorizes repair, rehabilitation, or replacement of any previously authorized structure or fill that does not qualify for the section 404(f) maintenance exemption.

    Applies when: Structures or fills previously authorized by the Corps (or authorized by 33 CFR 330.3) in waters of the United States. NWP 3(a), Notification and Note, 91 FR 768, 858-859 (Jan. 8, 2026) [14]
    Show the source text
    any previously authorized, currently serviceable structure or fill ... not to be put to uses differing from those uses specified or contemplated for it in the original permit ... Minor deviations in the structure's configuration or filled area, including those due to changes in materials ... that are necessary to make the repair, rehabilitation, or replacement are authorized. ... authorizes the repair, rehabilitation, or replacement of any previously authorized structure or fill that does not qualify for the Clean Water Act Section 404(f) exemption for maintenance.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • DefinitionFor NWP thresholds, 'loss of waters of the United States' means waters permanently adversely affected by filling, flooding, excavation, or drainage because of the regulated activity; permanent adverse effects include permanent discharges of dredged or fill material that change an aquatic area to dry land, increase the bottom elevation of a waterbody, or change the use of a waterbody. Waters temporarily filled, flooded, excavated, or drained but restored to pre-construction contours and elevations after construction are not counted.

    2026 NWP Definitions, 'Loss of waters of the United States', 91 FR 768, 884 (Jan. 8, 2026) [14]
    Show the source text
    Waters of the United States that are permanently adversely affected by filling, flooding, excavation, or drainage because of the regulated activity. ... Permanent adverse effects include permanent discharges of dredged or fill material that change an aquatic area to dry land, increase the bottom elevation of a waterbody, or change the use of a waterbody. ... Waters of the United States temporarily filled, flooded, excavated, or drained, but restored to pre-construction contours and elevations after construction, are not included in the measurement of loss
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementEPA's rule on which products must be registered (40 CFR 152.15), whose registration requirement is subject to 40 CFR 152.20, 152.25 and 152.30: a substance is considered intended for a pesticidal purpose, and thus a pesticide requiring registration, if (a) the person who distributes or sells it claims, states, or implies (by labeling or otherwise) that it can or should be used as a pesticide (or, per the full text, that it contains an active ingredient that can be used to manufacture a pesticide); (b) it consists of or contains one or more active ingredients and has no significant commercially valuable use as distributed or sold other than pesticidal use or use to manufacture a pesticide (per the full text); or (c) the person who distributes or sells it has actual or constructive knowledge that it will be used, or is intended to be used, for a pesticidal purpose.

    40 CFR 152.15 [30]
    Show the source text
    except as provided in §§ 152.20, 152.25, and 152.30. ... to be a pesticide requiring registration, if: (a) The person who distributes or sells the substance claims, states, or implies (by labeling or otherwise): (1) That the substance ... can or should be used as a pesticide; ... (b) The substance consists of or contains one or more active ingredients and has no significant commercially valuable use as distributed or sold other than ... (c) ... has actual or constructive knowledge that the substance will be used, or is intended to be used, for a pesticidal purpose.
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • DefinitionEPA's rules declare an organism to be a pest, under circumstances that make it deleterious to man or the environment, if it is any vertebrate animal other than man; any invertebrate animal such as an insect, other arthropod, nematode, or mollusk such as a slug and snail (excluding internal parasites of living man or other living animals); or any plant growing where not wanted, including any moss, alga, liverwort, or other plant of any higher order. Under that rule, algae and other plants growing where not wanted are pests when the circumstances make them deleterious to man or the environment.

    40 CFR 152.5 [30]
    Show the source text
    An organism is declared to be a pest under circumstances that make it deleterious to man or the environment, if it is: (a) Any vertebrate animal other than man; (b) Any invertebrate animal, including but not limited to, any insect, other arthropod, nematode, or mollusk such as a slug and snail, but excluding any internal parasite of living man or other living animals; (c) Any plant growing where not wanted, including any moss, alga, liverwort, or other plant of any higher order, and any plant part such as a root;
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • RequirementEPA states that, as a result of a Sixth Circuit decision, point source discharges to waters of the United States from pesticide applications have required NPDES permits since October 31, 2011; permits are required for any point source discharge to waters of the United States from the application of (1) biological pesticides and (2) chemical pesticides that leave a residue, and the CWA gives EPA no authority to exclude small 'de minimis' or short-term discharges.

    Applies when: Only if the product applied is a pesticide (for example, a product with algae- or weed-control claims) and the pond is a water of the United States. EPA, Pesticide Permitting - Frequent Questions (last updated March 31, 2026) [31]
    Show the source text
    As a result of the Sixth Circuit’s decision, point source discharges to waters of the United States from the application of pesticides require NPDES permits as of October 31, 2011. ... permits are required for any point source discharge to waters of the United States from the application of (1) biological pesticides and (2) chemical pesticides that leave a residue. ... The Clean Water Act (CWA) does not provide EPA with the authority to exclude certain types of discharges from the need to obtain permit coverage, such as small “de minimus” or short-term discharges,
    Open U.S. EPA (opens in a new tab)
More detail: 31 more verified statements on the federal permit status of sealing and lining
  • DefinitionEPA's section 404 regulations use the same effects-based definition of 'fill material' (material placed in waters of the United States that replaces any portion of a water with dry land or changes the bottom elevation of any portion of a water), with the same examples, including soil, clay and plastics.

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. 40 CFR 232.2 (definition of 'Fill material') [26]
    Show the source text
    Fill material. ... (1) Except as specified in paragraph (3) of this definition, the term fill material means material placed in waters of the United States where the material has the effect of: (i) Replacing any portion of a water of the United States with dry land; or (ii) Changing the bottom elevation of any portion of a water of the United States. (2) Examples of such fill material include, but are not limited to: rock, sand, soil, clay, plastics,
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • DefinitionCorps definition of 'fill material': material placed in waters of the United States that has the effect of replacing any portion of a water of the United States with dry land, or changing the bottom elevation of any portion of a water of the United States; examples include rock, sand, soil, clay, plastics, construction debris, wood chips and overburden; trash or garbage is not fill material.

    33 CFR 323.2(e)(1)-(3) [4]
    Show the source text
    (1) Except as specified in paragraph (e)(3) of this section, the term fill material means material placed in waters of the United States where the material has the effect of: (i) Replacing any portion of a water of the United States with dry land; or (ii) Changing the bottom elevation of any portion of a water of the United States. (2) Examples of such fill material include, but are not limited to: rock, sand, soil, clay, plastics, construction debris, wood chips, overburden from mining or other excavation activities ... (3) The term fill material does not include trash or garbage.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • Definition'Discharge of dredged material' includes any addition, including redeposit other than incidental fallback, of dredged material (including excavated material) into waters of the United States that is incidental to any activity, including mechanized landclearing, ditching, channelization, or other excavation (33 CFR 323.2(d)(1)(iii)). The exception in 33 CFR 323.2(d)(3)(i) for certain incidental additions does not apply to a person preparing to undertake mechanized landclearing, ditching, channelization or other excavation activity in a water of the United States which would result in a redeposit of dredged material, unless the person demonstrates to the satisfaction of the Corps (or EPA, as appropriate), before commencing the activity, that it would not have the effect of destroying or degrading any area of waters of the United States; the person bears the burden of that demonstration (see next claim for 'destroy' and 'degrade').

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. 33 CFR 323.2(d)(1)(iii), (d)(3)(i) [4]
    Show the source text
    Any addition, including redeposit other than incidential fallback, of dredged material, including excavated material, into waters of the United States which is incidental to any activity, including mechanized landclearing, ditching, channelization, or other excavation. ... this exception does not apply to any person preparing to undertake mechanized landclearing ... which would result in a redeposit of dredged material, unless the person demonstrates ... prior to commencing the activity ... that the activity would not have the effect of destroying or degrading any area ... bears the burden
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • DefinitionFor the redeposit rules, an activity 'destroys' an area of waters of the United States if it alters the area so that it would no longer be a water of the United States, and 'degrades' an area if it has more than a de minimis (inconsequential) effect by causing an identifiable individual or cumulative adverse effect on any aquatic function. A regulatory note adds that unauthorized discharges do not eliminate Clean Water Act jurisdiction, even where they have the effect of destroying waters of the United States.

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. 33 CFR 323.2(d)(4)-(5) and Note [4]
    Show the source text
    destroys an area of waters of the United States if it alters the area in such a way that it would no longer be a water of the United States. Note: Unauthorized discharges into waters of the United States do not eliminate Clean Water Act jurisdiction, even where such unauthorized discharges have the effect of destroying waters of the United States. ... degrades an area of waters of the United States if it has more than a de minimis (i.e., inconsequential) effect on the area by causing an identifiable individual or cumulative adverse effect on any aquatic function.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • DefinitionThe section 404 regulations define 'plowing' (an exempt normal farming activity) as all forms of primary tillage, including discing and harrowing, used on farm, forest or ranch land to break up, cut, turn over or stir soil to prepare it for planting crops. Plowing does not include redistributing soil, rock, sand or other surface materials in a way that changes any area of waters of the United States to dry land. As defined, plowing never involves a discharge of dredged or fill material.

    Applies when: Normal farming exemption; must be part of an established farming, silviculture or ranching operation (33 CFR 323.4(a)(1)(ii)). 33 CFR 323.4(a)(1)(iii)(D) [4]
    Show the source text
    (D) Plowing means all forms of primary tillage, including moldboard, chisel, or wide-blade plowing, discing, harrowing and similar physical means utilized on farm, forest or ranch land for the breaking up, cutting, turning over, or stirring of soil to prepare it for the planting of crops. The term does not include the redistribution of soil, rock, sand, or other surficial materials in a manner which changes any area of the waters of the United States to dry land. ... Plowing as described above will never involve a discharge of dredged or fill material.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • The Corps and EPA adopted identical definitions of 'fill material' in both agencies' regulations in a joint final rule published May 9, 2002 (effective June 10, 2002). The rule defines fill material as material placed in waters of the U.S. that has the effect of either replacing any portion of a water of the United States with dry land or changing the bottom elevation of any portion of a water, lists examples including rock, sand, soil, clay, plastics, construction debris and wood chips, and retains the effects-based approach of the April 2000 proposal.

    67 FR 31129-31130 (May 9, 2002), Summary; Effective Date [27]
    Show the source text
    Today's final rule defines ``fill material'' in both the Corps' and EPA's regulations as material placed in waters of the U.S. where the material has the effect of either replacing any portion of a water of the United States with dry land or changing the bottom elevation of any portion of a water. The examples of ``fill material'' identified in today's rule include rock, sand, soil, clay, plastics, construction debris, wood chips, ... This rule retains the effects-based approach ... EFFECTIVE DATE: June 10, 2002.
    Open U.S. Army Corps of Engineers and U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • Corps/EPA 2002 fill-rule preamble: recognizing that some discharges (such as suspended or settleable solids) can over time raise the bottom elevation of a water as waterborne pollutants settle, the agencies said they do not consider such pollutants to be 'fill material'; discharges subject to effluent limitation guidelines continue to be regulated under section 402.

