Pennsylvania Erosion & Sediment Control and NPDES Rules for Ponds
Pennsylvania's Chapter 102 defines earth disturbance to include excavations, embankments and the moving or stockpiling of soil, and requires everyone proposing or conducting earth disturbance to develop, implement and maintain BMPs to minimize the potential for accelerated erosion and sedimentation and to manage post-construction stormwater. E&S BMPs are required even when the disturbance is under 5,000 square feet, both for agricultural plowing or tilling and animal heavy use areas and for other earth disturbance such as pond excavation or embankment work. [1][2][3]
Outside those agricultural activities, a written E&S Plan is required when total disturbance will be 5,000 square feet or more, when Chapter 102 or other DEP regulations require one, or at any size when, because of its proximity to existing drainage features or patterns, the work has the potential to discharge to a High Quality or Exceptional Value (HQ/EV) water. Separately, earth disturbance of 1 acre or more, or earth disturbance on any part or stage of a larger common plan of development or sale involving 1 acre or more, needs an individual NPDES permit or general-permit coverage for construction stormwater before it begins; this permit threshold excludes agricultural plowing or tilling, animal heavy use areas, timber harvesting and road maintenance. [3][4]
DEP's pond guidance says that whether or not pond work needs a Chapter 105 authorization, developing an E&S plan and implementing and maintaining E&S BMPs is required under Chapter 102. DEP directs pond owners to their county conservation district or DEP regional office about E&S plan and permitting requirements. [5]
A person conducting agricultural plowing or tilling or animal heavy use areas needs no E&S Permit or NPDES construction stormwater permit for those activities but must still comply with the rest of Chapter 102, and DEP says construction on agricultural land that will disturb at least one acre must obtain NPDES coverage. Neither Chapter 102's definition of agricultural plowing or tilling nor DEP's agricultural permitting table mentions ponds; how a farm pond is classified is listed below as unconfirmed. [1][4][6]
Any violation of the Clean Streams Law, a DEP rule, regulation or order, or a permit condition is a summary offense punishable on conviction by a fine of $100 to $10,000 per offense; negligent violations are second-degree misdemeanors ($2,500 to $25,000 per offense) and intentional or knowing violations are third-degree felonies ($5,000 to $50,000 per offense). DEP may also, after a hearing, assess civil penalties of up to $10,000 per day for each violation, and Chapter 102 enforcement actions include orders to remediate or restore. [7][8]
Key points
Official sources disagree
- How far the Act 162 buffer alternative reaches. The Clean Streams Law text added by Act 162 of 2014 lets anyone whose earth disturbance requires an NPDES stormwater permit under Chapter 102 use either a riparian buffer or riparian forest buffer, or other BMPs, design standards and alternatives that are collectively substantially equivalent to a buffer in effectiveness. DEP's Act 162 web page says the amendment pertains to individual NPDES permit applications for construction stormwater. The riparian buffer rule in 25 Pa. Code § 102.14, as codified in its 2010 text, bars earth disturbance within 150 feet of a perennial or intermittent river, stream or creek, or a lake, pond or reservoir for projects that need a Chapter 102 permit in HQ or EV watersheds attaining their designated use, subject to the exceptions in § 102.14(d). [7][9][10]
- Whether every pond job needs an E&S plan. DEP's pond page says developing an E&S plan and implementing and maintaining E&S BMPs is required under Chapter 102 whether or not the pond work needs a Chapter 105 authorization. Section 102.4(b) requires E&S BMPs even below 5,000 square feet but a written E&S Plan only at 5,000 square feet or more, where the work, because of its proximity to existing drainage features or patterns, has the potential to discharge to HQ/EV waters, or where Chapter 102 or other DEP regulations require one. Separately, § 105.13(g) requires earthmoving on Chapter 105 projects, including small projects, to be conducted under an earth disturbance plan. [3][5][11]
- How the size triggers are worded. Section 102.4(b) uses '5,000 square feet (464.5 square meters) or more' and § 102.5(a) uses 'equal to or greater than 1 acre'. DEP's instructions for the individual NPDES permit (Rev. 7/2026) and for the PAG-01 (Rev. 3/2025) and PAG-02 (Rev. 3/2026) general permits treat proposed disturbance over 0.99 acre as needing NPDES coverage, outside agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance. York County Conservation District says construction on farms needs a written plan when disturbing 'more than 5,000 square feet' and an NPDES permit for planned disturbance 'over 1 acre' when building structures such as barns, manure storages, houses and silos. Clinton County Conservation District uses 'exceeds' for both thresholds, and Chester County Conservation District says 'greater than 5,000 square feet' for a written plan. [3][4][12][13][14][15][16][17]
- PAG-02 and special-protection waters. DEP's August 31, 2024 Pennsylvania Bulletin notice says PAG-02 may not be used for discharges to waters designated for special protection under Chapter 93. The PAG-02 fact sheet (Rev. 8/2024) says DEP will deny coverage when stormwater discharges directly to surface waters, including wetlands, with a designated or existing HQ or EV use. [18][19]
-
Definition"Earth disturbance activity" means a construction or other human activity that disturbs the land surface, expressly including land clearing and grubbing, grading, excavations, embankments, and the moving, depositing, stockpiling, or storing of soil, rock or earth materials.
Applies when: Covers pond excavation ("excavations") and embankment construction ("embankments"), plus spoil stockpiling 25 Pa. Code § 102.1 (definition of "Earth disturbance activity") [1]Show the source text
Earth disturbance activity—A construction or other human activity which disturbs the surface of the land, including land clearing and grubbing, grading, excavations, embankments, land development, agricultural plowing or tilling, operation of animal heavy use areas, timber harvesting activities, road maintenance activities, oil and gas activities, well drilling, mineral extraction, and the moving, depositing, stockpiling, or storing of soil, rock or earth materials.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementChapter 102 requires every person proposing or conducting earth disturbance activities to develop, implement and maintain BMPs to minimize the potential for accelerated erosion and sedimentation and to manage post-construction stormwater.
Applies when: Any earth disturbance activity, regardless of size 25 Pa. Code § 102.2(a) [2]Show the source text
This chapter requires persons proposing or conducting earth disturbance activities to develop, implement and maintain BMPs to minimize the potential for accelerated erosion and sedimentation and to manage post construction stormwater.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementDEP's pond guidance: whether or not pond work requires a Chapter 105 authorization, developing an E&S plan and implementing and maintaining E&S BMPs is required under Chapter 102, and DEP directs owners to their county conservation district or DEP regional office about E&S plan and permitting requirements. For maintenance dredging waived from Chapter 105 permitting, DEP says pond and dam owners should still obtain E&S plan approval from their county conservation district.
DEP, Introduction to Ponds and Chapter 105 (web page) [5]Show the source text
Pond and dam owners should still obtain Erosion and Sediment Control Plan approval from their County Conservation District. ... Note: While the activities described below may or may not require Chapter 105 authorization, the development of an erosion and sedimentation control plan and the implementation and maintenance of erosion and sedimentation control Best Management Practices is required under Chapter 102. Please contact your County Conservation District or the applicable DEP Regional Office regarding erosion and sedimentation control plan and permitting requirements for your project.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
Size cutoffFor earth disturbance other than agricultural plowing/tilling or animal heavy use areas (i.e., construction such as pond excavation or embankment work): E&S BMPs must be implemented and maintained even for disturbances under 5,000 square feet, and a written E&S Plan must be developed and implemented if one or more of these apply: (i) total earth disturbance will be 5,000 square feet (464.5 m²) or more; (ii) the person is required to develop an E&S Plan under Chapter 102 or other DEP regulations; or (iii) because of its proximity to existing drainage features or patterns, the activity has the potential to discharge to a water classified as High Quality or Exceptional Value under Chapter 93.
Applies when: Earth disturbance other than agricultural plowing/tilling or animal heavy use areas 25 Pa. Code § 102.4(b)(1)-(2) [3]Show the source text
E&S BMPs are required ... including those activities which disturb less than 5,000 square feet ... shall develop and implement a written E&S Plan under this chapter if one or more of the following criteria apply: ... will result in a total earth disturbance of 5,000 square feet (464.5 square meters) or more. ... is required to develop an E&S Plan under this chapter or under other Department regulations. ... because of its proximity to existing drainage features or patterns, has the potential to discharge to a water classified as a High Quality or Exceptional Value water
Open Pennsylvania Code & Bulletin (opens in a new tab) -
Size cutoffNPDES construction stormwater permit threshold: other than agricultural plowing/tilling, animal heavy use areas, timber harvesting or road maintenance, anyone proposing earth disturbance of 1 acre (0.4 hectare) or more - or earth disturbance on any portion, part or stage of a larger common plan of development or sale involving 1 acre or more - must obtain an individual NPDES permit or coverage under a general NPDES permit for Stormwater Discharges Associated With Construction Activities before commencing the earth disturbance.
Applies when: Pond construction (excavation, embankment, spoil, access) totaling >= 1 acre of earth disturbance 25 Pa. Code § 102.5(a) [4]Show the source text
Other than agricultural plowing or tilling activities, animal heavy use areas, timber harvesting activities or road maintenance activities, a person proposing an earth disturbance activity that involves equal to or greater than 1 acre (0.4 hectare) of earth disturbance, or an earth disturbance on any portion, part, or during any stage of, a larger common plan of development or sale that involves equal to or greater than 1 acre ... shall obtain an individual NPDES Permit or coverage under a general NPDES permit ... prior to commencing the earth disturbance activity.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
Clean Streams Law penalties: any violation of the Act, a DEP rule or regulation, a DEP order or a permit condition is a summary offense punishable on conviction by a fine of $100 to $10,000 for each separate offense; a negligent violation is a misdemeanor of the second degree with a fine of up to $25,000 for each separate offense (minimum $2,500); and an intentional or knowing violation is a felony of the third degree with a fine of up to $50,000 for each separate offense (minimum $5,000). Separately, DEP may, after hearing, assess a civil penalty of up to $10,000 per day for each violation.
35 P.S. §§ 691.602(a), (b), (b.1) and 691.605(a) (Clean Streams Law §§ 602, 605(a)) [7]Show the source text
summary offense ... not less than one hundred dollars ($100) nor more than ten thousand dollars ($10,000) for each separate offense ... negligently violates ... misdemeanor of the second degree ... ($2,500) nor more than twenty-five thousand dollars ($25,000) for each separate offense ... intentionally or knowingly violates ... felony of the third degree ... ($5,000) nor more than fifty thousand dollars ($50,000) for each separate offense ... after hearing, may assess a civil penalty ... shall not exceed ten thousand dollars ($10,000) per day for each violation.
Open Pennsylvania General Assembly (opens in a new tab) -
ProcessEnforcement and appeals: Chapter 102 compliance and enforcement actions include, among others listed, orders (including orders to remediate or restore) and civil penalty proceedings. A person aggrieved by a conservation district action under Chapter 102 must request an informal hearing with DEP within 30 days of the notice; DEP schedules it and makes a final determination within 30 days of the request, which may be appealed to the Environmental Hearing Board.
25 Pa. Code § 102.32(a), (c) [8]Show the source text
(3) Orders (including orders to remediate or restore). ... (4) Civil penalty proceedings, except as provided in subsection (b). ... (c) A person aggrieved by an action of a conservation district under this chapter shall request an informal hearing with the Department within 30 days following the notice of the action. The Department will schedule the informal hearing and make a final determination within 30 days of the request. Any final determination by the Department under the informal hearing may be appealed to the EHB
Open Pennsylvania Code & Bulletin (opens in a new tab)
How much ground are you disturbing?