    67 FR 31129, 31135 (May 9, 2002), preamble sec. 'f. Effluent Guideline Limitations and 402 Permits' [27]
    Show the source text
    Recognizing that some discharges (such as suspended or settleable solids) can have the associated effect, over time, of raising the bottom elevation of a water due to settling of waterborne pollutants, we do not consider such pollutants to be ``fill material,'' and nothing in today's rule changes that view. Nor does today's rule change any determination we have made regarding discharges that are subject to an effluent limitation guideline and standards, which will continue to be regulated under section 402 of the CWA.
    Open U.S. Army Corps of Engineers and U.S. EPA / Federal Register (govinfo) (opens in a new tab)
  • StatusLoper Bright (2024) overruled Chevron, but stated that it does not call into question prior cases that relied on the Chevron framework; the holdings of those cases that specific agency actions are lawful remain subject to statutory stare decisis.

    Loper Bright Enterprises v. Raimondo, 603 U.S. ___ (2024), slip op. at 34-35 [24]
    Show the source text
    By doing so, however, we do not call into question prior cases that relied on the Chevron framework. The holdings of those cases that specific agency actions are lawful—including the Clean Air Act holding of Chevron itself—are still subject to statutory stare decisis despite our change in interpretive methodology. ... Chevron is overruled.
    Open Supreme Court of the United States (opens in a new tab)
  • Definition'Dry land' in the exclusions means areas of the landscape that do not include waters such as streams, rivers, wetlands, lakes, ponds, tidal waters, ditches, and the like; jurisdictional and non-jurisdictional waters are not considered 'dry land' just because they lack water at a given time, and an area may remain 'dry land' even if it is wet after a rain.

    88 FR 3004, 3111-3112 (Jan. 18, 2023) (preamble) [6]
    Show the source text
    The term ``dry land'' refers to areas of the geographic landscape that do not include waters such as streams, rivers, wetlands, lakes, ponds, tidal waters, ditches, and the like. It is important to note that jurisdictional and non-jurisdictional waters are not considered ``dry land'' just because they lack water ... at a given time. Similarly, an area may remain ``dry land'' even if it is wet after a precipitation event.
    Open Federal Register (govinfo) (opens in a new tab)
  • Waterfilled depressions created in dry land incidental to construction activity, and pits excavated in dry land to obtain fill, sand, or gravel, are excluded 'unless and until the construction or excavation operation is abandoned and the resulting body of water meets the definition of waters of the United States'.

    Applies when: States where the Amended 2023 Rule is operative. 33 CFR 328.3(b)(7) [5]
    Show the source text
    (7) Waterfilled depressions created in dry land incidental to construction activity and pits excavated in dry land for the purpose of obtaining fill, sand, or gravel unless and until the construction or excavation operation is abandoned and the resulting body of water meets the definition of waters of the United States;
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • ExemptionEPA's parallel regulation likewise exempts construction or maintenance of farm or stock ponds from section 404 permit requirements, except as specified for toxic pollutants (40 CFR 232.3(a)) and recapture (40 CFR 232.3(b)).

    40 CFR 232.3(c)(3) [26]
    Show the source text
    (c) The following activities are exempt from section 404 permit requirements, except as specified in paragraphs (a) and (b) of this section: ... (3) Construction or maintenance of farm or stock ponds or irrigation ditches or the maintenance (but not construction) of drainage ditches.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • RequirementRecapture (CWA section 404(f)(2)): any discharge of dredged or fill material into navigable waters incidental to any activity whose purpose is bringing an area of the navigable waters into a use to which it was not previously subject, where the flow or circulation of navigable waters may be impaired or the reach of such waters reduced, requires a section 404 permit.

    33 U.S.C. 1344(f)(2) [10]
    Show the source text
    (2) Any discharge of dredged or fill material into the navigable waters incidental to any activity having as its purpose bringing an area of the navigable waters into a use to which it was not previously subject, where the flow or circulation of navigable waters may be impaired or the reach of such waters be reduced, shall be required to have a permit under this section.
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • ExemptionA separate 404(f) exemption covers maintenance, including emergency reconstruction of recently damaged parts, of currently serviceable structures such as dikes and dams; maintenance does not include any modification that changes the character, scope, or size of the original fill design, and emergency reconstruction must occur within a reasonable time after the damage.

    Applies when: Embankment (dammed) ponds whose dam or pond is in waters of the United States. 33 CFR 323.4(a)(2) [4]
    Show the source text
    (2) Maintenance, including emergency reconstruction of recently damaged parts, of currently serviceable structures such as dikes, dams, levees, groins, riprap, breakwaters, causeways, bridge abutments or approaches, and transportation structures. Maintenance does not include any modification that changes the character, scope, or size of the original fill design. Emergency reconstruction must occur within a reasonable period of time after damage occurs in order to qualify for this exemption.
    Open eCFR (Office of the Federal Register) (opens in a new tab)
  • ExemptionDischarges of dredged or fill material into waters of the United States that are regulated under CWA section 404 do not require NPDES (section 402) permits. EPA's NPDES rules also exclude any introduction of pollutants from non-point-source agricultural and silvicultural activities (including storm water runoff from orchards, cultivated crops, pastures, range lands and forest lands), but that exclusion does not cover discharges from concentrated animal feeding operations, discharges to aquaculture projects, or certain other listed point sources; return flows from irrigated agriculture are also excluded.

    40 CFR 122.3(b), (e), (f) [15]
    Show the source text
    The following discharges do not require NPDES permits: ... (b) Discharges of dredged or fill material into waters of the United States which are regulated under section 404 of CWA. ... (e) Any introduction of pollutants from non point-source agricultural and silvicultural activities, including storm water runoff from orchards, cultivated crops, pastures, range lands, and forest lands, but not discharges from concentrated animal feeding operations ... discharges to aquaculture projects ... (f) Return flows from irrigated agriculture.
    Open eCFR (opens in a new tab)
  • StatusThe current (2026) nationwide permits: the Corps reissued 56 NWPs and issued one new NWP (57 total), with general conditions and definitions, effective March 15, 2026 and expiring March 15, 2031.

    91 FR 768 (Jan. 8, 2026), Summary and DATES [14]
    Show the source text
    the U.S. Army Corps of Engineers (Corps) is reissuing 56 existing nationwide permits (NWPs), general conditions, and definitions, with some modifications. The Corps is also issuing one new NWP. DATES: The 57 NWPs, the general conditions, and the associated definitions will go into effect on March 15, 2026. The NWPs will expire on March 15, 2031.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessNWP 18 (Minor Discharges, 2026) authorizes minor discharges of dredged or fill material into all waters of the United States if (a) the discharged material and the volume excavated do not exceed 25 cubic yards below the ordinary high water mark; (b) the discharge will not cause the loss of more than 1/10 acre of waters of the United States; and (c) the discharge is not placed for the purpose of a stream diversion. A pre-construction notification (PCN) is required if the discharge or excavated volume exceeds 10 cubic yards (below the ordinary high water mark, per the full text), or if the discharge is in a special aquatic site, including wetlands.

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. NWP 18, 91 FR 768, 862 (Jan. 8, 2026) [14]
    Show the source text
    Minor discharges of dredged or fill material into all waters of the United States ... (a) The quantity of discharged dredged or fill material and the volume of area excavated do not exceed 25 cubic yards below the plane of the ordinary high water mark ... ... will not cause the loss of more than \1/10\-acre of waters of the United States; and (c) ... not placed for the purpose of a stream diversion. ... if: (1) the discharge of dredged or fill material or the volume of area excavated exceeds 10 cubic yards ... or (2) ... is in a special aquatic site, including wetlands.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessNWP 33 (Temporary Construction, Access, and Dewatering, 2026) authorizes temporary structures, work and discharges of dredged or fill material, including cofferdams, necessary for construction activities, access fills or dewatering of construction sites where the associated primary activity is authorized by the Corps or the U.S. Coast Guard, and also authorizes them for construction activities not otherwise subject to Corps or Coast Guard permit requirements. After construction, temporary fill must be entirely removed; the NWP does not authorize the use of cofferdams to dewater wetlands or other aquatic areas to change their use. A PCN is required if the activity is conducted in navigable waters of the United States (section 10 waters, per the full text).

    Applies when: Only where the pond (or the area worked in) is a 'water of the United States'. NWP 33, 91 FR 768, 866 (Jan. 8, 2026) [14]
    Show the source text
    Temporary structures, work, and discharges of dredged or fill material, including cofferdams, necessary for construction activities ... provided that the associated primary activity is authorized by the Corps of Engineers or the U.S. Coast Guard. This NWP also authorizes ... construction activities not otherwise subject to the Corps or U.S. Coast Guard permit requirements. ... temporary fill must be entirely removed ... does not authorize the use of cofferdams to dewater wetlands or other aquatic areas to change their use. ... conducted in navigable waters of the United States
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessNWP 40 (Agricultural Activities, 2026) authorizes construction of farm ponds in non-tidal waters of the United States, excluding perennial streams, provided the farm pond is used solely for agricultural purposes; it does not authorize the construction of aquaculture ponds. The discharge may not cause the loss of more than 1/2 acre of non-tidal waters of the United States, and a PCN must be submitted before starting. A Note says NWP 40 authorizes farm ponds that do not qualify for the 404(f)(1)(C) exemption because of the 404(f)(2) recapture provision.

    Applies when: Farm pond construction in non-tidal waters of the United States. NWP 40 and Note, 91 FR 768, 868 (Jan. 8, 2026) [14]
    Show the source text
    This NWP also authorizes the construction of farm ponds in non-tidal waters of the United States, excluding perennial streams, provided the farm pond is used solely for agricultural purposes. This NWP does not authorize the construction of aquaculture ponds. ... The discharge must not cause the loss of greater than\1/2\-acre of non-tidal waters of the United States. ... must submit a pre-construction notification ... authorizes the construction of farm ponds that do not qualify for the Clean Water Act section 404(f)(1)(C) exemption because of the recapture provision
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementNWP General Condition 6 (Suitable Material): no NWP activity may use unsuitable material (e.g., trash, debris, car bodies, asphalt), and material used for construction or discharged must be free from toxic pollutants in toxic amounts (see CWA section 307).

    Applies when: Any activity authorized by a 2026 NWP. 2026 NWP General Condition 6, 91 FR 768, 876 (Jan. 8, 2026) [14]
    Show the source text
    6. Suitable Material. No activity may use unsuitable material (e.g., trash, debris, car bodies, asphalt, etc.). Material used for construction or discharged must be free from toxic pollutants in toxic amounts (see section 307 of the Clean Water Act).
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementNWP General Condition 12 (Soil Erosion and Sediment Controls): appropriate erosion and sediment controls must be used and maintained during construction; exposed soil, other fills and any work below the ordinary high water mark must be permanently stabilized at the earliest practicable date; permittees are encouraged to work in waters during low-flow or no-flow periods.

    Applies when: Any activity authorized by a 2026 NWP. 2026 NWP General Condition 12, 91 FR 768, 876 (Jan. 8, 2026) [14]
    Show the source text
    12. Soil Erosion and Sediment Controls. Appropriate soil erosion and sediment controls must be used and maintained in effective operating condition during construction, and all exposed soil and other fills, as well as any work below the ordinary high water mark or high tide line, must be permanently stabilized at the earliest practicable date. Permittees are encouraged to perform work within waters of the United States during periods of low-flow or no-flow, or during low tides.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • RequirementNWP General Condition 25 (Water Quality): where the certifying authority has not previously certified an NWP under CWA section 401, a section 401 water quality certification must be obtained or waived for a proposed activity that may result in a point-source discharge into waters of the United States; if the activity requires a PCN and the NWP was not previously certified, it is not authorized by the NWP until certification is obtained or waived.

    Applies when: Any activity authorized by a 2026 NWP. 2026 NWP General Condition 25(a)-(b), 91 FR 768, 880 (Jan. 8, 2026) [14]
    Show the source text
    has not previously certified compliance of an NWP with CWA section 401, a CWA section 401 water quality certification for the proposed activity which may result in any discharge from a point source into waters of the United States must be obtained or waived ... If the NWP activity requires pre-construction notification and the certifying authority has not previously certified compliance of an NWP with CWA section 401, the proposed activity ... is not authorized by an NWP until water quality certification is obtained or waived.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • ProcessNWP General Condition 32 (PCN timing): the district engineer must decide within 30 calendar days whether a PCN is complete; absent written notice, the applicant may proceed once 45 calendar days have passed from the district's receipt of a complete PCN. Where the Corps must be notified that listed species or historic properties may be affected, work cannot begin until the Corps gives written notice of 'no effect' on listed species or 'no potential to cause effects' on historic properties, or required ESA section 7 consultation (or NHPA section 106 consultation) is completed.

    Applies when: NWP activities that require a PCN. 2026 NWP General Condition 32(a), 91 FR 768, 881 (Jan. 8, 2026) [14]
    Show the source text
    The district engineer must determine if the PCN is complete within 30 calendar days of the date of receipt ... (2) 45 calendar days have passed from the district engineer's receipt of the complete PCN and the prospective permittee has not received written notice ... the permittee cannot begin the activity until receiving written notification from the Corps that there is ``no effect'' on listed species or ``no potential to cause effects'' on historic properties, or that any consultation required under Section 7 of the Endangered Species Act ... has been completed.
    Open Federal Register / U.S. Army Corps of Engineers (opens in a new tab)
  • DefinitionUnder FIFRA, a 'pesticide' is (1) any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, (2) any substance or mixture of substances intended for use as a plant regulator, defoliant, or desiccant, and (3) any nitrogen stabilizer (the full text excepts certain animal drugs and feeds and liquid chemical sterilants). A 'pest' means (1) any insect, rodent, nematode, fungus, or weed, or (2) any other form of terrestrial or aquatic plant or animal life or virus, bacteria, or other micro-organism that EPA declares to be a pest.

    7 U.S.C. 136(t), (u) (FIFRA sec. 2(t), (u)) [32]
    Show the source text
    The term "pest" means (1) any insect, rodent, nematode, fungus, weed, or (2) any other form of terrestrial or aquatic plant or animal life or virus, bacteria, or other micro-organism ... which the Administrator declares to be a pest ... The term "pesticide" means (1) any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, (2) any substance or mixture of substances intended for use as a plant regulator, defoliant, or desiccant, and (3) any nitrogen stabilizer,
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • RequirementFIFRA section 3(a): except as provided by the Act, no person in any State may distribute or sell to any person any pesticide that is not registered under FIFRA.

    7 U.S.C. 136a(a) [29]
    Show the source text
    Except as provided by this subchapter, no person in any State may distribute or sell to any person any pesticide that is not registered under this subchapter.
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • ExemptionA product that is not intended to prevent, destroy, repel, or mitigate a pest, or to defoliate, desiccate or regulate the growth of plants, is not considered a pesticide. The rule lists types of products that are not pesticides unless a pesticidal claim is made on their labeling or in connection with their sale and distribution, including deodorizers, bleaches and cleaning agents, and products that exclude pests only by providing a physical barrier and contain no toxicants.

    Applies when: Relevant to products sold without pesticidal claims; 40 CFR 152.10 does not name pond sealants. 40 CFR 152.10 [30]
    Show the source text
    A product that is not intended to prevent, destroy, repel, or mitigate a pest, or to defoliate, desiccate or regulate the growth of plants, is not considered to be a pesticide. The following types of products or articles are not considered to be pesticides unless a pesticidal claim is made on their labeling or in connection with their sale and distribution: (a) Deodorizers, bleaches, and cleaning agents; ... (c) Products that are intended to exclude pests only by providing a physical barrier against pest access, and which contain no toxicants,
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • DefinitionEPA's rules separately list products that are not pesticides because they are not for use against pests: a fertilizer product not containing a pesticide, and a product intended to force bees from hives for the collection of honey crops.

    40 CFR 152.8 [30]
    Show the source text
    A substance or article is not a pesticide, because it is not intended for use against “pests” as defined in § 152.5, if it is: (a) A fertilizer product not containing a pesticide. (b) A product intended to force bees from hives for the collection of honey crops.
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • AgencyEPA's Label Review Manual (Chapter 2, revised January 2021) explains that a product is considered a pesticide if the person who distributes or sells it claims, states, or implies by labeling or otherwise, including advertising, collateral literature, or verbal statements, that it can or should be used as a pesticide; even without an express claim, a product composed of one or more active ingredients with no other significant commercially valuable use is a pesticide.

    EPA Label Review Manual, Chapter 2: What is a Pesticide? (rev. Jan. 2021), sec. II.A-B, p. 2-2 [33]
    Show the source text
    If a person who distributes or sells the product claims, states, or implies by labeling or otherwise (such as, advertising, collateral literature, or verbal statements) that the product can or should be used as a pesticide ... then the product is considered a pesticide ... Even in the absence of an expressed claim, if a product is composed of one or more active ingredients and has no other significant commercially valuable use other than (1) for a pesticidal purpose or (2) for use in manufacturing a pesticide, then the product is considered a pesticide.
    Open U.S. EPA, Office of Pesticide Programs (opens in a new tab)
  • AgencyEPA's Label Review Manual illustrates that the same product can be a pesticide or not depending on its claims: a bleach containing 5.25% sodium hypochlorite requires registration if its label states bacteria will be killed at certain doses, but a bleach with the same composition need not be registered if the label only claims to whiten, bleach, or clean and has no explicit or implicit antimicrobial claim. Physical-barrier products with no toxicants (e.g., black plastic or tar paper used to suppress weeds) are listed among products that are not pesticides absent pesticidal claims.

    EPA Label Review Manual, Chapter 2 (rev. Jan. 2021), sec. III.F.1 and III.F.3 [33]
    Show the source text
    a bleach product containing 5.25% sodium hypochlorite would require registration if the label states that bacteria will be killed at certain doses. In contrast, a bleach product with the same composition would not need to be registered if the label only claims to whiten, bleach, or clean laundry, and does not contain an explicit or implicit antimicrobial claim. ... Products that contain no toxicants and are intended to exclude pests only by providing a physical barrier against pest access. ... black plastic or tar paper used to suppress weeds
    Open U.S. EPA, Office of Pesticide Programs (opens in a new tab)
  • EPA's Pesticide General Permit FAQ gives, as an example of a pesticide application activity that is not eligible for coverage under EPA's Pesticide General Permit (PGP), alum used to control phosphorus levels in the water as a way to inhibit algae growth (as an algaestat, not as an algaecide), and says pesticide activities not eligible for the PGP may require an NPDES individual permit.

    EPA, Pesticide Permitting - Frequent Questions (last updated March 31, 2026), 'Is EPA's PGP available only for FIFRA registered products?' [31]
    Show the source text
    If a pesticide is being applied for a different reason, for example, clove oil being used to stun fish for collection purposes, or alum used to control phosphorus levels in the water as a way to inhibit algae growth (as an algaestat, not as an algaecide), that activity is not eligible for coverage under EPA’s PGP. Pesticide activities not eligible for coverage under EPA’s PGP may require an NPDES individual permit.
    Open U.S. EPA (opens in a new tab)
  • Within EPA's Construction General Permit (construction stormwater), treatment chemicals such as polymers, flocculants and coagulants may be applied only where treated stormwater is directed to a sediment control (for example a sediment basin or perimeter control) before discharge, and a permittee planning to add 'cationic treatment chemicals' may not file its Notice of Intent until it notifies the applicable EPA Regional Office and that office authorizes coverage. The 2022 CGP (as modified) expires at 11:59 pm on February 16, 2027.

    Applies when: Construction stormwater discharges covered by EPA's CGP (check whether EPA or the state is the NPDES permitting authority for the site). EPA 2022 Construction General Permit (as modified), Parts 1.1.9 and 2.2.13 [34]
    Show the source text
    This permit and the authorization to discharge expire at 11:59pm, February 16, 2027. ... If you plan to add “cationic treatment chemicals” (as defined in Appendix A) to stormwater and/or authorized non-stormwater prior to discharge, you may not submit your NOI until you notify your applicable EPA Regional Office ... and the EPA Regional Office authorizes coverage ... If using treatment chemicals (e.g., polymers, flocculants, coagulants): ... Chemicals may only be applied where treated stormwater is directed to a sediment control (e.g., sediment basin, perimeter control) before discharge.
    Open U.S. EPA (opens in a new tab)
  • DefinitionThe CGP defines 'treatment chemicals' as polymers, flocculants, or other chemicals used to reduce turbidity in stormwater, and 'cationic treatment chemicals' as polymers, flocculants, or other chemicals with an overall positive charge; common examples of cationic treatment chemicals are chitosan and cationic PAM.

    EPA 2022 CGP, Appendix A (Definitions) [17]
    Show the source text
    “Cationic Treatment Chemical” – polymers, flocculants, or other chemicals that contain an overall positive charge. ... Common examples of cationic treatment chemicals are chitosan and cationic PAM. ... “Treatment Chemicals” – polymers, flocculants, or other chemicals used to reduce turbidity in stormwater.
    Open U.S. EPA (opens in a new tab)

Not confirmed from a primary source

We could not confirm the following from an official source. Ask the agency listed before relying on any of it.