Under § 102.4(b), E&S BMPs are still required below 5,000 square feet, but a written plan is required below that size only when one of the other written-plan triggers above applies (see the conflict note above for DEP's pond page). The E&S Plan, inspection reports and monitoring records must be available at the site for DEP or conservation district review during all stages of the earth disturbance, and after a complaint or site inspection either may require the plan to be submitted for review and approval. [3]
DEP's FAQ says a project under 1 acre may still have to submit its E&S Plan to the county conservation district because of municipal ordinances, and the district may charge a fee to review it. [6]
DEP's instructions for the individual NPDES permit (Rev. 7/2026) and for the PAG-01 (Rev. 3/2025) and PAG-02 (Rev. 3/2026) general permits all say that, outside agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance, DEP treats proposed disturbance over 0.99 acre as needing NPDES coverage, because actual disturbance during construction is likely to reach 1 acre; for example, 0.999, 0.995 and 0.991 acre are rounded up to 1 acre and need a permit, while 0.99 acre or less needs no NPDES permit unless it is part of a larger common plan of development or sale or DEP otherwise requires one under federal regulations. For PAG-01 eligibility, the PAG-01 instructions likewise round disturbances of 4.999, 4.995 and 4.991 acres up to 5 acres (PAG-01 covers disturbance of less than 5 acres). DEP's Common Plan of Development or Sale FAQ also says a project cannot be phased to avoid the permit: if a person knows during planning or construction that disturbance will be 1 acre or greater, an NPDES permit is required before any earth disturbance for that project begins. [12][16][17][20][21]
Conservation district pages show local practice. Clinton County Conservation District counts associated roads and parking areas in a pond project's total disturbance and says a written plan above 5,000 square feet may not need district review, while an NPDES permit needs engineering approval and district review. Chester County Conservation District says any pond dredging, any disturbance associated with a Chapter 105 general permit (such as a stream crossing or wetland disturbance), and any disturbance of one acre or more must have an E&S plan developed and reviewed by the district. [14][15]
-
ProcessThe E&S Plan, inspection reports and monitoring records must be available at the project site for DEP or conservation district review during all stages of earth disturbance, and upon a complaint or site inspection DEP or the conservation district may require the E&S Plan to be submitted for review and approval. Where a Chapter 102 permit is required, permit coverage must be in place before earth disturbance begins.
25 Pa. Code § 102.4(b)(8)-(9), (e) [3]Show the source text
(8) The E&S Plan, inspection reports and monitoring records shall be available for review and inspection by the Department or the conservation district at the project site during all stages of the earth disturbance activity. ... (9) Upon complaint or site inspection, the Department or conservation district may require that the E&S Plan be submitted for review and approval ... shall have permit coverage prior to commencing the earth disturbance activity.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessDEP guidance for projects under 1 acre: even without a Chapter 102 permit, the E&S Plan may still have to be submitted to the county conservation district because of municipal ordinances, and the district may charge a fee to review it; DEP advises contacting the local district if unsure.
Applies when: Earth disturbance under 1 acre DEP Erosion and Sediment Control FAQ (v1.8), FAQ #5 [6]Show the source text
If your project will involve less than one acre of disturbance, you may still be required to submit your plan to the CCD due to municipal ordinances. You should contact your local CCD if you are unsure if your plan needs to be submitted and reviewed. The CCD may charge a fee to review the E&S Plan.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
Size cutoffHow DEP applies the 1-acre threshold: other than agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance activities, DEP considers earth disturbances exceeding 0.99 acre as needing NPDES permit coverage, because actual earth disturbance during construction is likely to meet or exceed the one-acre threshold for a permit under 25 Pa. Code § 102.5. For example, proposed earth disturbances of 0.999, 0.995 and 0.991 acre will be rounded up to one acre and a permit would be required. Disturbances of 0.99 acre and smaller would not require a permit, unless part of a larger common plan of development or sale or otherwise required by DEP in accordance with federal regulations.
DEP, Individual NPDES Permit Application Instructions (3800-PM-BCW0408a Rev. 7/2026), "Earth Disturbance Threshold" [12]Show the source text
Other than agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance activities, DEP considers earth disturbances exceeding 0.99 acre as needing NPDES permit coverage due to the likelihood that actual earth disturbance during construction will meet or exceed the one-acre threshold for a permit under 25 Pa. Code § 102.5. For example, proposed earth disturbances of 0.999, 0.995 and 0.991 acre will be rounded up to one acre and a permit would be required. Disturbances of 0.99 acre and smaller would not require a permit, unless part of a larger common plan of development or sale or otherwise required by DEP in accordance with federal regulations.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementDEP guidance: a project cannot be phased to avoid a Chapter 102 permit. If a person knows during planning or construction that earth disturbance will be 1 acre or greater, an NPDES permit is required before any earth disturbance for that project begins.
DEP Common Plan of Development or Sale FAQ (v1.5), FAQ #6 [20]Show the source text
No. A person cannot phase their project to circumvent the regulatory requirement of obtaining a permit under 25 Pa. Code § 102.5. If a person knows during the planning and/or construction of their project that the earth disturbance will be 1 acre or greater, then an NPDES permit is required prior to initiating any earth disturbance for that project.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
Clinton County Conservation District's pond guidance (not specific to farms) says any pond project with earth disturbance needs an implemented E&S plan. A written, implemented plan is required above 5,000 square feet, though district staff may not need to review it. If total disturbance, including associated roads and parking areas, exceeds 1 acre, an NPDES permit is required, needs engineering approval and is reviewed by district staff.
Clinton County Conservation District, "Building Ponds" (web page) [14]Show the source text
Any project involving earth disturbance requires an implemented plan to stop accelerated erosion and sedimentation. If the earth disturbance exceeds 5,000 square feet, a written and implemented plan is required, but may not need to be reviewed by our staff. If the total disturbance (which includes bring in pavers or paving associated roads and parking areas), exceeds 1 acre, a National Pollutant Discharge Elimination System (NPDES) permit is required for your project. This permit needs engineering approval and would be reviewed by the District Staff.
Open Clinton County, PA (Conservation District) (opens in a new tab) -
ProcessChester County Conservation District: all disturbance over 5,000 square feet needs a written E&S Plan. Any disturbance associated with a Chapter 105 General Permit (for example a stream crossing or wetland disturbance), any pond dredging, and any disturbance of one acre or more must have an E&S Plan developed and reviewed by the Conservation District office.
Chester County Conservation District, FAQ "When is an Erosion and Sediment Control Plan required?" [15]Show the source text
All disturbances greater than 5,000 square feet must have a written Erosion and Sediment Control Plan. Any disturbance associated with the use of Chapter 105 General Permit (GP) (stream crossing, wetland disturbance, etc.), pond dredgings, or one acre and greater disturbance must have an Erosion and Sediment Control Plan developed and reviewed by the Conservation District office.
Open Chester County, PA (Conservation District) (opens in a new tab) -
Size cutoffDEP's PAG-01 Notice of Intent instructions (Rev. 3/2025) state that, other than agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance activities, DEP considers earth disturbances exceeding 0.99 acre as needing NPDES permit coverage, because actual earth disturbance during construction is likely to meet or exceed the one-acre threshold for a permit under 25 Pa. Code § 102.5. For example, proposed earth disturbances of 0.999, 0.995 and 0.991 acre will be rounded up to one acre and a permit would be required. Disturbances of 0.99 acre and smaller would not require a permit, unless part of a portion, part, or stage of a larger common plan of development or sale or otherwise required by DEP in accordance with federal regulations. For the purpose of determining PAG-01 eligibility, disturbances of 4.999, 4.995 and 4.991 acres are likewise rounded up to five acres.
DEP, PAG-01 NOI Instructions (3800-PM-BCW0404a Rev. 3/2025), "Earth Disturbance Threshold" [16]Show the source text
Other than agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance activities, DEP considers earth disturbances exceeding 0.99 acre as needing NPDES permit coverage due to the likelihood that actual earth disturbance during construction will meet or exceed the one-acre threshold for a permit under 25 Pa. Code § 102.5. For example, proposed earth disturbances of 0.999, 0.995 and 0.991 acre will be rounded up to one acre and a permit would be required. Disturbances of 0.99 acre and smaller would not require a permit, unless part of a portion, part, or stage of a larger common plan of development or sale or otherwise required by DEP in accordance with federal regulations. Similarly, disturbances of 4.999, 4.995 and 4.991 acres will be rounded up to five (5) acres for the purpose of determining PAG-01 eligibility.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
Size cutoffDEP's PAG-02 Notice of Intent instructions (Rev. 3/2026) state that, other than agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance activities, DEP considers earth disturbances exceeding 0.99 acre as needing NPDES permit coverage, because actual earth disturbance during construction is likely to meet or exceed the one-acre threshold for a permit under 25 Pa. Code § 102.5. For example, proposed earth disturbances of 0.999, 0.995 and 0.991 acre will be rounded up to one acre and a permit would be required. Disturbances of 0.99 acre and smaller would not require a permit, unless part of a portion, part, or stage of a larger common plan of development or sale or otherwise required by DEP in accordance with federal regulations.
DEP, PAG-02 NOI Instructions (3800-PM-BCW0405a Rev. 3/2026), "Earth Disturbance Threshold" [17]Show the source text
Other than agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas, and road maintenance activities, DEP considers earth disturbances exceeding 0.99 acre as needing NPDES permit coverage due to the likelihood that actual earth disturbance during construction will meet or exceed the one-acre threshold for a permit under 25 Pa. Code § 102.5. For example, proposed earth disturbances of 0.999, 0.995 and 0.991 acre will be rounded up to one acre and a permit would be required. Disturbances of 0.99 acre and smaller would not require a permit, unless part of a portion, part, or stage of a larger common plan of development or sale or otherwise required by DEP in accordance with federal regulations.
Open Pennsylvania Department of Environmental Protection (opens in a new tab)
Farm and agricultural ponds
Chapter 102 defines agricultural plowing or tilling as earth disturbance to prepare and maintain soil for producing crops, including no-till, and an animal heavy use area as a barnyard, feedlot, loafing area, exercise lot or similar area on an agricultural operation where, because of the concentration of animals, vegetative cover dense enough to minimize accelerated erosion and sedimentation cannot be established and maintained by usual planting methods. These activities follow a separate track: BMPs are required even under 5,000 square feet, a written E&S Plan is required at 5,000 square feet or more, and the landowner and any lessee, renter, tenant or other occupier are jointly and individually responsible for developing the written plan. [1][3]
A person conducting those activities needs no E&S Permit or NPDES construction stormwater permit "for these activities". Anyone not required to obtain a Chapter 102 permit must still comply with the rest of the chapter, and the agricultural E&S subsection says nothing in it negates other Chapter 102 requirements, "such as those applicable to construction activities". [3][4]
DEP's guidance says construction on agricultural land that will disturb at least one acre must obtain NPDES coverage, listing barns, homes, animal housing, compost facilities, equipment or vehicle lanes and manure storage as examples, and says the list is not complete. DEP's Agricultural E&S Manual says an Ag E&S Plan does not cover construction, and that construction on an agricultural operation may need a Construction E&S Plan and, depending on the acres disturbed, an NPDES permit. [6][22]
DEP's permitting table marks installing swales, diversions, waterways, filter strips or terraces as part of agricultural plowing and tilling or animal heavy use areas, converting land to agricultural land, and establishing wildlife food plots as not subject to NPDES permitting, PCSM or HQ/EV riparian buffer requirements. DEP's FAQ also says the earth disturbance associated with proposed BMPs that address water-quality concerns of agricultural plowing or tilling and animal heavy use areas is exempt from permit coverage. The table does not list farm, livestock-watering or irrigation ponds, and the definition of agricultural plowing or tilling does not mention ponds. [1][6]
The NRCS Pennsylvania Pond (Code 378) standard (October 2023) requires the pond to be planned, designed and built to comply with all federal, state and local laws and regulations, and says the landowner must obtain all necessary permits before construction. [23]
-
Definition"Agricultural plowing or tilling activity" is earth disturbance involving the preparation and maintenance of soil for the production of agricultural crops, including no-till cropping. An "animal heavy use area" is a barnyard, feedlot, loafing area, exercise lot or similar area on an agricultural operation where the concentration of animals prevents establishing and maintaining vegetative cover.
25 Pa. Code § 102.1 (definitions of "Agricultural plowing or tilling activity" and "Animal heavy use area") [1]Show the source text
Earth disturbance activity involving the preparation and maintenance of soil for the production of agricultural crops. ... The term includes no-till cropping methods ... Barnyard, feedlot, loafing area, exercise lot, or other similar area on an agricultural operation where due to the concentration of animals it is not possible to establish and maintain vegetative cover of a density capable of minimizing accelerated erosion and sedimentation by usual planting methods.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ExemptionAgricultural plowing/tilling and animal heavy use areas follow a separate track: BMPs are required even for disturbance under 5,000 square feet, and a written E&S Plan is required when those activities disturb 5,000 square feet or more; the landowner and any lessee, renter, tenant or other occupier are jointly and individually responsible for the plan. This agricultural track does not negate Chapter 102 requirements that apply to construction activities.