  • Whether spreading, mixing (discing or tilling) and compacting bentonite or other soil amendments into a drained pond bed, placing a compacted clay liner, or installing a geomembrane or geosynthetic clay liner in a pond that is a water of the United States is a discharge of fill material or dredged material. No Corps or EPA regulation, preamble, guidance letter, 2026 nationwide permit or district document found addresses pond sealing or lining. — ask: Corps district regulatory office (request a written determination or pre-application meeting); EPA regional wetlands (404) office
  • Whether the Section 404(f)(1)(C) exemption for maintenance of farm or stock ponds covers sealing or relining an existing farm or stock pond, and whether that work could be recaptured under 404(f)(2). The statute and regulations do not define pond maintenance. — ask: Corps district regulatory office; EPA regional office
  • Whether a Corps district would authorize pond sealing or lining under a 2026 nationwide permit (such as NWP 3 or NWP 18), and whether a sealing layer that raises the pond bottom counts as loss of waters of the United States toward nationwide permit limits. — ask: Corps district regulatory office; the state section 401 certifying agency
  • Whether applying bentonite (broadcast or as a slurry) or a two-part polymer or flocculant sealant through the water of a full pond that is a water of the United States needs an NPDES permit, is a Section 404 fill discharge, or is neither, and whether hand, spreader, pump or boat application is a point source. — ask: EPA regional NPDES office or the state NPDES permitting authority; Corps district regulatory office
  • Any EPA statement, outside the Construction General Permit's treatment-chemical provisions, on adding polymers, polyacrylamide or other flocculants directly to ponds, lakes or other surface waters. — ask: EPA regional NPDES office; state water quality agency
  • Whether any ingredient of a particular pond sealant (for example, residual acrylamide monomer in polyacrylamide) is a Section 307(a) toxic pollutant that would take an otherwise exempt discharge out of the 404(f) exemption or conflict with nationwide permit General Condition 6. — ask: EPA regional office; the product's safety data sheet
  • Whether EPA considers any pond-sealing product, bentonite or polymer, to be a pesticide, or whether marketing claims such as "clears water," "reduces nutrients" or "helps prevent algae" are pesticidal claims requiring FIFRA registration. — ask: EPA Office of Pesticide Programs (Registration Division); the state pesticide regulatory agency
  • Whether temporarily draining a pond that is a water of the United States to dry the bed for sealing changes its jurisdictional status, and whether sealing work in an excluded artificial pond can still need federal authorization for any discharge that leaves the pond. — ask: Corps district regulatory office (approved jurisdictional determination)

NRCS pond sealing and lining standards (CPS 520, 521, 522)

As retrieved September 28, 2026, NRCS's national practice standards index lists three pond sealing or lining standards with these version dates: Pond Sealing or Lining, Compacted Soil Treatment (Code 520), 05/2016; Pond Sealing or Lining, Concrete (Code 522), 05/2016; and Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 08/2023. [12]

The current CPS 520 (May 2016) defines Compacted Soil Treatment as a liner for an impoundment built of compacted soil with or without soil amendments to reduce seepage losses, and applies where in-place natural soils have excessive seepage rates and an adequate quantity and type of soil is available either for a compacted soil liner without amendments or for an amended liner treated with a soil dispersant or bentonite. The finished compacted liner must be at least the greatest of the thickness needed to meet a specific-discharge design value, a thickness required by state regulations, or the Table 1 minimum: 12 inches for a design storage depth of 16 feet or less, 18 inches for 16.1-24 feet and 24 inches for 24.1-30 feet. Side slopes should be 3H:1V or flatter when the "bathtub" construction method is used, and slopes as steep as 2H:1V can be considered with the "stair-step" method. [35]

CPS 520 requires bentonite to be sodium bentonite with a free swell of at least 22 milliliters measured by ASTM D5890, unless laboratory tests using other bentonite types are used for design. For clean water ponds without laboratory tests or field performance data on similar soils, the minimum bentonite rates per 1-inch lift are 0.375 lb/sq ft for silts (ML, CL-ML), 0.5 lb/sq ft for silty sands (SM, SC-SM, SP-SM) and 0.625 lb/sq ft for clean sand (SP, SW), installed in lifts no thicker than 6 inches; the minimum soil dispersant rates per 6-inch lift are 7.5 lbs per 100 sq ft for polyphosphate (TSPP, STPP) and 15 lbs per 100 sq ft for soda ash. A clean water pond liner is to be designed to reduce seepage to a rate that will allow the pond to function as intended, while a waste storage impoundment liner must meet specific discharge rates and requires laboratory testing. [35]

CPS 521 (August 2023 revision) covers geomembrane or geosynthetic clay liners where in-place natural soils have excessive seepage rates and lining or sealing is needed for water conservation or to protect surface or groundwater from contamination; its Table 1 lists minimum clear-water thicknesses including 30 mil for HDPE, LLDPE and PVC and 45 mil for EPDM, and 0.75 lbs./square foot for a geosynthetic clay liner. It requires PVC liners and geosynthetic clay liners to be covered with at least 12 inches of soil placed within 24 hours after liner placement and anchorage, and its considerations say PVC geomembranes are not recommended for aquatic production because stabilizers in the liner material leach out and may be harmful to aquatic species. CPS 522 (May 2016) covers liners of reinforced or nonreinforced concrete and requires the designer to select either "reduced seepage" or "liquid tight" criteria. [36][37]

PROPOSED, not final: on September 1, 2026 NRCS published a notice of availability and request for comments (91 FR 56102, Docket NRCS-2026-0100) on proposed revisions to 48 conservation practice standards, including 520 and 522, and will consider comments received by October 1, 2026. The notice says NRCS State Conservationists who choose to adopt these standards in their states will incorporate them into their state's electronic Field Office Technical Guide. [13]

The notice describes the proposed 520 changes as no major technical revisions; clarifications and readability edits; two added purposes; new criteria on compliance with applicable laws, safety and existing impoundment requirements; and a reduced minimum liner thickness for clean-water storage impoundments. The proposed September 2026 draft of 520 would keep the Table 1 minimum liner thicknesses by depth "unless the impoundment is for water storage where the minimum thickness is 12 inches at all depths," would keep the 22-milliliter bentonite specification and the same clean-water-pond rates with a 6-inch maximum lift, and would state that "The landowner or operator is responsible for obtaining all necessary permits and approvals prior to, during, and after construction of the facility." For 522, the notice says the only major technical revision is the addition of leak-detection requirements for installations in high-permeability soils. [13][38]

  • StatusNRCS's national Conservation Practice Standards index lists three pond sealing/lining standards with these current version dates: Pond Sealing or Lining, Compacted Soil Treatment (Code 520), unit square feet, dated 05/2016; Pond Sealing or Lining, Concrete (Code 522), dated 05/2016; and Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), dated 08/2023.

    NRCS, Conservation Practice Standards index (National Handbook of Conservation Practices) [12]
    Show the source text
    Pond Sealing or Lining, Compacted Soil Treatment (Sq.Ft). (520) 05/2016 Pond Sealing or Lining, Concrete (Sq.Ft) (522) 05/2016 Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Sq.Ft.) (521) 08/2023
    Open USDA NRCS (opens in a new tab)
  • DefinitionNRCS CPS 520 (national, May 2016) defines Pond Sealing or Lining - Compacted Soil Treatment as a liner for an impoundment constructed using compacted soil with or without soil amendments, installed to reduce seepage losses from impoundments constructed for water conservation and environmental protection.

    NRCS CPS Pond Sealing or Lining - Compacted Soil Treatment (Code 520), NHCP May 2016, Definition and Purpose, p. 520-CPS-1 [35]
    Show the source text
    DEFINITION A liner for an impoundment constructed using compacted soil with or without soil amendments. PURPOSE This practice is installed to reduce seepage losses from impoundments constructed for water conservation and environmental protection.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 520 applies where in-place natural soils have excessive seepage rates AND either (a) an adequate quantity and type of soil suitable for a compacted soil liner without amendments is available, or (b) an adequate quantity and type of soil suitable for treatment with a soil dispersant or bentonite amendment is available for an amended soil liner.

    NRCS CPS 520 (May 2016), Conditions Where Practice Applies, p. 520-CPS-1 [35]
    Show the source text
    This practice applies where— • In-place natural soils have excessive seepage rates, and • An adequate quantity and type of soil suitable for constructing a compacted soil liner without amendments is available, or • An adequate quantity and type of soil suitable for treatment with a soil dispersant or bentonite amendment is available for an amended soil liner.
    Open USDA NRCS (opens in a new tab)
  • Size cutoffCPS 520 minimum finished compacted liner thickness is the greatest of: the thickness needed to achieve a specific-discharge design value, a thickness required by State regulations, or the Table 1 minimum by design storage depth - 12 inches for depths of 16 ft or less, 18 inches for 16.1-24 ft, and 24 inches for 24.1-30 ft.

    NRCS CPS 520 (May 2016), Criteria - Liner Thickness and Table 1, pp. 520-CPS-1 to -2 [35]
    Show the source text
    Liner Thickness. The minimum thickness of the finished compacted liner must be the greater of— • The liner thickness required to achieve a specific discharge (unit seepage) design value, or ... A liner thickness required by State regulations, or • The minimum liner thickness as shown in table 1. Table 1. Minimum liner thickness by design storage depth. Design Storage Liner Thickness Depth (ft) (in) ≤16 12 16.1–24 18 24.1–30 24
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 520 bentonite material specification: bentonite must be sodium bentonite with a free swell of at least 22 milliliters measured by ASTM D5890, unless laboratory tests using other bentonite types are used for design. For waste storage impoundments, laboratory permeability tests using bentonite of the same quality and fineness as proposed are required.

    NRCS CPS 520 (May 2016), Additional Criteria for Bentonite Treatment - Bentonite Material; Application Rate, p. 520-CPS-3 [35]
    Show the source text
    Bentonite Material. The bentonite must be a sodium bentonite with a free swell of at least 22 milliliters as measured by ASTM Standard Test Method D5890, unless laboratory tests using other bentonite types are used for design. Application Rate. For waste storage impoundments, conduct laboratory permeability tests using bentonite of the same quality and fineness as that proposed for use.
    Open USDA NRCS (opens in a new tab)
  • Size cutoffCPS 520 minimum bentonite application rates for clean water ponds (used when there are no laboratory tests or field performance data on similar soils), in lbs per sq ft per 1-inch lift thickness: silts (ML, CL-ML) 0.375; silty sands (SM, SC-SM, SP-SM) 0.5; clean sand (SP, SW) 0.625. The liner is installed with a maximum 6-inch lift thickness.