Applies when: Agricultural plowing or tilling activities and animal heavy use areas only 25 Pa. Code § 102.4(a)(1)-(3), (9) [3]Show the source text
For agricultural plowing or tilling activities or for animal heavy use areas ... including for those activities which disturb less than 5,000 square feet ... Written E&S Plans are required for the following activities that disturb 5,000 square feet ... or more of land ... The landowner, and any lessee, renter, tenant or other land occupier ... are jointly and individually responsible for developing a written E&S Plan ... Nothing in this section negates the requirements under other provisions of this chapter, such as those applicable to construction activities.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ExemptionThe agricultural permit exemption covers only the agricultural activities themselves. A person conducting agricultural plowing or tilling or animal heavy use areas does not need an E&S Permit or an NPDES construction stormwater permit "for these activities". Anyone who does not need a Chapter 102 permit must still comply with the other provisions of Chapter 102.
25 Pa. Code § 102.5(j), (k) [4]Show the source text
(j) A person proposing or conducting agricultural plowing or tilling activities or animal heavy use areas is not required to obtain an E&S Permit, or an NPDES Permit for Stormwater Discharges Associated With Construction Activities, for these activities under this chapter. ... (k) A person proposing or conducting an earth disturbance activity who is not required to obtain a permit under this chapter shall comply with the other provisions of this chapter.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementThe agricultural E&S subsection states that nothing in it negates the requirements of other Chapter 102 provisions, "such as those applicable to construction activities".
25 Pa. Code § 102.4(a)(9) [3]Show the source text
(9) Nothing in this section negates the requirements under other provisions of this chapter, such as those applicable to construction activities.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementDEP guidance: construction activities on agricultural lands that will disturb at least one acre must obtain NPDES permit coverage (DEP's examples: barn or home construction or expansion, new animal housing, compost facilities, equipment/vehicle lanes, manure storage). DEP's table marks installing swales, diversions, waterways, filter strips or terraces as part of agricultural plowing/tilling or AHUAs, converting land to agricultural land, and establishing wildlife food plots as not subject to NPDES permitting. Farm ponds are not listed.
Applies when: Construction on agricultural operations disturbing >= 1 acre DEP Erosion and Sediment Control FAQ (v1.8, rev. Aug. 12, 2026), FAQ #5 [6]Show the source text
Construction activities on agricultural lands that will disturb at least one acre must obtain NPDES permit coverage. Agricultural construction activities include, but are not limited to, barn or home construction or expansion; new animal housing; compost facilities; lanes for equipment or vehicle access; and manure storage facilities. ... Installing swales, diversions, waterways, filter strips, or terraces as No No No part of agricultural plowing and tilling activities or AHUAs ... Converting land to No No No agricultural land Establishing wildlife food No No No plots
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
RequirementDEP's Agricultural E&S Manual: an Ag E&S Plan does not cover construction activities. Anyone starting construction on an agricultural operation may need a Construction E&S Plan and, depending on the acres disturbed, an NPDES permit. New construction requires E&S BMPs and may require a Construction E&S Plan under § 102.4(b). DEP directs questions about construction on agricultural operations to the county conservation district or DEP.
DEP, Soil Erosion and Sediment Control Manual for Agricultural Operations (383-4200-002), Appendix C - Construction E&S [22]Show the source text
An Ag E&S Plan does not cover construction activities; therefore, if a person is looking to commence construction on an agricultural operation, a Construction E&S Plan and, depending upon the acres disturbed, an NPDES permit may be necessary. ... New construction requires erosion and sedimentation control BMPs and may require a Construction E&S Plan under 25 Pa. Code Section 102.4(b). ... For more information relating to construction on agricultural operations, contact your local county conservation district or the Department.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
ExemptionDEP's agricultural permitting table marks as NOT subject to NPDES permitting, PCSM or HQ/EV riparian buffer requirements: installing swales, diversions, waterways, filter strips or terraces as part of agricultural plowing and tilling or animal heavy use areas, converting land to agricultural land, and establishing wildlife food plots. The same table marks, for example, building a house as subject to all three. Farm ponds, livestock-watering ponds, irrigation ponds and impoundments are not listed in the table.
DEP Erosion and Sediment Control FAQ (v1.8), FAQ #5 permitting table [6]Show the source text
Building a house Yes Yes Yes ... Installing swales, diversions, waterways, filter strips, or terraces as No No No part of agricultural plowing and tilling activities or AHUAs ... Converting land to No No No agricultural land ... Establishing wildlife food No No No plots
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
ExemptionDEP guidance: agricultural plowing or tilling (including no-till) and animal heavy use areas do not require permit coverage but still require an Agricultural E&S Plan or conservation plan. DEP adds that the earth disturbance from BMPs proposed to address water-quality concerns of plowing/tilling and animal heavy use areas is also exempt from permit coverage.
DEP Erosion and Sediment Control FAQ (v1.8), FAQ #5 [6]Show the source text
Agricultural plowing or tilling activities (including no-till) and animal heavy use areas (AHUAs), as defined at 25 Pa. Code § 102.1, do not require permit coverage, but they still require the development of an agricultural E&S Plan (Ag E&S Plan) or conservation plan. Therefore, the earth disturbance associated with proposed BMPs to address water quality concerns of agricultural plowing or tilling and AHUA are exempt from permit coverage.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
DefinitionChapter 102 defines "agricultural plowing or tilling activity" as earth disturbance involving the preparation and maintenance of soil for the production of agricultural crops, including no-till cropping (planting crops with minimal mechanical tillage). The definition does not mention ponds, impoundments or other structures.
25 Pa. Code § 102.1 (definition of "Agricultural plowing or tilling activity") [1]Show the source text
Agricultural plowing or tilling activity— ... (i) Earth disturbance activity involving the preparation and maintenance of soil for the production of agricultural crops. ... (ii) The term includes no-till cropping methods, the practice of planting crops with minimal mechanical tillage.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementThe NRCS Pennsylvania Pond (Code 378) standard (Oct. 2023) itself requires that the pond be planned, designed and built to comply with all federal, state and local laws and regulations. It states the landowner must obtain all necessary permits before construction.
NRCS Pennsylvania Conservation Practice Standard, Pond (Code 378), General Criteria Applicable to All Ponds [23]Show the source text
Plan, design, and construct the pond to comply with all Federal, State, and local laws and regulations. ... The landowner is also required to obtain all necessary permits for project installation prior to construction.
Open USDA NRCS Pennsylvania (eFOTG) (opens in a new tab)
When the pond also needs a Chapter 105 permit
Except for small projects, a Chapter 105 permit application must include proof of an application for an Earth Disturbance Permit or an E&S plan for activities in the stream and earthmoving activities; the plan must conform to Chapter 102 and include, if applicable, a conservation district letter finding it satisfactory. Earthmoving on Chapter 105 projects, including small projects, must be conducted under an earth disturbance plan. [11]
DEP's dam permit application instructions (Rev. 6/2018) say final approval of an NPDES permit for stormwater discharge or of an E&S plan from the county conservation district is required for dam permit issuance. [24]
Chapter 102 excuses a separate E&S Permit or NPDES construction permit for earth disturbance approved under a DEP permit issued under a chapter other than Chapter 92 or 102, if that permit includes requirements to comply with both Chapter 92 and Chapter 102 (§ 102.5(g)). It also excuses one for earth disturbance associated with discharging dredged or fill material to waters of the United States that requires a federal Clean Water Act section 404 permit or coverage under one, for the area of disturbance covered by that 404 permit (§ 102.5(i)). In its 2010 comment responses on § 102.5(g), DEP gave mining and waste management permits as examples and did not name Chapter 105 permits. [4][25]
In its 2010 comment responses on § 102.5(i), DEP said an activity covered by another permit issued under section 404, "such as a Chapter 105 permit", needs no additional E&S or NPDES permit for the activity that permit covers; that for a Chapter 105 permit this is the area within the watercourse, floodway or body of water; and that activities outside the area permitted under section 404 need their own E&S or NPDES coverage. DEP's current individual NPDES application instructions (Rev. 7/2026) ask whether the project needs a Chapter 105 permit or other authorization and, if so, how many acres, if any, are excluded from NPDES permit requirements under § 102.5(i). [12][25]
-
RequirementExcept for small projects, an application for a Chapter 105 permit must be accompanied by proof of an application for an Earth Disturbance Permit or an erosion and sedimentation control plan for activities in the stream and earthmoving activities. The plan must conform to Chapter 102 and must include, if applicable, a copy of a conservation district letter saying the district reviewed the plan and considered it satisfactory. Earthmoving activities, including small projects, must be conducted under an earth disturbance plan.
25 Pa. Code § 105.13(g) [11]Show the source text
(g) Except for small projects, an application for a permit under this chapter shall be accompanied by proof of an application for an Earth Disturbance Permit or an erosion and sedimentation control plan for activities in the stream and earthmoving activities. The plan must conform to requirements in Chapter 102 ... and must include a copy of a letter from the conservation district ... considered it to be satisfactory, if applicable. Earthmoving activities, including small projects, shall be conducted pursuant to an earth disturbance plan.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessDEP's dam permit application instructions (item 10) state that final approval of an NPDES permit for stormwater discharge or an Erosion and Sedimentation Control Plan (ESCP) from the appropriate county conservation district is required for Dam Permit issuance. At a minimum, for application completeness, submission of the ESCP should be included.
DEP, Instructions for Completing Dam Permit Application (3140-PM-BWEW0001 Rev. 6/2018), item 10 [24]Show the source text
Erosion and Sedimentation Control Plan and ... approval letter: Final approval of an NPDES Permit for ... stormwater discharge or an Erosion and Sedimentation ... Control Plan (ESCP) from the appropriate county ... conservation district is required for Dam Permit ... issuance. At a minimum for application completeness, ... submission of the ESCP should be included.
Open Pennsylvania DEP, Bureau of Waterways Engineering and Wetlands (opens in a new tab) -
ExemptionSection 102.5(g) text: a person conducting earth disturbance approved under a DEP permit issued under a chapter other than Chapter 92 or Chapter 102, where that permit "includes requirements to comply with Chapter 92 and this chapter", need not obtain an additional E&S Permit or NPDES construction stormwater permit. The permit must include requirements to comply with both Chapter 92 (NPDES) and Chapter 102.
25 Pa. Code § 102.5(g) [4]Show the source text
(g) A person proposing or conducting an earth disturbance activity approved under a Department permit issued under a chapter other than Chapter 92 (relating to National Pollutant Discharge Elimination System permitting, monitoring and compliance) or this chapter, which includes requirements to comply with Chapter 92 and this chapter, need not obtain an additional E&S Permit or NPDES Permit for Stormwater Discharges Associated With Construction Activities.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ExemptionSection 404 overlap: a person discharging dredged or fill material to waters of the United States who must obtain a Clean Water Act section 404 permit (or coverage under one) need not obtain an additional Chapter 102 E&S Permit or NPDES construction stormwater permit for the area of disturbance covered by the 404 permit.
Applies when: Embankment or fill in a stream/wetland that requires a USACE section 404 permit 25 Pa. Code § 102.5(i) [4]Show the source text
(i) A person proposing or conducting an earth disturbance activity associated with discharging dredged or fill material to waters of the United States which is required to obtain a permit or coverage under a permit under section 404 of the Federal Clean Water Act (33 U.S.C.A. § 1344) need not obtain an additional E&S Permit or NPDES Permit for Stormwater Discharges Associated With Construction Activities for the area of disturbance covered by the Clean Water Act section 404 permit.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
DEP's 2010 comment-response on § 102.5(g) says the subsection is not meant to let another state permit avoid an NPDES requirement. It applies where Chapter 92 and 102 requirements are built into other DEP regulations and permits reviewed in those permit applications. DEP's examples are mining and waste management permits; Chapter 105 permits are not given as an example.
Chapter 102 Comment-Response Document (2010 final rulemaking), § 102.5, response to comment 52 [25]Show the source text
The reference in 102.5 (g) is an existing requirement, and is not intended to avoid an NPDES permit requirement. The requirements are to comply with both Chapter 92 and 102 when these requirements are included in other Department regulations and permit requirements that are reviewed for other permit applications. The other Department permit provides sufficient authorization, therefore a separate authorization under permits identified in this rule are not necessary - Some examples include mining and waste management permits.
Open PA DEP / Environmental Quality Board (opens in a new tab) -
ExemptionHow DEP described Chapter 105 permits in 2010: the E&S approval is obtained during review of the Water Obstruction and Encroachment permit, because an E&S Plan is a required part of that application. An activity covered by another permit issued under section 404, "such as a Chapter 105 permit", needs no additional E&S or NPDES permit for the activity that permit covers. For a Chapter 105 permit, the covered area is "the area within the watercourse, floodway or body of water", and other activities outside the 404-permitted area need their own E&S or NPDES coverage.