    Applies when: Clean water ponds, absent laboratory tests or field performance data NRCS CPS 520 (May 2016), Additional Criteria for Bentonite Treatment - Application Rate, Table 3, p. 520-CPS-3 [35]
    Show the source text
    For clean water ponds, in the absence of laboratory tests or field performance data on soils similar to those to be treated, apply the bentonite at a rate equal to or greater to the amount listed in table 3. Install the liner with a maximum of 6-inch-lift thickness. Table 3. Minimum Bentonite Application Rates for Clean Water Ponds. ... Silts (ML, CL-ML) 0.375 Silty Sands (SM, SC- 0.5 SM, SP-SM) Clean Sand (SP, SW) 0.625
    Open USDA NRCS (opens in a new tab)
  • DefinitionNRCS CPS 521 (national, August 2023 revision) defines Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner as a liner for a water, wastewater, salt, manure, or similar agricultural by-product impoundment constructed using a geomembrane or geosynthetic clay material. It applies where in-place natural soils have excessive seepage rates and lining or sealing is needed for water conservation or to protect surface or groundwater from contamination.

    NRCS CPS Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), NHCP August 2023R, Definition; Conditions Where Practice Applies, p. 521-CPS-1 [36]
    Show the source text
    A liner for a water, wastewater, salt, manure, or similar agricultural by-product impoundment constructed using a geomembrane or a geosynthetic clay material. ... This practice applies where in-place natural soils have excessive seepage rates and pond lining or sealing is needed for water conservation or to protect surface or groundwater from contamination.
    Open USDA NRCS (opens in a new tab)
  • Size cutoffCPS 521 requires geomembrane and GCL materials to meet Table 1, which lists these minimum thicknesses in mil for clear water (wastewater value in parentheses): HDPE 30 (60); LLDPE 30 (60); LLDPE-R 24 (45); PVC 30 (40); EPDM 45 (45); FPP 30 (45); FPP-R 36 (45, marked with footnote 3, 'NR - Not recommended for waste storage'); PE-R 36 (NR - not recommended for waste storage). For a geosynthetic clay liner (GCL) the table lists 0.75 lbs./square foot. 1 mil = 1/1000 inch.

    NRCS CPS 521 (August 2023R), Materials, Table 1, p. 521-CPS-2 [36]
    Show the source text
    Geomembrane and geosynthetic clay liner (GCL) materials must meet the requirements in table 1. ... Type 1 Name Minimum Thickness (mil) 2 Wastewater Clear Water ... HDPE Polyethylene 60 30 ... LLDPE Polyethylene 60 30 ... LLDPE-R Polyethylene 45 24 PVC Polyvinyl Chloride 40 30 ... EPDM Diene Terpolymer 45 45 ... FPP Polypropylene 45 30 ... FPP-R Polypropylene 45 3 36 ... PE-R Polyethylene NR 3 36 ... GCL Liner 0.75 lbs./square foot ... 1 mil = 1/1000 inch 3 NR – Not recommended for waste storage.
    Open USDA NRCS (opens in a new tab)
  • DefinitionNRCS CPS 522 (national, May 2016) defines Pond Sealing or Lining - Concrete as a liner for an impoundment constructed using reinforced or nonreinforced concrete. Its 'Conditions Where Practice Applies' section lists three bulleted conditions, without saying whether all or any of them must be met: in-place natural soils have excessive seepage rates; construction of a compacted soil liner is not feasible with available soils; and use of the impoundment requires concrete both as a liner and a protective subgrade cover.

    NRCS CPS Pond Sealing or Lining - Concrete (Code 522), NHCP May 2016, Definition; Conditions Where Practice Applies, p. 522-CPS-1 [37]
    Show the source text
    A liner for an impoundment constructed using reinforced or nonreinforced concrete. ... This practice applies where— • In-place natural soils have excessive seepage rates. • Construction of a compacted soil liner is not feasible with available soils. • Use of impoundment requires concrete both as a liner and a protective subgrade cover.
    Open USDA NRCS (opens in a new tab)
  • StatusPROPOSED (not final): On September 1, 2026 NRCS published a notice of availability and request for comments (91 FR 56102-56106, FR Doc. 2026-17863, Docket No. NRCS-2026-0100) proposing revisions to 48 conservation practice standards, including Pond Sealing or Lining, Compacted Soil Treatment (Code 520) and Pond Sealing or Lining, Concrete (Code 522). Comments received by October 1, 2026 will be considered.

    91 FR 56102 (Sept. 1, 2026), FR Doc. 2026-17863, Docket No. NRCS-2026-0100 [13]
    Show the source text
    [Docket No. NRCS-2026-0100] Proposed Revisions to the National Handbook of Conservation Practices ... ACTION: Notice of availability, request for comments. ... DATES: We will consider comments that we receive by October 1, 2026. ... NRCS is requesting comments on the following 48 CPSs: ... Pond Sealing or Lining, Compacted Soil Treatment (Code 520); Pond Sealing or Lining, Concrete (Code 522);
    Open Federal Register / GPO govinfo (opens in a new tab)
  • StatusPROPOSED: The Sept. 1, 2026 notice describes the CPS 520 changes as: no major technical revisions; clarifications, examples and readability edits; two purposes added; new criteria on compliance with applicable laws, safety, and existing impoundment requirements; and a reduced minimum liner thickness for clean-water storage impoundments.

    91 FR 56102, 56105 (Sept. 1, 2026), Pond Sealing or Lining, Compacted Soil Treatment (Code 520) [13]
    Show the source text
    Pond Sealing or Lining, Compacted Soil Treatment (Code 520): No major technical revisions were made to this CPS. All updates were made to clarify content, provide examples, improve readability, and maintain consistency across paragraphs. Two purposes were added to the ``Purpose'' section, and new criteria were included in the ``Criteria'' section regarding compliance with applicable laws, safety, and existing impoundment requirements. The minimum liner thickness for clean-water storage impoundments was reduced in the ``Criteria'' section.
    Open Federal Register / GPO govinfo (opens in a new tab)
  • Size cutoffPROPOSED CPS 520 (draft dated September 2026, posted by NRCS for the Docket NRCS-2026-0100 comment period): the Table 1 minimum liner thickness by depth would remain (12 in for <=16 ft; 18 in for 16.1-24 ft; 24 in for 24.1-30 ft) 'unless the impoundment is for water storage where the minimum thickness is 12 inches at all depths.'

    Applies when: Proposed; water-storage (clean water) impoundments NRCS CPS 520, proposed draft "520 NHCP CPS Pond Sealing or Lining, Compacted Soil Treatment 2026 FR" (NHCP September 2026), Liner thickness, Table 1, p. 520-CPS-2 [38]
    Show the source text
    The minimum liner thickness as shown in Table 1 unless the impoundment is for water storage where the minimum thickness is 12 inches at all depths. Table 1. Minimum liner thickness by depth. Design Storage Depth (ft) Liner Thickness (in) ≤16 12 16.1–24 18 24.1 - 30 24
    Open USDA NRCS (opens in a new tab)
  • RequirementPROPOSED CPS 520 (Sept. 2026 draft) would add general criteria that the liner be planned, designed and constructed to comply with all federal, state, tribal and local laws and regulations, and that 'The landowner or operator is responsible for obtaining all necessary permits and approvals prior to, during, and after construction of the facility.' Its Purpose section would list three purposes: reduce seepage losses from impoundments constructed for water conservation including irrigation or water for livestock; reduce pollution to surface and groundwater, including potential drinking water sources; and protect soil and water from contaminants or erosion. (The Sept. 1, 2026 notice describes two purposes as added; the current 2016 standard has one purpose.)

    NRCS CPS 520, proposed draft (NHCP September 2026), Purpose; General Criteria Applicable to All Purposes, p. 520-CPS-1 [38]
    Show the source text
    Reduce seepage losses from impoundments constructed for water conservation including irrigation or water for livestock. • Reduce pollution to surface and groundwater, including potential drinking water sources. • Protect soil and water from contaminants or erosion. ... Plan, design, and construct the liner to comply with all federal, state, tribal, and local laws and regulations. The landowner or operator is responsible for obtaining all necessary permits and approvals prior to, during, and after construction of the facility.
    Open USDA NRCS (opens in a new tab)
  • StatusPROPOSED: The Sept. 1, 2026 notice says the only major technical revision to CPS 522 is the addition of leak-detection requirements for installations in high-permeability soils; two purposes were added and criteria added on compliance with applicable laws, safety, and existing impoundment requirements.

    91 FR 56102, 56105 (Sept. 1, 2026), Pond Sealing or Lining, Concrete (Code 522) [13]
    Show the source text
    Pond Sealing or Lining, Concrete (Code 522): The only major technical revision to this CPS was the addition of leak-detection requirements for installations in high-permeability soils. Other revisions throughout the CPS were made to clarify content, provide examples, improve readability, and maintain paragraph structure. Two purposes were added to the ``Purpose'' section, and additional criteria were included in the ``Criteria'' section to address compliance with applicable laws, safety, and existing impoundment requirements.
    Open Federal Register / GPO govinfo (opens in a new tab)
More detail: 16 more verified statements on NRCS pond sealing and lining standards
  • RequirementCPS 520 seepage design: a compacted soil liner for a clean water pond is designed to reduce seepage to a rate that will allow the pond to function as intended; by contrast, a liner for a waste storage impoundment must meet specific discharge rates in NEH Part 651 (AWMFH) Chapter 10, Appendix 10D (or more restrictive State rates), and laboratory testing of the liner material is required for waste storage impoundments.

    Applies when: Clean water pond vs. waste storage impoundment NRCS CPS 520 (May 2016), Criteria - Design Seepage Requirements, p. 520-CPS-1 [35]
    Show the source text
    Design a compacted soil liner for a waste storage impoundment to reduce specific discharge (unit seepage) to rates specified in the National Engineering Handbook (NEH), Part 651, Agricultural Waste Management Field Handbook (AWMFH), Chapter 10, Appendix 10D, or rates mandated in State regulations, if they are more restrictive. ... Laboratory testing of compacted soil liner material for a waste storage impoundment is required ... Design a compacted soil liner for a clean water pond to reduce seepage to a rate that will allow the pond to function as intended.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 520 side slopes should be 3H:1V or flatter to allow compaction on slopes when the 'bathtub' construction method is used; slopes as steep as 2H:1V can be considered with the 'stair-step' method (AWMFH Appendix 10D); steeper slopes can be designed for isolated areas if the slope is protected.

    NRCS CPS 520 (May 2016), Criteria - Side Slopes, p. 520-CPS-2 [35]
    Show the source text
    The side slopes of the impoundment should be 3H (horizontal) to 1V (vertical) or flatter to facilitate compaction of soil on the slopes when the “bathtub” method of construction is used, as described in AWMFH, Appendix 10D. Slopes as steep as 2H to 1V can be considered if the “stair-step” method of construction as described in appendix 10D of the AWMFH is used. Steeper side slopes can be designed for isolated areas if the slope is protected.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 520 requires the liner design to include measures against uplift water pressure if a seasonal high water table occurs above the lowest potential liquid level in the impoundment (examples: perimeter drains, maintaining a minimum liquid depth, liners heavy enough to resist uplift), and requires evaluating the foundation for karstic bedrock, joints and other bedrock discontinuities to decide whether a compacted soil liner is appropriate.