Chapter 102 Comment-Response Document (2010 final rulemaking), § 102.5(i), response to IRRC comment 5 [25]Show the source text
The E&S approval would be obtained during the review of the Water Obstruction and Encroachment Permit since an E&S Plan is a required part of that application ... such as a Chapter 105 permit, does not require an additional E&S or NPDES permit for the activity covered by that other permit. In the case of a Chapter 105 permit, that would be the area within the watercourse, floodway or body of water. ... Any other activities outside of the area permitted for coverage under Section 404 would need additional E&S or NPDES coverage.
Open PA DEP / Environmental Quality Board (opens in a new tab) -
ProcessDEP's current individual NPDES permit application handles Chapter 105 overlap by asking for acreage. Applicants state whether the project needs a Chapter 105 permit or authorization, identify its type, and report any acreage excluded from NPDES permit requirements under § 102.5(i).
DEP, Individual NPDES Permit Application Instructions (3800-PM-BCW0408a Rev. 7/2026), items 23-25 [12]Show the source text
23. Chapter 105 Permit or Authorization. Check the box for Yes if the project requires a permit or other authorization under 25 Pa. Code Chapter 105 ... 25. If Yes to question #23, report any area, in acres, that is excluded from NPDES permit requirements under the authority of 25 Pa. Code 102.5(i), if applicable.
Open Pennsylvania Department of Environmental Protection (opens in a new tab)
The NPDES construction permit
DEP's Bureau of Clean Water administers the statewide Chapter 102 program. Persons disturbing 1 acre or more may, if eligible, apply for coverage under the PAG-01 (small construction) or PAG-02 (construction) general permit; if ineligible for both, they may apply for an individual NPDES permit. [26]
A person whose earth disturbance requires a Chapter 102 permit must submit to DEP or a conservation district a complete application or Notice of Intent (NOI), an E&S Plan, a post-construction stormwater (PCSM) Plan and proof of consultation with the Pennsylvania Natural Heritage Program about the presence of state or federal threatened or endangered species. If the application or NOI is found incomplete, the applicant has 60 days to complete it or it is considered withdrawn; a specific extension may be requested in writing. [27]
PAG-01 took effect March 1, 2022, expires February 28, 2027, covers disturbance of at least 1 acre and less than 5 acres, and may not be used for discharges to special-protection waters; complete NOI packages are due 30 or 60 days before construction, depending on factors in the NOI instructions. DEP's PAG-01 fact sheet (Rev. 4/2025) sets design limits relevant to ponds: sediment basins and sediment traps cannot be used (compost sock sediment traps are allowed), alternative E&S BMPs need DEP's written authorization, and post-construction impervious area is limited to 30,000 square feet within the disturbed area and 12% of the total site. [21][28]
DEP published notice of a draft reissued PAG-01 on August 22, 2026; it is a proposal, not a final permit. The draft would keep the $500 administrative filing fee and the $100 per disturbed acre fee, and would drop the two review-period options so that NOIs would be due at least 60 days before earth disturbance begins; DEP says existing PAG-01 permittees who want to continue coverage will need to submit an NOI by February 28, 2027. Comments closed September 21, 2026, and DEP estimates issuance in January 2027 and a March 1, 2027 effective date. [29][30]
PAG-02 was reissued effective December 8, 2024 and expires December 7, 2029. An administratively complete NOI is due at least 60 calendar days before the planned start of any new discharge, and a permittee may not begin a new discharge under PAG-02 until coverage is approved in writing and all other state and local permits and approvals arising from the earth disturbance reported in the NOI (which may include local building permits and Chapter 105 permits) are obtained. Except as specified in Part C II.B of the permit, the permittee must also have recorded with the Recorder of Deeds a legal instrument disclosing planned PCSM measures and received written DEP or district authorization to schedule the pre-construction meeting, and that meeting must be held unless DEP or the district waives it in writing. [18][19]
Under PAG-02, until the Notice of Termination is approved (unless DEP or the district approves otherwise in writing), routine visual site inspections are weekly and post-storm inspections are due within 24 hours after the end of each storm of 0.25 inch or more in 24 hours or snowmelt sufficient to cause a discharge. Effective December 8, 2025, inspections must be performed by qualified personnel, such as people who complete DEP's Qualified Site Inspector Training Program initially and every two years thereafter. [31]
-
AgencyDEP's Bureau of Clean Water administers the statewide Chapter 102 program. Persons disturbing one or more acres may, if eligible, seek coverage under the PAG-01 (small construction) or PAG-02 (construction) general NPDES permits; if ineligible for both, they may apply for an individual NPDES permit. DEP lists RA-EPChapter102@pa.gov as the Bureau of Clean Water contact for the Chapter 102 program.
DEP, Construction Stormwater (web page) [26]Show the source text
DEP's Bureau of Clean Water administers the statewide Chapter 102 program for earth disturbance activities ... If eligible, persons disturbing one or more acres may apply for coverage under the PAG-01 NPDES General Permit for Discharges of Stormwater Associated with Small Construction Activities or PAG-02 NPDES General Permit ... If ineligible for PAG-01 or PAG-02 coverage, persons may apply for an individual NPDES permit ... contact DEP’s Bureau of Clean Water at RA-EPChapter102@pa.gov.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
ProcessA person whose earth disturbance requires a permit under § 102.5 must submit to DEP or a conservation district a complete application or Notice of Intent (NOI), an E&S Plan meeting § 102.4 and a PCSM Plan meeting § 102.8, plus proof of consultation with the Pennsylvania Natural Heritage Program (PNHP) regarding the presence of State or Federal threatened or endangered species. If DEP or the district finds the application/NOI incomplete, the applicant has 60 days to complete it or it is considered withdrawn; the applicant may request a specific extension in writing.
25 Pa. Code § 102.6(a)(1)-(2), (c)(2) [27]Show the source text
Submit to the Department or a conservation district a complete application or NOI, an E&S Plan meeting the requirements of § 102.4 ... a PCSM Plan meeting the requirements of § 102.8 ... Provide proof of consultation with the Pennsylvania Natural Heritage Program (PNHP) regarding the presence of a State or Federal threatened or endangered species ... have 60 days to provide the information necessary to complete the application or NOI, or ... will consider the application to be withdrawn by the applicant. Requests for a specific extension may be sought by the applicant in writing.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
StatusPAG-01 (small construction) general permit: effective March 1, 2022 and expiring February 28, 2027; it covers earth disturbance of at least 1 acre and less than 5 acres and may not be used for discharges to special protection waters. Complete NOI packages are due 30 or 60 days before construction depending on factors in the NOI instructions, and PAG-01 applicants are not required to prepare the § 102.8(g) stormwater analysis.
51 Pa.B. 7128 (Nov. 13, 2021), Notice of availability of PAG-01 [21]Show the source text
The PAG-01 General Permit will become effective on March 1, 2022, and will expire on February 28, 2027. ... involving earth disturbance greater than or equal to 1 acre and less than 5 acres ... may not be used for discharges to waters designated for special protection ... must submit a complete Notice of Intent (NOI) package 30 or 60 days prior to the planned date for commencing construction activities involving earth disturbance ... Applicants are not required to prepare a stormwater analysis under 25 Pa. Code § 102.8(g)
Open Pennsylvania Bulletin / DEP (opens in a new tab) -
RequirementPAG-01 design limits relevant to ponds: under the PAG-01 small-construction general permit, E&S BMPs must follow DEP's E&S Manual except that sediment traps (compost sock sediment traps are allowed) and sediment basins cannot be used; alternative E&S BMPs are not allowed unless DEP authorizes them in writing; chemicals may not be introduced to stormwater during construction; and post-construction impervious area must be 30,000 square feet or less and 12% or less of the total project site.
Applies when: Projects seeking PAG-01 coverage (1 to <5 acres) DEP, PAG-01 Fact Sheet (3800-PM-BCW0404e Rev. 4/2025), Eligibility Criteria B.1-B.2 [28]Show the source text
with the exception of sediment traps (compost sock sediment traps are allowable) and sediment basins, which cannot be utilized under this General Permit. In addition, applicants are not authorized to use alternative E&S BMPs unless authorized to do so by DEP in writing ... The introduction of chemicals to stormwater during construction is prohibited. ... a. Less than or equal to thirty thousand square feet (≤ 30,000 sf) (within the area of disturbance), and ... b. Less than or equal to twelve percent (≤ 12%) of the total project site area.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
StatusDEP published notice of a DRAFT reissued PAG-01 general permit (the "2027 General Permit") in the Pennsylvania Bulletin on August 22, 2026 (56 Pa.B. 5629). PAG-01 is meant to provide NPDES coverage for stormwater discharges to surface waters from less than 5 acres of earth disturbance. This is a proposal, not a final permit.
56 Pa.B. 5629 (Aug. 22, 2026), Doc. No. 26-1207 [29]Show the source text
The Department of Environmental Protection (Department) is announcing the availability of a draft National Pollutant Discharge Elimination System (NPDES) General Permit for Stormwater Discharges from Small Construction Activities (PAG-01). ... PAG-01 is intended to provide NPDES permit coverage for storm- water discharges to surface waters to persons conducting less than 5 acres of earth disturbance.
Open Pennsylvania Bulletin (DEP notice) (opens in a new tab) -
ProcessProposed PAG-01 process changes (draft): DEP would eliminate the two review-period options, so NOIs would be due at least 60 days before earth disturbance begins. The $500 administrative filing fee and the $100 per disturbed acre fee would not change. DEP expects existing PAG-01 permittees who want to continue coverage to submit an NOI by February 28, 2027. Written comments were accepted through September 21, 2026.
56 Pa.B. 5629 (Aug. 22, 2026) [29]Show the source text
The Department is also proposing to eliminate the two review period options ... NOIs would be due at least 60 days prior to the planned date of beginning earth disturbance. ... The proposed administrative filing fee ($500) and disturbed acreage fee ($100 per disturbed acre) have not changed ... permittees with existing PAG-01 coverage that are interested in continuing their coverage will need to submit an NOI ... by February 28, 2027. ... submit written comments regarding the Draft PAG-01 General Permit and associated documents through Monday, September 21, 2026.
Open Pennsylvania Bulletin (DEP notice) (opens in a new tab) -
StatusPAG-02 current version: DEP reissued the PAG-02 General NPDES Permit for Discharges of Stormwater Associated with Construction Activities effective December 8, 2024, expiring December 7, 2029. PAG-02 may not be used for discharges to waters designated for special protection (HQ/EV) under Chapter 93 or for other discharges that do not meet its eligibility requirements.
54 Pa.B. 5536 (Aug. 31, 2024), Notice of availability of PAG-02 [18]Show the source text
The PAG-02 General Permit will become effective on December 8, 2024, and will expire on December 7, 2029. ... The PAG-02 General Permit may not be used for discharges to waters designated for special protection under 25 Pa. Code Chapter 93 (relating to water quality standards) or other discharges that do not meet eligibility requirements of the PAG-02 General Permit.
Open Pennsylvania Bulletin / DEP (opens in a new tab) -
ProcessPAG-02 process: an administratively complete NOI must be submitted at least 60 calendar days before the planned start of any new discharge. Before starting, the permittee must have written approval of coverage; have all other state and local permits and approvals (which may include local building permits and Chapter 105 permits); except as specified in Part C II.B of the General Permit, have recorded with the Recorder of Deeds a legal instrument disclosing planned PCSM stormwater control measures and received written DEP/district authorization to schedule the pre-construction meeting; and hold a pre-construction meeting unless DEP or the district waives it in writing.
DEP, PAG-02 Fact Sheet (3800-PM-BCW0405g Rev. 8/2024) [19]Show the source text
received written approval of coverage ... all other state and local permits and approvals ... local building permits ... and Chapter 105 permits ... recorded a legal instrument disclosing planned post-construction stormwater ... with the Recorder of Deeds ... and has received written authorization from DEP/CCD to schedule a pre-construction meeting, except as specified in Part C II.B ... A pre-construction meeting has been held unless waived by DEP or CCD, in writing. ... administratively complete NOI at least 60 calendar days prior to the planned date for commencing any new discharge
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementPAG-02 inspection duties: throughout construction and until the Notice of Termination is approved (unless DEP/district approves otherwise in writing), routine visual site inspections are required weekly, and post-storm inspections within 24 hours after the end of each measurable storm (0.25 inch or more of precipitation over a 24-hour period) or snowmelt sufficient to cause a discharge. Effective December 8, 2025, inspections must be performed by qualified personnel, such as those who complete DEP's Qualified Site Inspector Training Program initially and every two years thereafter.
Applies when: Projects with PAG-02 coverage PAG-02 General Permit (sample, 3800-PM-BCW0405d Rev. 1/2026), Part A III.C.1 and III.C.1.c [31]Show the source text
until the NOT has been approved by DEP/CCD (unless otherwise approved in writing ... Routine Inspections must be conducted weekly. ... PostStorm Event Inspections must be conducted within 24 hours after the conclusion of each ... measurable storm event (i.e., precipitation in an amount of 0.25 inch or greater over a 24-hour period) or the occurrence of snowmelt sufficient to cause a discharge. ... Effective December 8, 2025, site inspections must be performed ... by qualified personnel ... Qualified Site Inspector Training Program ... initially and every two years thereafter
Open Pennsylvania Department of Environmental Protection (opens in a new tab)
What E&S controls look like on a pond job
DEP's Erosion and Sediment Pollution Control Program Manual (effective March 31, 2012) says off-site surface water should be diverted away from areas to be disturbed wherever feasible, runoff from disturbed areas should be collected and conveyed to a sediment basin, sediment trap or other BMP, and both the extent of disturbance and the time until final stabilization should be minimized. It adds that existing vegetation, especially trees, should be preserved wherever possible, and that water pumped from excavations usually needs sediment removal treatment. [32]
Chapter 102 requires E&S BMPs to be designed, implemented and maintained to minimize the potential for accelerated erosion and sedimentation. DEP's E&S Manual lists BMPs and design standards; others may be used when the person demonstrates to DEP that they minimize accelerated erosion and sedimentation. Activities requiring an NPDES permit must also comply with the federal construction and development effluent guidelines at 40 CFR Part 450. DEP's examples of BMPs include minimizing earth disturbance, silt fence, mulch, channels, sediment traps, sediment basins and establishing permanent stabilization. [6][33]
The E&S Plan must be prepared by someone trained and experienced in E&S control for a project of that size and scope, and must include, among other items, the volume and rate of runoff from the site and its upstream watershed, the Chapter 93 classification of receiving waters, a maintenance program providing for weekly and post-storm BMP inspections with a written report for each, and potential thermal impacts to surface waters. The Manual says every project needing a written plan must have a BMP installation sequence, that controls should be installed and functioning before clearing and grubbing, and that for permitted sites the permit must be obtained before clearing and grubbing begins. [3][32]
For earthwork within lakes and ponds, the Manual says the appropriate Chapter 105 permits must be obtained from DEP wherever the structures described in that section (such as cofferdams) are installed, and that a cofferdam is usually sufficient to protect impounded water from construction turbidity because water within a lake or pond typically has no appreciable flow velocity. [32]
When an earth disturbance or any stage of it is finished, the site must immediately have topsoil restored, replaced or amended and be seeded, mulched or otherwise permanently stabilized; if work will stop for more than 4 days, the site must be immediately seeded, mulched or otherwise protected. Permanent stabilization can mean, among other options, a minimum uniform 70% perennial vegetative cover dense enough to resist accelerated erosion and sedimentation; once it is established, the temporary E&S BMPs must be removed. [34]
-
What E&S control means in practice (DEP E&S Manual): divert off-site surface water away from areas to be disturbed where feasible; collect runoff from disturbed areas and convey it to a sediment basin, sediment trap or other BMP for sediment removal; minimize the extent of disturbance and the time between initial disturbance and final stabilization; preserve existing vegetation, especially trees; and treat water pumped from excavations for sediment.
DEP, Erosion and Sediment Pollution Control Program Manual (386-2134-001, eff. Mar. 31, 2012), Chapter 1 [32]Show the source text
All off-site surface water should be diverted away from areas to be disturbed (wherever feasible); all runoff from disturbed areas should be collected and conveyed to a sediment basin, sediment trap, or other BMP for sediment removal. The extent of the disturbance, as well as the time period between initial disturbance and final stabilization, should be minimized. Existing vegetation, especially existing trees, should be preserved wherever possible ... Sediment removal treatment for water pumped from excavations is usually needed.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementE&S BMPs must be designed, implemented and maintained to minimize accelerated erosion and sedimentation, using BMPs and design standards listed in DEP's Erosion and Sediment Pollution Control Program Manual; other BMPs or design standards may be used when the person demonstrates to DEP that they achieve the regulatory standard. Activities requiring an NPDES permit must also comply with the federal construction and development effluent guidelines at 40 CFR Part 450.
25 Pa. Code § 102.11(a)(1), (b), (c) [33]Show the source text
Design, implement and maintain E&S BMPs to minimize the potential for accelerated erosion and sedimentation ... Various E&S BMPs and their design standards are listed in the Erosion and Sediment Pollution Control Program Manual ... BMPs and design standards other than those listed in the manuals or Buffer Guidance may be used when ... demonstrates to the Department that the alternate BMP or design standard minimizes accelerated erosion and sedimentation ... Activities requiring an NPDES permit under this chapter must also comply with 40 CFR Part 450
Open Pennsylvania Code & Bulletin (opens in a new tab) -
DEP's plain-English summary: the E&S Plan must show how land and water are protected against accelerated erosion and sedimentation using BMPs - for example minimizing earth disturbance, silt fence, mulch, channels, sediment traps, sediment basins, and establishing permanent stabilization - and must show the full extent of the site, BMP locations, and the timing and sequence of BMP installation. County conservation districts can provide guidance on plan development.
DEP Erosion and Sediment Control FAQ (v1.8, rev. Aug. 12, 2026), FAQ #5 [6]Show the source text
The E&S Plan must show how land and water resources are to be protected against accelerated erosion and sedimentation through the use of BMPs. Examples of BMPs include, but are not limited to: minimizing earth disturbance, silt fence, mulch, channels, sediment traps, sediment basins, and the establishment of permanent stabilization. The E&S Plan must show the full extent of the site, location of BMPs, the timing and sequence of BMP installation, and other information required by the regulations. CCDs can provide guidance for E&S Plan development.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
RequirementThe E&S Plan must be prepared by a person trained and experienced in E&S control methods applicable to the size and scope of the project. Unless DEP or the conservation district (after consulting DEP) authorizes otherwise, earth disturbance must be planned and implemented, to the extent practicable, to minimize the extent and duration of disturbance, maximize protection of existing drainage features and vegetation, minimize soil compaction, and use other measures that prevent or minimize increased stormwater runoff.
25 Pa. Code § 102.4(b)(3)-(4) [3]Show the source text
(3) The E&S Plan shall be prepared by a person trained and experienced in E&S control methods and techniques applicable to the size and scope of the project being designed. ... (i) Minimize the extent and duration of the earth disturbance. ... (ii) Maximize protection of existing drainage features and vegetation. ... (iii) Minimize soil compaction. ... (iv) Utilize other measures or controls that prevent or minimize the generation of increased stormwater runoff.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementRequired E&S Plan contents include, among other listed items: the volume and rate of runoff from the project site and its upstream watershed; the location and Chapter 93 classification of all surface waters that may receive runoff; a maintenance program providing for BMP inspection weekly and after each stormwater event, with a written report documenting each inspection; and identification of potential thermal impacts to surface waters.
25 Pa. Code § 102.4(b)(5)(iv), (v), (x), (xiii) [3]Show the source text
(iv) The volume and rate of runoff from the project site and its upstream watershed area. ... (v) The location of all surface waters of this Commonwealth which may receive runoff within or from the project site and their classification under Chapter 93. ... the inspection of BMPs on a weekly basis and after each stormwater event ... The program must provide for completion of a written report documenting each inspection ... (xiii) Identification of potential thermal impacts to surface waters of this Commonwealth from the earth disturbance activity
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessDEP's E&S Manual on sequencing: every earthmoving project requiring a written E&S Plan needs a BMP installation sequence; controls should be installed and functioning before clearing and grubbing, with initial clearing limited to what is needed to install perimeter BMPs; and for permitted sites the NPDES (or other Chapter 102) permit must be obtained before clearing and grubbing begins.
DEP, Erosion and Sediment Pollution Control Program Manual (386-2134-001), Chapter 2 - BMP Sequencing [32]Show the source text
A BMP sequence must be provided for every earthmoving project requiring a written E&S plan. ... Appropriate controls should be installed and functioning prior to clearing and grubbing. ... Initial clearing should be limited to that which is necessary to ... install the proposed perimeter BMPs. ... For permitted sites, the NPDES permit, ESCP permit or ESCGP ... permit must be obtained prior to beginning clearing and grubbing operations.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementDEP's E&S Manual on earthwork within lakes and ponds: wherever the structures in that section are installed (for example, cofferdams for in-pond work), the appropriate Chapter 105 permits must be obtained and designs must follow them. The manual says a cofferdam is usually sufficient to protect impounded water from construction turbidity, because pond water typically has no appreciable flow velocity.
DEP, Erosion and Sediment Pollution Control Program Manual (386-2134-001), Chapter 3, "Earthwork within Lakes and Ponds" [32]Show the source text
EARTHWORK WITHIN LAKES AND PONDS ... NOTE: Wherever the structures described in this section are installed, the appropriate Chapter 105 permits must be obtained from the Department. Designs shall adhere to the conditions of those permits. ... Since the water within a lake or pond typically has no appreciable flow velocity, a cofferdam is usually sufficient to protect impounded water from the turbidity caused by construction activity.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementSite stabilization: upon final completion of an earth disturbance or any stage or phase of it, the site must immediately have topsoil restored, replaced or amended and be seeded, mulched or otherwise permanently stabilized; permanent stabilization means (among the options) a minimum uniform 70% perennial vegetative cover dense enough to resist accelerated erosion. Temporary E&S BMPs are removed once permanent stabilization is established. If work will stop for more than 4 days, the site must be immediately seeded, mulched or otherwise protected.
25 Pa. Code § 102.22(a)-(b) [34]Show the source text
Upon final completion of an earth disturbance activity or any stage or phase of an activity, the site shall immediately have topsoil restored, replaced, or amended, seeded, mulched or otherwise permanently stabilized ... Once permanent stabilization has been established, the temporary E&S BMPs shall be removed. ... A minimum uniform 70% perennial vegetative cover, with a density capable of resisting accelerated erosion and sedimentation. ... where a cessation of earth disturbance activities will exceed 4 days, the site shall be immediately seeded, mulched, or otherwise protected
Open Pennsylvania Code & Bulletin (opens in a new tab)
Buffers, post-construction stormwater and special-protection waters
A person proposing a new earth disturbance that needs Chapter 102 permit coverage or another new DEP permit requiring compliance with Chapter 102 must ensure a written PCSM Plan is developed, implemented, operated and maintained; PCSM must be planned, to the extent practicable, to prevent an increase in the rate of runoff, minimize any increase in runoff volume and minimize impervious areas. A licensed professional or designee must be on site and responsible during critical stages of PCSM Plan implementation, and for any property containing a PCSM BMP the permittee must record an instrument with the recorder of deeds that discloses the BMP and gives notice that responsibility for its long-term operation and maintenance is a covenant that runs with the land. [35]
Where a project needs a Chapter 102 permit and any receiving surface water is classified HQ or EV, the permit application must evaluate and include nondischarge alternatives in the E&S Plan or demonstrate that none exist, in which case the E&S Plan must include antidegradation best available combination of technologies (ABACT), except as provided in § 93.4c(b)(1)(iii). DEP's PAG-02 fact sheet says DEP will deny coverage where, among other conditions, stormwater discharges directly to surface waters, including wetlands, with a designated or existing HQ or EV use, or the construction may adversely affect a Pennsylvania or federal threatened or endangered species or its critical habitat. [3][19]
As codified in its 2010 text, § 102.14 says that, except as provided in § 102.14(d), a project needing a Chapter 102 permit in an EV or HQ watershed attaining its designated use (as listed by DEP at the time of application) may not disturb earth within 150 feet of a perennial or intermittent river, stream or creek, or a lake, pond or reservoir, and must protect any existing riparian buffer. Around a pond, the buffer is measured horizontally and perpendicular to the bank from the normal pool elevation. [10]
The § 102.14(d) exceptions include, among others, project sites more than 150 feet from a river, stream, creek, lake, pond or reservoir, activities involving less than 1 acre of earth disturbance, and activities that do not need Chapter 102 permit coverage. Act 162 of 2014 amended the Clean Streams Law to let a person whose earth disturbance requires an NPDES stormwater permit under Chapter 102 use a riparian buffer or riparian forest buffer, or other BMPs, design standards and alternatives that are collectively substantially equivalent in effectiveness; the conflict note above covers how far that reaches. [7][10]
-
RequirementPost-construction stormwater management (PCSM): anyone proposing a new earth disturbance activity that requires Chapter 102 permit coverage must ensure a written PCSM Plan is developed, implemented, operated and maintained. PCSM must be planned, to the extent practicable, to prevent an increase in the rate of stormwater runoff, minimize any increase in runoff volume, and minimize impervious areas.