    NRCS CPS 520 (May 2016), Criteria - Foundation, p. 520-CPS-2 [35]
    Show the source text
    The liner design will include measures to protect against damage to the soil liner due to uplift water pressures if a seasonal high water table occurs at a level above that of the lowest potential level of liquid in the impoundment. Examples of protective design measures are the use of perimeter drains to lower the water table, maintaining minimum liquid depth ... Evaluate the foundation for conditions such as karstic bedrock, joints, and other discontinuities of the underlying bedrock to determine the appropriateness for a compacted soil liner.
    Open USDA NRCS (opens in a new tab)
  • Size cutoffCPS 520 soil dispersant treatment: the dispersant must be tetrasodium pyrophosphate (TSPP), sodium tripolyphosphate (STPP), or soda ash unless lab tests support other types. For clean water ponds without lab tests or field performance data on similar soils, the minimum rate per 6-inch lift is 7.5 lbs per 100 sq ft for polyphosphate (TSPP, STPP) and 15 lbs per 100 sq ft for soda ash, with a maximum 6-inch lift thickness.

    Applies when: Clean water ponds, absent laboratory tests or field performance data NRCS CPS 520 (May 2016), Additional Criteria for Soil Dispersant Treatment and Table 2, pp. 520-CPS-2 to -3 [35]
    Show the source text
    The dispersant must be tetrasodium pyrophosphate (TSPP), sodium tripolyphosphate (STPP), or soda ash unless laboratory tests using other dispersant types are used in the design. ... For clean water ponds, in the absence of laboratory tests or field performance data on soils similar to those to be treated, apply dispersant ... Install the liner with a maximum 6-inch-lift thickness. ... Minimum Application Rate Dispersant Type per 6-inch lift thickness (lbs./100 ft2) Polyphosphate 7.5 (TSPP, STPP) Soda Ash 15
    Open USDA NRCS (opens in a new tab)
  • CPS 520 considerations (recommendations, not requirements): consider a composite liner system (geomembrane and/or geosynthetic clay liner) for sites with liquid depths greater than 24 feet, and consider installing a 12-inch protective soil cover over the compacted soil liner.

    NRCS CPS 520 (May 2016), Considerations, p. 520-CPS-4 [35]
    Show the source text
    Consider using a composite liner system, including a geomembrane and/or geosynthetic clay liner for sites that have liquid depths greater than 24 feet. Consider installing a 12-inch protective soil cover over the compacted soil liner.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 520 operation and maintenance includes, at a minimum, excluding animals and equipment from the treated area, repairing liner damage and restoring the liner to its original thickness and condition, and removing roots of trees and large shrubs at first appearance.

    NRCS CPS 520 (May 2016), Operation and Maintenance, p. 520-CPS-4 [35]
    Show the source text
    This includes, but is not limited to— • Excluding animals and equipment from the treated area. • Repairing damage to the liner; restoring the liner to its original thickness and condition. • Removing roots from trees and large shrubs at first appearance.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 521 general criteria: the liner must be planned, designed and constructed to comply with all Federal, State, Tribal and local laws and regulations; the structure to be lined must meet applicable NRCS standards; the liner is designed and installed per manufacturer recommendations; and the installer or manufacturer must certify that the installation meets the material and installation requirements of the plans and specifications.

    NRCS CPS 521 (August 2023R), General Criteria Applicable to All Purposes; Design, p. 521-CPS-1 [36]
    Show the source text
    Plan, design, and construct the liner to comply with all Federal, State, Tribal, and local laws and requlations. ... The structure to be lined must meet all applicable NRCS standards. ... Design and install the liner in accordance with manufacturer recommendations. The installer or manufacturer must certify that the liner installation meets the material and installation requirements of the plans and specifications.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 521 gas venting and drainage: all geomembrane pond liners require vents at the crest of the side slopes spaced no more than 50 feet apart; ponds without a bottom gas venting system require a minimum bottom grade of 2 percent; and all geomembrane liners require a drainage system if the pond invert is within 2 feet of the seasonal high water table.

    NRCS CPS 521 (August 2023R), Gas venting; Groundwater drainage, pp. 521-CPS-2 to -3 [36]
    Show the source text
    All geomembrane pond liners require vents at the crest of the side slopes with a spacing not to exceed 50 feet. ... a minimum bottom grade of 2 percent is required for ponds without a bottom gas venting system. ... All geomembrane liners require a drainage system if the invert elevation of the pond is within 2 feet of the seasonal high water table.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 521 cushion, cover and slopes: a cushion layer is required between the liner and sharp angular particles larger than 3/8 inch (geomembranes) or 1/2 inch (GCLs) - either a nonwoven geotextile of 10 oz/sq yd or heavier or at least 6 inches of suitable soil. PVC liners and GCLs must be covered with at least 12 inches of soil, placed within 24 hours after liner placement and anchorage; side slopes may be no steeper than 2:1.

    NRCS CPS 521 (August 2023R), Cushion; Cover soil, pp. 521-CPS-3 to -4 [36]
    Show the source text
    This includes angular particles and concretions greater than 3/8 inch for geomembrane liners and 1/2 inch for GCLs. The cushion may be a 10-ounce-per-square-yard or heavier nonwoven geotextile or a layer at least 6 inches thick of soil meeting the particle size and shape requirements of the subgrade. ... Cover PVC liners and GCLs with a minimum of 12 inches of soil measured perpendicular to the finished surface. ... Place cover soil within 24 hours after placement and anchorage of the liner ... Side slopes shall be no steeper than 2:1.
    Open USDA NRCS (opens in a new tab)
  • CPS 521 considerations state that PVC geomembranes are not recommended for aquatic production because stabilizers in PVC liner material leach out and may be harmful to aquatic species; consult manufacturers before selecting a geomembrane for aquatic production.

    NRCS CPS 521 (August 2023R), Considerations, p. 521-CPS-5 [36]
    Show the source text
    PVC geomembranes are not recommended for aquatic production. The stabilizers in the PVC liner material leach out and may be harmful to aquatic species. Consult with manufacturers before selecting a geomembrane material used for aquatic production.
    Open USDA NRCS (opens in a new tab)
  • RequirementCPS 522 requires the designer to select either 'reduced seepage' or 'liquid tight' criteria. Where liquid tightness is not required, the building code requirements must be one of ACI 318, ACI 330R or ACI 360R. Operation and maintenance includes visually inspecting the liner annually.

    NRCS CPS 522 (May 2016), Criteria - Liquid Tight; Reduced Seepage; Operation and Maintenance, pp. 522-CPS-1 to -2 [37]
    Show the source text
    Select the concrete liner design for either ‘reduced seepage’ or ‘liquid tight’ criteria, depending on the site conditions and management needs. ... Reduced Seepage Where liquid tightness is not required, building code requirements must be one of the following: • ACI 318, Building Code Requirements for Reinforced Concrete, ACI. • ACI 330R, Guide for the Design and Construction of Concrete Parking Lots, ACI. • ACI 360R, Guide to Design of Slabs-on-Ground, ACI. ... Visually inspecting liner annually.
    Open USDA NRCS (opens in a new tab)
  • StatusHistory of CPS 521: NRCS's April 27, 2023 Federal Register notice (Docket NRCS-2023-0005; comments due May 30, 2023) proposed revising CPS 521's materials table, gas venting, water drainage, and leak detection criteria and slope requirements, and adding considerations on safety, leak detection and liner protection.

    88 FR 25619-25620 (Apr. 27, 2023), FR Doc. 2023-08842, Docket No. NRCS-2023-0005 [39]
    Show the source text
    [Docket No. NRCS-2023-0005] ... DATES: We will consider comments that we receive by May 30, 2023. ... Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521): Revised the materials table; the gas venting, water drainage, and leak detection criteria; and the slope requirements. Also, added new considerations on safety, leak detection, and liner protection.
    Open Federal Register / GPO govinfo (opens in a new tab)
  • StatusHistory of the code numbers: NRCS's March 4, 2016 Federal Register notice (Docket NRCS-2016-0001) listed the compacted-soil standard as 'Pond Sealing or Lining--Compacted Soil Treatment (Code 521B)', combining the prior compacted soil liner standards 521B, 521C and 521D into one, and introduced 'Pond Sealing or Lining--Concrete (Code 521C)' as a new standard developed as an alternative practice for lining and sealing animal waste storage ponds and lagoons.

    81 FR 11509-11510 (Mar. 4, 2016), FR Doc. 2016-04824, Docket No. NRCS-2016-0001 [40]
    Show the source text
    521B Pond Sealing or Lining--Compacted Soil Treatment now combines the existing compacted soil liner standards (521B. 521C & 521D) into one standard code which is now 521B Pond Sealing or Lining--Compacted Soil Treatment. ... Pond Sealing or Lining--Concrete (Code 521C)--521C Pond Sealing or Lining--Concrete is a new standard developed as an alternative practice for lining and sealing animal waste storage ponds and lagoons as needed.
    Open Federal Register / GPO govinfo (opens in a new tab)
  • ProcessThe Sept. 1, 2026 notice states that NRCS State Conservationists who choose to adopt these CPSs in their States will incorporate them into their respective electronic Field Office Technical Guide, and that Section 343 of the Federal Agriculture Improvement and Reform Act of 1996 (Pub. L. 104-127) states that revisions made after enactment of the law to NRCS State technical guides used to carry out highly erodible land (HEL) and wetland provisions must be made available for public review and comment.

    91 FR 56102 (Sept. 1, 2026), Supplementary Information - Background [13]
    Show the source text
    NRCS State Conservationists who choose to adopt these CPSs in their States will incorporate them into their respective electronic Field Office Technical Guide. ... Section 343 of the Federal Agriculture Improvement and Reform Act of 1996 (Pub. L. 104-127) states that revisions made after enactment of the law to NRCS State technical guides used to carry out HEL and wetland provisions must be made available for public review and comment.
    Open Federal Register / GPO govinfo (opens in a new tab)
  • RequirementPROPOSED CPS 520 (Sept. 2026 draft) keeps the bentonite specification (sodium bentonite, free swell at least 22 mL by ASTM D5890, unless laboratory tests support other bentonite materials) and the same clean-water-pond minimum rates per 1-inch lift (silts 0.375, silty sands 0.5, clean sand 0.625 lbs/sq ft) with a maximum 6-inch lift; it would also require uplift protection where the impoundment is near a stream channel or other surface water impoundment with a hydraulically connected foundation and groundwater.

    NRCS CPS 520, proposed draft (NHCP September 2026), Foundation; Additional Criteria for Bentonite Treatment, Table 3, pp. 520-CPS-3 to -4 [38]
    Show the source text
    or if the impoundment is near a stream channel or other surface water impoundments where the foundation and groundwater is hydraulicly connected. ... The bentonite used must be a sodium bentonite with a free swell of at least 22 milliliters as measured by ASTM Standard Test Method D5890, unless laboratory tests support the use of other bentonite materials. ... Install the liner with a maximum lift thickness of 6 inches. ... Silts (ML, CL-ML) 0.375 Silty Sands (SM, SC-SM, SP-SM) 0.5 Clean Sand (SP, SW) 0.625
    Open USDA NRCS (opens in a new tab)
  • RequirementPROPOSED CPS 522 (Sept. 2026 draft): liquid tightness would be required for waste storage impoundments and for other impoundments where enhanced protection for geologic concerns, groundwater resources, or other risk factors is required; a concrete liner for a clean water pond would be designed to reduce seepage to meet or exceed the current version of ACI 318, ACI 330R or ACI 360R; and a leak detection system would be required for waste storage impoundments using a concrete liner on Group I or II soil types having an estimated permeability greater than 5 x 10-5 cm/sec.

    NRCS CPS 522, proposed draft "522 NHCP CPS Pond Sealing or Lining, Concrete 2026 FR" (NHCP September 2026), Design seepage requirements; Leakage detection, p. 522-CPS-2 [41]
    Show the source text
    Liquid tightness is required for waste storage impoundments and other impoundments where enhanced protection for geologic concerns, groundwater resources, or other risk factors is required. Reduced Seepage Design a concrete liner for a clean water pond to reduce seepage to meet or exceed the current version of one of the following: • ACI 318 ... ACI 330R ... ACI 360R ... A leak detection system is required for waste storage impoundments using a concrete liner on Group I or II soil types having an estimated permeability greater than 5 x 10-5 cm/sec.
    Open USDA NRCS (opens in a new tab)

Not confirmed from a primary source

We could not confirm the following from an official source. Ask the agency listed before relying on any of it.

  • Whether NRCS has adopted final versions of CPS 520 and 522 after the September 1, 2026 proposal, and their effective dates. As of September 28, 2026 the comment period was still open and the national index still listed both dated 05/2016. — ask: NRCS Conservation Engineering Division or the NRCS State Office
  • Whether a particular state has adopted CPS 520, 521 or 522 with state-specific criteria, such as different bentonite rates or liner thickness, in its Field Office Technical Guide. — ask: The NRCS State Office or State Conservation Engineer for the state where the pond is located

More detail

More detail: 11 more verified statements on which ponds are waters of the United States and the Clean Water Act definitions
  • The same preamble says artificial lakes and ponds are often used for more than one purpose and can have other beneficial purposes such as animal habitat, water retention, or recreation, and that the agencies' historic practice, which they intend to continue, is to treat such features as excluded even when there is another incidental beneficial use.

    88 FR 3004, 3116 (Jan. 18, 2023) (preamble) [6]
    Show the source text
    The agencies recognize that artificial lakes and ponds are often used for more than one purpose and can have other beneficial purposes, such as animal habitat, water retention, or recreation. ... The agencies' historic practice, which the agencies intend to continue under this rule, is to consider these features as excluded even when there is another incidental beneficial use of the feature.
    Open Federal Register (govinfo) (opens in a new tab)
  • ProcessA Corps approved jurisdictional determination (AJD) is a Corps document stating the presence or absence of waters of the United States on a parcel (or identifying their limits); AJDs are designated appealable actions, are case-specific and typically made in response to a request, and are valid for five years unless new information warrants revision before the expiration date or a District Engineer has identified, after public notice and comment, that specific geographic areas with rapidly changing environmental conditions merit re-verification on a more frequent basis.

    USACE Kansas City District, MFR for AJD NWK-2025-00300 (Aug. 21, 2025), Background [42]
    Show the source text
    An Approved Jurisdictional Determination (AJD) is a Corps document stating the presence or absence of waters of the United States on a parcel ... AJDs are clearly designated appealable actions ... AJDs are case-specific and are typically made in response to a request. AJDs are valid for a period of five years unless new information warrants revision of the determination before the expiration date or a District Engineer has identified, after public notice and comment, that specific geographic areas with rapidly changing environmental conditions merit re-verification on a more frequent basis.
    Open U.S. Army Corps of Engineers, Kansas City District (opens in a new tab)
  • Example of district practice: in an August 2025 approved jurisdictional determination, the Kansas City District concluded that a 0.85-acre manmade residential-development stormwater detention pond constructed in uplands, with no defined tributary connecting it to the tributary system (and therefore not an impoundment), was not a jurisdictional water of the United States.

    USACE Kansas City District, MFR for AJD NWK-2025-00300 (Aug. 21, 2025), sec. 8 [42]
    Show the source text
    The 0.85 acre pond depicted in the attached map is a manmade residential development stormwater detention pond constructed in the uplands. ... There is no defined tributary connecting this pond to the tributary system and is therefore not an impoundment. ... Based on the information outlined above, we have concluded that the 0.85 acre pond that exists within the review area is not a jurisdictional water of the United States.
    Open U.S. Army Corps of Engineers, Kansas City District (opens in a new tab)
  • ExemptionWhere the Amended 2023 WOTUS rule applies, 40 CFR 120.2(b) says the following are not waters of the United States even if they otherwise meet paragraphs (a)(2)-(5): artificial lakes or ponds created by excavating or diking dry land to collect and retain water and used exclusively for such purposes as stock watering, irrigation, settling basins, or rice growing; and artificial reflecting or swimming pools or other small ornamental bodies of water created by excavating or diking dry land to retain water for primarily aesthetic reasons.

    Applies when: States where the Amended 2023 Rule is operative (see fed-wotus topic for the state-by-state split and the pre-2015 regime used in the other states) 40 CFR 120.2(b)(5)-(6) [43]
    Show the source text
    The following are not “waters of the United States” even where they otherwise meet the terms of paragraphs (a)(2) through (5) of this section: ... (5) Artificial lakes or ponds created by excavating or diking dry land to collect and retain water and which are used exclusively for such purposes as stock watering, irrigation, settling basins, or rice growing; (6) Artificial reflecting or swimming pools or other small ornamental bodies of water created by excavating or diking dry land to retain water for primarily aesthetic reasons;
    Open eCFR / Office of the Federal Register (opens in a new tab)
  • DefinitionThe Clean Water Act defines 'discharge of a pollutant' as (A) any addition of any pollutant to navigable waters from any point source, and 'navigable waters' as the waters of the United States, including the territorial seas. The definition thus has four elements: an 'addition', of a 'pollutant', to navigable waters (waters of the United States), from a 'point source'.

    33 U.S.C. 1362(7), (12)(A) [3]
    Show the source text
    (7) The term "navigable waters" means the waters of the United States, including the territorial seas. ... (12) The term "discharge of a pollutant" and the term "discharge of pollutants" each means (A) any addition of any pollutant to navigable waters from any point source
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • Definition'Point source' means any discernible, confined and discrete conveyance - the statute lists examples including any pipe, ditch, channel, tunnel, conduit, well, discrete fissure and container - from which pollutants are or may be discharged. The term does not include agricultural stormwater discharges and return flows from irrigated agriculture.

    33 U.S.C. 1362(14) [3]
    Show the source text
    The term "point source" means any discernible, confined and discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding operation, or vessel or other floating craft, from which pollutants are or may be discharged. This term does not include agricultural stormwater discharges and return flows from irrigated agriculture.
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • Definition'Pollutant' is defined as dredged spoil, solid waste, incinerator residue, sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials, radioactive materials, heat, wrecked or discarded equipment, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water. The definition's two express exclusions concern (A) sewage from vessels or discharges incidental to the normal operation of an Armed Forces vessel, and (B) water, gas or other material injected into a well to facilitate oil or gas production (and related oil and gas disposal wells), subject to State approval conditions.

    33 U.S.C. 1362(6) [3]
    Show the source text
    The term "pollutant" means dredged spoil, solid waste, incinerator residue, sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials, radioactive materials, heat, wrecked or discarded equipment, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water. This term does not mean (A) "sewage from vessels or a discharge incidental to the normal operation of a vessel of the Armed Forces" ... (B) water, gas, or other material which is injected into a well to facilitate production of oil or gas
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • DefinitionEPA's NPDES regulation defines 'discharge of a pollutant' as any addition of any pollutant to waters of the United States from any point source, and states that this includes additions from surface runoff collected or channelled by man and from discharges through pipes, sewers or other conveyances owned by a State, municipality or other person that do not lead to a treatment works. For NPDES purposes, 'waters of the United States' has the meaning in 40 CFR 120.2.

    40 CFR 122.2 (definitions of "Discharge of a pollutant" and "Waters of the United States") [44]
    Show the source text
    Discharge of a pollutant means: (a) Any addition of any “pollutant” or combination of pollutants to “waters of the United States” from any “point source,” ... This definition includes additions of pollutants into waters of the United States from: surface runoff which is collected or channelled by man; discharges through pipes, sewers, or other conveyances owned by a State, municipality, or other person which do not lead to a treatment works ... Waters of the United States or waters of the U.S. means the term as it is defined in § 120.2 of this chapter.
    Open eCFR (opens in a new tab)
  • DefinitionUnder the Clean Water Act, 'pollutant' means dredged spoil, solid waste, incinerator residue, sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials, radioactive materials, heat, wrecked or discarded equipment, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water; 'navigable waters' means the waters of the United States; and 'discharge of a pollutant' means any addition of any pollutant to navigable waters from any point source.

    33 U.S.C. 1362(6), (7), (12)(A) [3]
    Show the source text
    (6) The term "pollutant" means dredged spoil, solid waste, incinerator residue, sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials, radioactive materials, heat, wrecked or discarded equipment, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water. ... (7) The term "navigable waters" means the waters of the United States, including the territorial seas. ... (12) The term "discharge of a pollutant" and the term "discharge of pollutants" each means (A) any addition of any pollutant to navigable waters from any point source,
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • DefinitionA 'point source' is any discernible, confined and discrete conveyance, including any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding operation, or vessel or other floating craft, from which pollutants are or may be discharged; it does not include agricultural stormwater discharges and return flows from irrigated agriculture.

    33 U.S.C. 1362(14) [3]
    Show the source text
    (14) The term "point source" means any discernible, confined and discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding operation, or vessel or other floating craft, from which pollutants are or may be discharged. This term does not include agricultural stormwater discharges and return flows from irrigated agriculture.
    Open Office of the Law Revision Counsel, U.S. House of Representatives (opens in a new tab)
  • DefinitionEPA's NPDES regulations define 'discharge of a pollutant' as any addition of any pollutant or combination of pollutants to waters of the United States from any point source, and define 'pollutant' to include (among other things) dredged spoil, solid waste, chemical wastes, biological materials, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water.