Applies when: Earth disturbance requiring a Chapter 102 permit 25 Pa. Code § 102.8(a)-(b) [35]Show the source text
a person proposing a new earth disturbance activity that requires permit coverage under this chapter or other new Department permit that requires compliance with this chapter shall be responsible to ensure that a written PCSM Plan is developed, implemented, operated and maintained in accordance with this section. ... (2) Prevent an increase in the rate of stormwater runoff. ... (3) Minimize any increase in stormwater runoff volume. ... (4) Minimize impervious areas.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementPCSM applies beyond NPDES permits. After November 19, 2010, anyone proposing a new earth disturbance that requires Chapter 102 permit coverage, or "other new Department permit that requires compliance with this chapter", must ensure a written PCSM Plan is developed, implemented, operated and maintained under § 102.8.
25 Pa. Code § 102.8(a) [35]Show the source text
(a) PCSM applicability. After November 19, 2010, a person proposing a new earth disturbance activity that requires permit coverage under this chapter or other new Department permit that requires compliance with this chapter shall be responsible to ensure that a written PCSM Plan is developed, implemented, operated and maintained in accordance with this section.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementPCSM long-term obligations: a licensed professional (or designee) must be onsite and responsible during critical stages of PCSM Plan implementation; and for any property containing a PCSM BMP, the permittee must record an instrument with the recorder of deeds disclosing the BMP and giving notice that responsibility for its long-term operation and maintenance is a covenant that runs with the land, binding on and enforceable by later owners.
25 Pa. Code § 102.8(k), (m)(2) [35]Show the source text
(k) Licensed professional oversight of critical stages. A licensed professional or a designee shall be present onsite and be responsible during critical stages of implementation of the approved PCSM Plan. ... the permittee or co-permittee shall record an instrument with the recorder of deeds which will assure disclosure of the PCSM BMP ... provide notice that the responsibility for long-term operation and maintenance of the PCSM BMP is a covenant that runs with the land that is binding upon and enforceable by subsequent grantees
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementSpecial protection (High Quality / Exceptional Value) waters: for earth disturbance that requires a Chapter 102 permit where any receiving surface water is classified HQ or EV under Chapter 93, the applicant must, in the permit application, evaluate and include nondischarge alternatives in the E&S Plan unless it demonstrates none exist; if it demonstrates none exist, the E&S Plan must include ABACT (antidegradation best available combination of technologies), except as provided in 25 Pa. Code § 93.4c(b)(1)(iii).
Applies when: Permitted earth disturbance with any HQ or EV receiving water 25 Pa. Code § 102.4(b)(6) [3]Show the source text
for an earth disturbance activity that requires a permit under this chapter and for which any receiving surface waters of this Commonwealth is classified as High Quality or Exceptional Value under Chapter 93, the person proposing the activity shall, in the permit application, do the following: ... (i) Evaluate and include nondischarge alternatives in the E&S Plan, unless a person demonstrates that nondischarge alternatives do not exist for the project. ... nondischarge alternatives do not exist for the project, the E&S Plan must include ABACT, except as provided in § 93.4c(b)(1)(iii).
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ExemptionPAG-02 ineligibility: DEP will deny PAG-02 coverage when, among other listed conditions, stormwater discharges go directly to surface waters, including wetlands, with a designated or existing use of HQ or EV; the construction may adversely affect a Pennsylvania or federal endangered or threatened species or its critical habitat; or discharges go to waters impaired for siltation, turbidity and similar causes unless managed with a non-discharge alternative or ABACT BMPs.
DEP, PAG-02 Fact Sheet (Rev. 8/2024), Eligibility Criteria 9, 13, 14 [19]Show the source text
DEP will deny coverage under the PAG-02 General Permit when one or more of the following conditions exist: ... Stormwater discharges directly to surface waters, including wetlands, with a designated or existing use of ... High-Quality Waters (HQ) or Exceptional Value Waters (EV) ... may adversely affect a Pennsylvania or federal endangered or threatened species or its critical habitat. ... Stormwater discharges to surface waters identified as waters impaired for siltation; turbidity; ... unless the discharges will be managed with a non-discharge alternative or Antidegradation Best Available
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementRiparian buffer rule in special protection watersheds (as codified in the 2010 text): except as provided in the § 102.14(d) exceptions, when earth disturbance requires a Chapter 102 permit and the project site is in an Exceptional Value or High Quality watershed attaining its designated use (as listed by DEP at the time of application), earth disturbance may not be conducted within 150 feet of a perennial or intermittent river, stream or creek, or a lake, pond or reservoir, and any existing riparian buffer must be protected. Newly established riparian forest buffers along special protection waters total 150 feet (50 feet in Zone 1 and 100 feet in Zone 2).
Applies when: Permitted earth disturbance in HQ/EV watersheds within 150 ft of streams, lakes, ponds or reservoirs 25 Pa. Code § 102.14(a)(1), (b)(2)(ii) [10]Show the source text
Except as in accordance with subsection (d) ... when the activity requires a permit under this chapter may not conduct earth disturbance activities within 150 feet of a perennial or intermittent river, stream, or creek, or lake, pond or reservoir when the project site is located in an exceptional value or high quality watershed attaining its designated use as listed by the Department at the time of application and shall protect any existing riparian buffer ... A total of 150 feet (45.7 meters), comprised of 50 feet (15.2 meters) in Zone 1 and 100 feet (30.5 meters) in Zone 2
Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab) -
RequirementRiparian buffer rules name ponds. Except as provided in § 102.14(d), persons whose earth disturbance requires a Chapter 102 permit, where the project site is in an exceptional value or high quality watershed attaining its designated use, may not conduct earth disturbance within 150 feet of a perennial or intermittent river, stream or creek, or a lake, pond or reservoir, and must protect any existing riparian buffer. Buffers must be measured horizontally and perpendicular to the bank from the normal pool elevation of a lake, pond or reservoir (and from top of streambank), with no more than a 10% variation below the minimum width.
Applies when: Projects requiring a Chapter 102 permit in EV/HQ watersheds attaining their designated use, subject to the § 102.14(d) exceptions 25 Pa. Code § 102.14(a)(1), (c)(3) [10]Show the source text
when the activity requires a permit under this chapter may not conduct earth disturbance activities within 150 feet of a perennial or intermittent river, stream, or creek, or lake, pond or reservoir when the project site is located in an exceptional value or high quality watershed attaining its designated use ... (3) Measurements. Riparian buffers must be measured horizontally and perpendicularly to the bank with no more than a 10% variation below the minimum width from the normal pool elevation for lake, pond or reservoir and from top of streambank.
Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab) -
ExemptionThe mandatory riparian buffer requirement of § 102.14(a) does not apply to, among other listed exceptions: project sites more than 150 feet from a river, stream, creek, lake, pond or reservoir; activities involving less than 1 acre of earth disturbance; and activities for which Chapter 102 permit coverage is not required.
25 Pa. Code § 102.14(d)(1)(i)-(iii) [10]Show the source text
(i) A project site located greater than 150 feet (45.7 meters) from a river, stream, creek, lake, pond or reservoir. ... (ii) Activities involving less than 1 acre (0.4 hectare) of earth disturbance. ... (iii) Activities when permit coverage is not required under this chapter.
Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab) -
RequirementAct 162 of 2014 amended the Clean Streams Law so that, for earth disturbance requiring an NPDES stormwater permit under Chapter 102, the person may use or install either a riparian buffer/riparian forest buffer or other BMPs, design standards and alternatives that collectively are substantially equivalent to a buffer in effectiveness.
35 P.S. § 691.402(c)(1) (Clean Streams Law § 402(c)(1), added by Act 162 of 2014) [7]Show the source text
For persons proposing or conducting earth disturbance activities when the activity requires a National Pollutant Discharge Elimination System permit for storm water discharge under 25 Pa. Code Ch. 102 (relating to erosion and sediment control), the person may use or install either: ... (i) a riparian buffer or riparian forest buffer; or ... (ii) another option or options among available best management practices, design standards and alternatives that collectively are substantially equivalent to a riparian buffer or riparian forest buffer in effectiveness
Open Pennsylvania General Assembly (opens in a new tab)
Who reviews it, fees and timing
DEP says county conservation districts with trained staff are delegated to review E&S Plans, process permit applications, conduct training, inspect sites and, in certain circumstances, take enforcement actions; every county except Philadelphia has a district. DEP's individual NPDES permit instructions (Rev. 7/2026) say that in every county except Forest and Philadelphia, the district is the initial recipient of individual NPDES application packages, and projects in more than two counties within one DEP regional office's jurisdiction are submitted to that regional office. [6][12]
Chapter 102's codified fees are a $500 administrative filing fee for general permits and $1,500 for individual permits, plus $100 per disturbed acre for projects of 1 acre or more (rounded to the closest whole acre), and conservation districts may charge additional fees. Holders of an individual NPDES permit for construction stormwater also pay a $500 annual fee under Chapter 92a; for permits first issued after August 28, 2021, it is due on each anniversary of the permit's effective date until DEP terminates the permit. [27][36]
In its July 2026 Chapter 102 fee report to the Environmental Quality Board, DEP said it plans to evaluate increasing Chapter 102 permit fees and, depending on that evaluation, may draft a proposed rulemaking; the report itself does not change the fees. No Chapter 102 rulemaking, proposed or final, appears in the Pennsylvania Bulletin's 2026 list of Pa. Code chapters affected as printed in the Sept. 26, 2026 issue, and DEP's Regulatory Update dated Sept. 28, 2026, its status chart of Environmental Quality Board regulations, lists no rulemaking identified as amending Chapter 102 at any stage. [37][38][39]
A complete application package for a new individual NPDES permit is due at least 120 calendar days before the planned start of construction. Under Executive Order 2023-07, DEP has 81 business days to take final action on PAG-02 NOIs for new, renewed and amended coverage and 117 business days on new, renewal and amendment individual permit applications (22 business days for transfer applications). If DEP does not act within those periods, fees may be refunded under its "PAyback" policy (for individual permits, the disturbed acreage fees). PAyback applies only to DEP, not to conservation districts; for PAG-02 it applies only when DEP, not a district, received the NOI. [12][40][41]
Except for local stormwater approvals, a municipality or county may not issue a building or other permit or approval to someone whose earth disturbance requires a Chapter 102 permit until DEP or the conservation district has issued that permit or approved general-permit coverage. [42]
Upon permanent stabilization and installation of BMPs in accordance with an approved plan, the permittee must submit a Notice of Termination to DEP or the conservation district. Until it receives written approval of the notice, the permittee remains responsible for complying with the permit, including long-term operation and maintenance of all PCSM BMPs; DEP or the district will conduct a final inspection and approve or deny the notice within 30 days. [43]
-
AgencyDEP describes the district role: county conservation districts with trained staff are delegated to review E&S Plans, process permit applications, conduct training, perform site inspections and, in certain circumstances, take enforcement actions. Every Pennsylvania county except Philadelphia has a conservation district office (the Philadelphia Water Department performs many of these functions).
DEP Erosion and Sediment Control FAQ (v1.8), FAQ #4 [6]Show the source text
CCDs with trained staff are delegated the responsibility to review E&S Plans, process permit applications, conduct training, perform site inspections, and in certain ... circumstances, conduct enforcement actions. Every county in Pennsylvania except Philadelphia ... County has a CCD office (although the Philadelphia Water Department performs many of these ... functions and collaborates closely with DEP).
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
ProcessIndividual NPDES permit (construction stormwater): generally needed when a project will not qualify for a general NPDES permit. A complete application package for a new permit must be submitted at least 120 calendar days before the planned start of construction. In all counties except Forest and Philadelphia, the county conservation district is the initial recipient of application packages, but projects in more than two counties within the jurisdiction of one DEP regional office are submitted to that DEP regional office.
DEP, Individual NPDES Permit Application Instructions (3800-PM-BCW0408a Rev. 7/2026) [12]Show the source text
For all counties in Pennsylvania except for Forest and Philadelphia counties, the County Conservation District (CCD) is the initial recipient ... the submission of an Individual NPDES Permit Application package is necessary when an applicant’s project will not qualify for coverage under a General NPDES Permit. ... at least 120 calendar days prior to the planned date for commencing construction. ... more than two counties but within the jurisdiction of the same DEP regional office, submit the application package to the appropriate DEP regional office.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
FeeChapter 102 permit fees as codified in 25 Pa. Code § 102.6: $500 administrative filing fee for general permits and $1,500 for individual permits, plus $100 per disturbed acre for projects of 1 acre or more (fractional acreage rounded to the closest whole number). Conservation districts may charge additional fees under the Conservation District Law.
25 Pa. Code § 102.6(b)(1), (3) [27]Show the source text
a $500 administrative filing fee for general permits and a $1,500 administrative filing fee for individual permits. In addition, $100 for each disturbed acre is required to be added to the base administrative filing fee for projects of 1 acre or greater of disturbance. The fees will be calculated based upon the following formula: base fee plus $100 for each disturbed acre. For fractional acreage, the acreage shall be rounded to the closest whole number. ... (3) Conservation districts may charge additional fees in accordance with section 9(13) of the Conservation District Law
Open Pennsylvania Code & Bulletin (opens in a new tab) -
FeeHolders of an individual NPDES permit for stormwater associated with construction activities also pay a $500 annual fee under Chapter 92a; for permits first issued after August 28, 2021, it is due on each anniversary of the permit's effective date until DEP terminates the permit.
Applies when: Individual (not general) NPDES construction stormwater permits 25 Pa. Code § 92a.62(a)-(b) [36]Show the source text
The annual fee for permits issued for the first time after August 28, 2021, is due on each anniversary of the effective date of the initial permit until the Department terminates the permit. ... | Stormwater Associated with Construction Activities | $500
Open Pennsylvania Code & Bulletin (opens in a new tab) -
StatusFee status: in its three-year Chapter 102 fee report to the Environmental Quality Board (July 2026), DEP stated that it plans to evaluate increasing Chapter 102 permit fees and, depending on that evaluation, may draft a proposed rulemaking; the report itself does not change the fees.
DEP, 3-Year Regulatory Fee and Program Cost Analysis Report to the EQB - Chapter 102 (July 2026) [37]Show the source text
Based on the analysis in this report, DEP plans to evaluate the potential for increasing Chapter 102 permit fees. Depending on this evaluation, DEP may draft a proposed rulemaking to address the disparity between program costs and sustainable funding sources including fee revenues.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
TimelineReview time commitment (PAG-02): under Governor's Executive Order 2023-07, DEP has 81 business days to take final action on PAG-02 NOIs for new, renewed and amended coverage; failure may result in a fee refund ("PAyback") if DEP received the NOI, but PAyback does not apply to PAG-02 NOIs received by conservation districts.
DEP SOP BCW-102-002, Review of PAG-02 NOIs (v1.6, rev. June 11, 2025) [40]Show the source text
Under the Governor’s Executive Order 2023-07 (Building Efficiency in the Commonwealth’s Permitting, Licensing, and Certification Processes), DEP has 81 business days to take a final action on PAG-02 NOIs for new, renewed, and amended coverage. Failure to take action within this period of time may result in a refund in fees (“PAyback”) if DEP is the recipient of the NOI. PAyback does not apply to PAG-02 NOIs received by CCDs.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
TimelineReview time commitment (individual NPDES construction stormwater permit): under Executive Order 2023-07, DEP has 117 business days to take final action on new, renewal and amendment applications and 22 business days for transfers; failure may result in a refund of disturbed acreage fees (PAyback), which applies to DEP only, not to conservation districts.
DEP SOP BCW-102-003, Review of Individual NPDES Permit Applications (v1.9, rev. Feb. 2, 2026) [41]Show the source text
DEP has 117 business days to take a final action on new, renewal, and amendment individual permit applications for stormwater discharges associated with earth disturbance activities and 22 business days for transfer applications. Failure to take action within this period of time may result in a refund in disturbed acreage fee(s) (“PAyback”). PAyback refund policies impact DEP only; CCDs are not subject to the PAyback refund policy.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
ProcessMunicipal permit hold: except for local stormwater approvals, a municipality or county may not issue a building or other permit or approval to someone whose earth disturbance requires a DEP Chapter 102 permit until DEP or the conservation district has issued the E&S or individual NPDES permit or approved general NPDES permit coverage.
25 Pa. Code § 102.43 [42]Show the source text
With the exception of local stormwater approvals or authorizations, a municipality or county may not issue a building or other permit or approval to those proposing or conducting earth disturbance activities requiring a Department permit until the Department or a conservation district has issued the E&S or individual NPDES Permit, or approved coverage under the general NPDES Permit for Stormwater Discharges Associated With Construction Activities
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessPermit termination: upon permanent stabilization under § 102.22(a)(2) and installation of BMPs in accordance with an approved plan, the permittee or co-permittee submits a Notice of Termination (NOT) to DEP or the conservation district. The permittee remains responsible for compliance with the permit terms and conditions, including long-term operation and maintenance of all PCSM BMPs, until it receives written approval of the NOT; DEP or the district will conduct a final inspection and approve or deny the NOT within 30 days.
25 Pa. Code § 102.7(a), (c) [43]Show the source text
Upon permanent stabilization of the earth disturbance activity under § 102.22(a)(2) ... and installation of BMPs in accordance with an approved plan ... shall submit a notice of termination to the Department or conservation district. ... Until the permittee or co-permittee has received written approval of a notice of termination ... will remain responsible for compliance with the permit terms and conditions including long-term operation and maintenance of all PCSM BMPs ... will conduct a final inspection and approve or deny the notice of termination within 30 days.
Open Pennsylvania Code & Bulletin (opens in a new tab)
More detail
More detail: 47 more verified statements on Pennsylvania erosion, sediment and construction stormwater rules
-
Pennsylvania's erosion and sediment control regulations, 25 Pa. Code Chapter 102, are issued under sections 5 and 402 of The Clean Streams Law (35 P.S. §§ 691.5 and 691.402). The chapter was originally adopted September 29, 1972, effective October 30, 1972.
25 Pa. Code Chapter 102 (Authority and Source notes) [44]Show the source text
The provisions of this Chapter 102 issued under sections 5 and 402 of The Clean Streams Law (35 P.S. § § 691.5 and 691.402), unless otherwise noted. ... The provisions of this Chapter 102 adopted September 29, 1972, effective October 30, 1972, 2 Pa.B. 1796, unless otherwise noted.
Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab) -
RequirementUnder section 402 of The Clean Streams Law, when DEP finds that an activity creates a danger of pollution of the waters of the Commonwealth, DEP may by rule or regulation require that the activity be conducted only under a DEP permit. Once a permit is required by such rules, conducting the activity without a permit is unlawful and is declared a nuisance.
35 P.S. § 691.402(a)-(b) (Clean Streams Law § 402(a)-(b)) [7]Show the source text
Whenever the department finds that any activity, not otherwise requiring a permit under this act, ... creates a danger of pollution of the waters of the Commonwealth ... the department may, by rule or regulation, require that such activity be conducted only pursuant to a permit issued by the department ... it shall be unlawful for a person or municipality to conduct the activity regulated except pursuant to a permit issued by the department. Conducting such activity without a permit, ... is hereby declared to be a nuisance.
Open Pennsylvania General Assembly (opens in a new tab) -
DefinitionThe Clean Streams Law defines "waters of the Commonwealth" to include ponds, impoundments, dammed water, springs, ditches and all other bodies or channels of surface and underground water, whether natural or artificial.
35 P.S. § 691.1 (Clean Streams Law § 1, definition of "Waters of the Commonwealth") [7]Show the source text
"Waters of the Commonwealth" shall be construed to include any and all rivers, streams, creeks, rivulets, impoundments, ditches, water courses, storm sewers, lakes, dammed water, ponds, springs and all other bodies or channels of conveyance of surface and underground water, or parts thereof, whether natural or artificial, within or on the boundaries of this Commonwealth.
Open Pennsylvania General Assembly (opens in a new tab) -
DefinitionThe "NPDES Permit for Stormwater Discharges Associated With Construction Activities" is the permit required for the discharge or potential discharge of stormwater into waters of the Commonwealth from construction activities (including clearing and grubbing, grading and excavation) involving 1 acre (0.4 hectare) or more of earth disturbance, or earth disturbance on any portion, part, or stage of a larger common plan of development or sale involving 1 acre or more over the life of the project.
25 Pa. Code § 102.1 (definition of "NPDES Permit for Stormwater Discharges Associated With Construction Activities") [1]Show the source text
NPDES Permit for Stormwater Discharges Associated With Construction Activities—A permit required for the discharge or potential discharge of stormwater into waters of this Commonwealth from construction activities, including clearing and grubbing, grading and excavation activities involving 1 acre (0.4 hectare) or more of earth disturbance activity or an earth disturbance activity on any portion, part, or during any stage of, a larger common plan of development or sale that involves 1 acre (0.4 hectare) or more of earth disturbance activity over the life of the project.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
DefinitionAn "E&S Plan" is a site-specific plan of drawings and narrative identifying BMPs to minimize accelerated erosion and sedimentation before, during and after earth disturbance; a "PCSM plan" is a site-specific plan of drawings and narrative identifying BMPs to manage changes in stormwater runoff volume, rate and water quality after earth disturbance activities have ended and the project site is permanently stabilized. "Surface waters" include perennial and intermittent streams, rivers, lakes, reservoirs, ponds, wetlands, springs, natural seeps and estuaries, but exclude water at facilities approved for wastewater treatment.
25 Pa. Code § 102.1 (definitions of "E&S Plan", "PCSM plan", "Surface waters") [1]Show the source text
Sediment Control Plan—A site-specific plan consisting of both drawings and a narrative that identifies BMPs to minimize accelerated erosion and sedimentation before, during and after earth disturbance activities. ... to manage changes in stormwater runoff volume, rate and water quality after earth disturbance activities have ended and the project site is permanently stabilized. ... Surface waters—Perennial and intermittent streams, rivers, lakes, reservoirs, ponds, wetlands, springs, natural seeps, and estuaries, excluding water at facilities approved for wastewater treatment
Open Pennsylvania Code & Bulletin (opens in a new tab) -
DefinitionChapter 102 defines "earth disturbance activity" as a construction or other human activity that disturbs the land surface, listing among other things land clearing and grubbing, grading, excavations, embankments, land development and the moving, depositing, stockpiling or storing of soil, rock or earth materials. The same list also names agricultural plowing or tilling and operation of animal heavy use areas as earth disturbance activities. The definition does not name ponds.
25 Pa. Code § 102.1 (definition of "Earth disturbance activity") [1]Show the source text
Earth disturbance activity—A construction or other human activity which disturbs the surface of the land, including land clearing and grubbing, grading, excavations, embankments, land development, agricultural plowing or tilling, operation of animal heavy use areas, timber harvesting activities, road maintenance activities, oil and gas activities, well drilling, mineral extraction, and the moving, depositing, stockpiling, or storing of soil, rock or earth materials.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
DefinitionChapter 102 defines a "conservation plan" as a plan that identifies conservation practices and includes site-specific BMPs for agricultural plowing or tilling activities and animal heavy use areas. The definition is tied to those two activity types and does not mention construction.
25 Pa. Code § 102.1 (definition of "Conservation plan") [1]Show the source text
Conservation plan—A plan that identifies conservation practices and includes site specific BMPs for agricultural plowing or tilling activities and animal heavy use areas.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
Size cutoffNPDES construction stormwater permit threshold: other than agricultural plowing or tilling, animal heavy use areas, timber harvesting and road maintenance, anyone proposing earth disturbance of 1 acre (0.4 hectare) or more, or disturbance on any part or stage of a larger common plan of development or sale totaling 1 acre or more, must obtain an individual NPDES permit or general NPDES permit coverage for Stormwater Discharges Associated With Construction Activities before starting the earth disturbance.