    40 CFR 122.2 (definitions of 'Discharge of a pollutant' and 'Pollutant') [44]
    Show the source text
    Discharge of a pollutant means: (a) Any addition of any “pollutant” or combination of pollutants to “waters of the United States” from any “point source,” ... Pollutant means dredged spoil, solid waste, incinerator residue, filter backwash, sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials, radioactive materials (except those regulated under the Atomic Energy Act of 1954, as amended (42 U.S.C. 2011 et seq.)), heat, wrecked or discarded equipment, rock, sand, cellar dirt and industrial, municipal, and agricultural waste discharged into water.
    Open eCFR (opens in a new tab)

Sources

Every statement above links to one of these official sources. Expand “Show the source text” under any statement to read the exact passage it rests on.

  1. About Waters of the United States (EPA web page, last updated September 9, 2026) (opens in a new tab) — U.S. EPA, document date 2026-09-09, retrieved September 28, 2026
  2. 33 U.S.C. 1311 - Effluent limitations (CWA section 301) (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, document date Laws in effect on September 27, 2026, retrieved September 28, 2026
  3. 33 U.S.C. 1362 (CWA sec. 502) Definitions (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, retrieved September 28, 2026
  4. 33 CFR Part 323 - Permits for Discharges of Dredged or Fill Material into Waters of the United States (opens in a new tab) — eCFR (Office of the Federal Register), document date current eCFR text; 323.2 last amended 73 FR 79645, Dec. 30, 2008, retrieved September 28, 2026
  5. 33 CFR 328.3 - Definitions (waters of the United States) (eCFR, current; 88 FR 3142, Jan. 18, 2023, as amended at 88 FR 61968, Sept. 8, 2023) (opens in a new tab) — eCFR / Office of the Federal Register, document date 2023-09-08, retrieved September 28, 2026
  6. Revised Definition of "Waters of the United States," 88 FR 3004 (Jan. 18, 2023), FR Doc. 2022-28595 (opens in a new tab) — Federal Register (govinfo), document date 2023-01-18, retrieved September 28, 2026
  7. Regulatory Guidance Letter 05-04: Guidance on the Discharge of Sediments From or Through a Dam and the Breaching of Dams (opens in a new tab) — U.S. Army Corps of Engineers, document date 2005-08-19, retrieved September 28, 2026
  8. Greenfield Mills, Inc. v. Macklin, No. 02-1863 (7th Cir. Mar. 19, 2004) (slip opinion) (opens in a new tab) — U.S. Court of Appeals for the Seventh Circuit, document date 2004-03-19, retrieved September 28, 2026
  9. NPDES Water Transfers Rule, final rule, 73 FR 33697-33708 (June 13, 2008), FR Doc. E8-13360 (opens in a new tab) — U.S. EPA / Federal Register (govinfo), document date 2008-06-13, retrieved September 28, 2026
  10. 33 U.S.C. 1344 - Permits for dredged or fill material (CWA section 404) (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, document date Text contains laws in effect on September 27, 2026, retrieved September 28, 2026
  11. Exemptions to Permit Requirements under CWA Section 404 (opens in a new tab) — U.S. Environmental Protection Agency, document date Last updated March 10, 2026, retrieved September 28, 2026
  12. Conservation Practice Standards | Natural Resources Conservation Service (opens in a new tab) — USDA NRCS, retrieved September 28, 2026
  13. Proposed Revisions to the National Handbook of Conservation Practices, 91 FR 56102 (FR Doc. 2026-17863, Docket NRCS-2026-0100) (opens in a new tab) — Federal Register / GPO govinfo, document date 2026-09-01, retrieved September 28, 2026
  14. Reissuance and Modification of Nationwide Permits (final rule), FR Doc. 2026-00121 (opens in a new tab) — Federal Register / U.S. Army Corps of Engineers, document date 2026-01-08; effective 2026-03-15; expires 2031-03-15, retrieved September 28, 2026
  15. 40 CFR 122.3 (eCFR current) (opens in a new tab) — eCFR, document date current eCFR (48 FR 14153, Apr. 1, 1983, as amended through 78 FR 38594, June 27, 2013), retrieved September 28, 2026
  16. EPA 2022 Construction General Permit, Permit Parts 1-9 (as modified, effective April 8, 2025) (opens in a new tab) — U.S. EPA, document date 2025-04-08 (2025-06-10 for EPA Regions 1 and 3), retrieved September 28, 2026
  17. EPA 2022 CGP Appendix A - Definitions and Acronyms (as modified, April 2025) (opens in a new tab) — U.S. EPA, document date 2025-04, retrieved September 28, 2026
  18. Proposed 2027 CGP Appendix A - Definitions and Acronyms (opens in a new tab) — U.S. EPA, document date 2026-07, retrieved September 28, 2026
  19. EPA, Frequently Asked Questions on Removal of Obsolete Dams (EPA-840-F-16-001, December 2016) (opens in a new tab) — U.S. EPA Office of Water, document date 2016-12, retrieved September 28, 2026
  20. Updates to the National Pollutant Discharge Elimination System Definitions and Exclusions, proposed rule, 91 FR 56819-56825 (Sept. 4, 2026) (opens in a new tab) — U.S. EPA / Federal Register (govinfo), document date 2026-09-04, retrieved September 28, 2026
  21. Catskill Mountains Chapter of Trout Unlimited, Inc. v. EPA (Catskill III), Nos. 14-1823 et al. (2d Cir. Jan. 18, 2017) (opens in a new tab) — U.S. Court of Appeals for the Second Circuit (govinfo USCOURTS), document date 2017-01-18, retrieved September 28, 2026
  22. Supreme Court docket No. 17-418, New York v. EPA (docket page) (opens in a new tab) — Supreme Court of the United States, retrieved September 28, 2026
  23. Supreme Court docket No. 17-446, Riverkeeper, Inc. v. EPA (docket page) (opens in a new tab) — Supreme Court of the United States, retrieved September 28, 2026
  24. Loper Bright Enterprises v. Raimondo, No. 22-451 (slip opinion, June 28, 2024) (opens in a new tab) — Supreme Court of the United States, document date 2024-06-28, retrieved September 28, 2026
  25. 40 CFR Part 450 Construction and Development Point Source Category (eCFR, current) (opens in a new tab) — eCFR / Office of the Federal Register, retrieved September 28, 2026
  26. 40 CFR Part 232 - 404 Program Definitions; Exempt Activities Not Requiring 404 Permits (opens in a new tab) — eCFR (Office of the Federal Register), document date current eCFR text, retrieved September 28, 2026
  27. Final Revisions to the Clean Water Act Regulatory Definitions of "Fill Material" and "Discharge of Fill Material", 67 FR 31129 (May 9, 2002) (opens in a new tab) — U.S. Army Corps of Engineers and U.S. EPA / Federal Register (govinfo), document date 2002-05-09, retrieved September 28, 2026
  28. Coeur Alaska, Inc. v. Southeast Alaska Conservation Council, 557 U.S. 261 (2009) (U.S. Reports) (opens in a new tab) — U.S. Supreme Court (U.S. Reports via govinfo.gov), document date 2009-06-22, retrieved September 28, 2026
  29. 7 U.S.C. 136a: Registration of pesticides (FIFRA section 3) (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, retrieved September 28, 2026
  30. 40 CFR Part 152, Subpart A - General Provisions (152.1-152.15) (eCFR, current) (opens in a new tab) — eCFR / Office of the Federal Register, retrieved September 28, 2026
  31. Pesticide Permitting - Frequent Questions (EPA NPDES web page, last updated March 31, 2026) (opens in a new tab) — U.S. EPA, document date 2026-03-31, retrieved September 28, 2026
  32. 7 U.S.C. 136: Definitions (FIFRA section 2) (opens in a new tab) — Office of the Law Revision Counsel, U.S. House of Representatives, retrieved September 28, 2026
  33. EPA Label Review Manual, Chapter 2: What is a Pesticide? (Revised January 2021) (opens in a new tab) — U.S. EPA, Office of Pesticide Programs, document date 2021-01, retrieved September 28, 2026
  34. 2022 NPDES Construction General Permit (as modified, effective April 8, 2025; expires Feb. 16, 2027) (opens in a new tab) — U.S. EPA, document date 2025-04-08, retrieved September 28, 2026
  35. Conservation Practice Standard Pond Sealing or Lining, Compacted Soil Treatment (Code 520) (opens in a new tab) — USDA NRCS, document date May 2016, retrieved September 28, 2026
  36. Conservation Practice Standard Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521) (opens in a new tab) — USDA NRCS, document date August 2023R, retrieved September 28, 2026
  37. Conservation Practice Standard Pond Sealing or Lining - Concrete (Code 522) (opens in a new tab) — USDA NRCS, document date May 2016, retrieved September 28, 2026
  38. PROPOSED CPS 520 Pond Sealing or Lining, Compacted Soil Treatment (2026 FR draft) (opens in a new tab) — USDA NRCS, document date September 2026 (proposed), retrieved September 28, 2026
  39. Proposed Revisions to the National Handbook of Conservation Practices, FR Doc. 2023-08842 (Docket NRCS-2023-0005) (opens in a new tab) — Federal Register / GPO govinfo, document date 2023-04-27, retrieved September 28, 2026
  40. Notice of Proposed Changes to the National Handbook of Conservation Practices, 81 FR 11509 (Docket NRCS-2016-0001) (opens in a new tab) — Federal Register / GPO govinfo, document date 2016-03-04, retrieved September 28, 2026
  41. PROPOSED CPS 522 Pond Sealing or Lining, Concrete (2026 FR draft) (opens in a new tab) — USDA NRCS, document date September 2026 (proposed), retrieved September 28, 2026
  42. USACE Kansas City District, Memorandum for Record, Pre-2015 Regulatory Regime Approved Jurisdictional Determination, NWK-2025-00300 (Aug. 21, 2025) (opens in a new tab) — U.S. Army Corps of Engineers, Kansas City District, document date 2025-08-21, retrieved September 28, 2026
  43. 40 CFR 120.2 Definitions (waters of the United States) (eCFR, current) (opens in a new tab) — eCFR / Office of the Federal Register, retrieved September 28, 2026
  44. 40 CFR 122.2 (eCFR current) (opens in a new tab) — eCFR, document date current eCFR, retrieved September 28, 2026

This is not legal advice. It is a plain-English summary of official sources, checked September 28, 2026. Laws, permits and agency practice change, and how they apply depends on your exact site. Confirm with the agencies named here, and with a licensed professional engineer for any dam, before you build.

Planning a pond?

Talk it through with a Natural Waterscapes pond expert before you break ground. We can help you size the project so it fits the permits you can realistically get.