Applies when: Pond excavation/embankment that is not agricultural plowing or tilling 25 Pa. Code § 102.5(a) [4]Show the source text
Other than agricultural plowing or tilling activities, animal heavy use areas, timber harvesting activities or road maintenance activities, a person proposing an earth disturbance activity that involves equal to or greater than 1 acre (0.4 hectare) of earth disturbance ... shall obtain an individual NPDES Permit or coverage under a general NPDES permit for Stormwater Discharges Associated With Construction Activities prior to commencing the earth disturbance activity.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
Size cutoffOther Chapter 102 permit thresholds: an E&S Permit is required for timber harvesting or road maintenance involving 25 acres (10 hectares) or more of earth disturbance; for oil and gas activities involving 5 acres (2 hectares) or more over the life of the project; and (other than agricultural plowing/tilling, AHUAs, timber harvesting or road maintenance) for earth disturbance of 5 acres or more over the life of the project that does not require a permit under subsections (a)-(c).
25 Pa. Code § 102.5(b)-(d) [4]Show the source text
timber harvesting or road maintenance activity involving 25 acres (10 hectares) or more of earth disturbance shall obtain an E&S Permit ... oil and gas activities that involve 5 acres (2 hectares) or more of earth disturbance over the life of the project ... Other than agricultural plowing or tilling activities, animal heavy use areas, timber harvesting or road maintenance activities ... 5 acres (2 hectares) or more of earth disturbance over the life of the project that do not require a permit under subsections (a), (b), and (c), shall obtain an E&S Permit
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessMunicipal notice: a municipality or county that issues building or other permits must notify DEP or the conservation district within 5 days of receiving a permit application involving 1 acre (0.4 hectare) or more of earth disturbance.
25 Pa. Code § 102.42 [45]Show the source text
A municipality or county which issues building or other permits shall notify the Department or conservation district within 5 days of receipt of an application for a permit involving an earth disturbance activity consisting of 1 acre (0.4 hectare) or more.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementDEP's agricultural E&S manual states that an Agricultural E&S Plan does not cover construction activities: construction on an agricultural operation may require a Construction E&S Plan and, depending on the acres disturbed, an NPDES permit.
Applies when: Construction on an agricultural operation DEP, Soil Erosion and Sediment Control Manual for Agricultural Operations (383-4200-002, eff. Oct. 5, 2019) [22]Show the source text
An Ag E&S Plan does not cover construction activities; therefore, if a person is looking to commence construction on an agricultural operation, a Construction E&S Plan and, depending upon the acres disturbed, an NPDES permit may be necessary.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementDEP guidance on farms: construction activities on agricultural lands that will disturb at least one acre must obtain NPDES permit coverage. DEP's examples of agricultural construction, which it says is not a complete list, are barn or home construction or expansion, new animal housing, compost facilities, equipment or vehicle lanes, and manure storage facilities. Ponds are not named.
DEP Erosion and Sediment Control FAQ (v1.8, rev. Aug. 12, 2026), FAQ #5 [6]Show the source text
Construction activities on agricultural lands that will disturb at least one acre must obtain NPDES permit coverage. Agricultural construction activities include, but are not limited to, barn or home construction or expansion; new animal housing; compost facilities; lanes for equipment or vehicle access; and manure storage facilities.
Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (opens in a new tab) -
DEP's Agricultural E&S Manual applies to agricultural operations with plowing or tilling (including no-till) and animal heavy use areas. By its own terms it does not apply to construction activities or to modifying structures or facilities on agricultural operations, and it points those to the construction E&S requirements of § 102.4(b).
DEP, Soil Erosion and Sediment Control Manual for Agricultural Operations (383-4200-002, Oct. 5, 2019), Applicability [22]Show the source text
This guidance applies to all agricultural operations that include plowing or tilling activities, including no-till, and AHUAs. This guidance does not apply to construction activities or to modification of structures or facilities associated with agricultural operations; refer to 25 Pa. Code § 102.4(b) for more information.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
York County Conservation District says construction on farms needs a written E&S Plan when it disturbs more than 5,000 square feet. It says NPDES permits are required for planned disturbance of over 1 acre when building structures such as barns, manure storages, houses, silos and bunk silos, and must be issued before earthmoving starts. It says normal plowing and tilling and installing BMPs such as waterways, barnyard improvements and animal walkways "may not need" an NPDES permit or construction E&S plan if the farm's Ag E&S Plan includes and addresses them. Ponds are not mentioned.
York County Conservation District, "Construction on Farms and Permitting" (web page) [13]Show the source text
Construction activities on farms require a written Erosion and Sedimentation Control Plan when disturbing more than 5,000 square feet ... NPDES Permits are required for planned disturbances of over 1 acre when building structures such as barns, manure storages ... Permits are to be issued prior to commencement of earthmoving. Normal plowing and tilling and the installation of BMP's such as waterways, barnyard improvements and animal walkways may not need an NPDES Permit or construction E&S plan as long as those activities are included and addressed in the farm's Ag E&S Plan.
Open York County Conservation District (opens in a new tab) -
RequirementWithin the agricultural E&S subsection (§ 102.4(a), which applies to agricultural plowing or tilling and animal heavy use areas), the portion of a conservation plan that identifies BMPs for those activities may be used to satisfy the E&S Plan requirements of that subsection if it meets § 102.4(a)(4)-(6) (cost-effective and reasonable BMPs, including limiting soil loss to T over the crop rotation; plan maps; and an implementation schedule).
25 Pa. Code § 102.4(a)(7) [3]Show the source text
(7) The portion of a conservation plan that identifies BMPs utilized to minimize accelerated erosion and sedimentation from agricultural plowing or tilling activities, or from operation of animal heavy use areas, may be used to satisfy the E&S Plan requirements of this subsection if it meets the requirements of paragraphs (4)—(6).
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessDEP's Agricultural E&S Manual: an NRCS Conservation Plan may serve as the Ag E&S Plan if it meets all of § 102.4(a) and the operator or landowner specifically asks NRCS for this. DEP, not NRCS, decides whether the NRCS plan satisfies the regulatory requirements.
DEP, Soil Erosion and Sediment Control Manual for Agricultural Operations (383-4200-002) [22]Show the source text
An NRCS Conservation Plan may fulfill the requirement of an Ag E&S Plan, but the operator/landowner must specifically request this during their consultation with NRCS. Additionally, the Department is the regulatory authority that determines if the NRCS Conservation Plan satisfies the Department's regulatory requirements of an Ag E&S Plan. ... NRCS Conservation Plan may fulfill requirements for an Ag E&S Plan if it meets all the requirements of 25 Pa. Code § 102.4(a), as requested by the operator/landowner; however, this determination is made by the Department.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
DEP's 2010 comment-response document says the 2010 agricultural revisions address "two primary sources of erosion on agricultural operations - crop fields and animal heavy use areas". It says they clarify that an NRCS conservation plan meeting the regulations can be used as the agricultural E&S plan.
Chapter 102 Comment-Response Document (2010 final rulemaking), General Comments, response to comment 25 [25]Show the source text
These regulations address the two primary sources of erosion on agricultural operations - crop fields and animal heavy use areas. This final rulemaking clarifies current regulations by specifying that an NRCS conservation plan (which meets the requirements of these regulations) can be used to meet the requirements for an agricultural E&S plan.
Open PA DEP / Environmental Quality Board (opens in a new tab) -
DEP's watershed-improvement permitting guide describes Chapter 105 General Permit GP-9 (Agricultural Activities) as authorizing certain agricultural activities that encroach into streams and their floodways or bodies of water: grassed or lined waterways, terraces, diversions, waste storage facilities and spring development. It also covers minor drainage that supports those activities and is necessary for contour strips, when part of an existing agricultural operation and implemented as part of a conservation plan consistent with Chapter 102 and approved by the county conservation district. Ponds are not on the GP-9 list in this DEP description.
DEP, The Pennsylvanian's Guide to Permitting for Watershed Improvement Projects (3300-BK-DEP5328), Chapter 105 general permits - GP-9 [46]Show the source text
GP-9 Agricultural Activities: This GP authorizes the installation, operation, modification, and maintenance of certain agricultural activities that encroach into streams and their floodways or bodies of water. These agricultural activities include: grassed or lined waterways, terraces, diversions, waste storage facilities, and spring development. Minor drainage that supports the above activities and is necessary for contour strips when part of an existing agricultural operation and implemented as part of a conservation plan consistent with Chapter 102 and approved by the CCD is also included.
Open PA DEP (opens in a new tab) -
ExemptionOther permit exclusions: an activity approved under a DEP permit issued under another chapter that includes requirements to comply with Chapters 92 and 102 needs no additional E&S Permit or NPDES construction stormwater permit; agricultural plowing/tilling and animal heavy use areas need no Chapter 102 permit; but anyone not required to obtain a Chapter 102 permit must still comply with the other provisions of Chapter 102.
25 Pa. Code § 102.5(g), (j), (k) [4]Show the source text
approved under a Department permit issued under a chapter other than Chapter 92 ... or this chapter, which includes requirements to comply with Chapter 92 and this chapter, need not obtain an additional E&S Permit or NPDES Permit ... (j) A person proposing or conducting agricultural plowing or tilling activities or animal heavy use areas is not required to obtain an E&S Permit ... (k) A person proposing or conducting an earth disturbance activity who is not required to obtain a permit under this chapter shall comply with the other provisions of this chapter.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementLink to Chapter 105 dam/encroachment permits: except for small projects, a Chapter 105 permit application must be accompanied by proof of an application for an Earth Disturbance Permit or an E&S control plan conforming to Chapter 102, including, if applicable, a letter from the county conservation district stating it reviewed the plan and considered it satisfactory. Earthmoving for all Chapter 105 projects, including small projects, must follow an earth disturbance plan.
Applies when: Embankment dams or other water obstructions/encroachments requiring a Chapter 105 permit 25 Pa. Code § 105.13(g) [11]Show the source text
Except for small projects, an application for a permit under this chapter shall be accompanied by proof of an application for an Earth Disturbance Permit or an erosion and sedimentation control plan ... The plan must conform to requirements in Chapter 102 ... and must include a copy of a letter from the conservation district ... indicating that the district has reviewed the erosion and sediment control plan of the applicant and considered it to be satisfactory, if applicable. Earthmoving activities, including small projects, shall be conducted pursuant to an earth disturbance plan.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementDuring construction of a dam, water obstruction or encroachment permitted under Chapter 105, the permittee must follow the Chapter 102 E&S plan submitted with the application, and construction must minimize erosion of the stream banks and bed.
Applies when: Chapter 105-permitted dam construction 25 Pa. Code § 105.46 [47]Show the source text
(a) During the construction of a dam, water obstruction or encroachment, the permittee shall follow the erosion and sediment control plan prepared in accordance with Chapter 102 (relating to erosion and sediment control) and submitted as part of the application. ... (b) Construction must be done in a manner to minimize erosion of banks and bed of the stream and disturbance of the regimen of the stream.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
In the 2010 final rulemaking preamble, the EQB said most comments on § 102.5(g) asked how it applies alongside other permits and authorizations. The EQB did not revise it, said "a comprehensive list of Department permits can be provided in guidance", and explained that other DEP permits that review Chapter 92 and 102 requirements in their own application process provide sufficient authorization, making a separate Chapter 102 permit duplicative. The preamble does not name Chapter 105 permits under § 102.5(g).
40 Pa.B. 4861 (Aug. 21, 2010), preamble, § 102.5 Permit requirements (subsection (g)) [48]Show the source text
The majority of comments received regarding this subsection requested clarification on the applicability in relationship with other permits under Chapter 92 and the authorizations needed. The Board has not revised this subsection in the final-form rulemaking. A comprehensive list of Department permits can be provided in guidance. ... As a result, these other Department permits provide sufficient authorization, so a separate authorization under permits identified in this chapter would be duplicative.
Open Pennsylvania Bulletin (opens in a new tab) -
PennDOT asked whether a bridge project with a Chapter 105 permit escapes a separate E&S or NPDES permit under § 102.5(g). DEP answered that a project issued a permit requiring compliance with both Chapter 92 and 102 would not need the additional NPDES or E&S permit, and again gave a mining or waste management permit as the example. It said activities outside the permitted mining or waste area may still need separate NPDES or E&S coverage.
Chapter 102 Comment-Response Document (2010 final rulemaking), § 102.5, response to comment 76 [25]Show the source text
102.5(g) states that a person conducting an earth disturbance activity under a ... If a bridge replacement project requires a Chapter 105 permit does that mean that a separate E&S permit or NPDES permit is not required ... If a permit that requires compliance with both Chapter 92 and 102 is issued for a project, then that project would not need to obtain the additional NPDES or E&S Permit. An example would be a mining or waste management permit. ... any activities outside the mining or waste area not permitted may need to be covered by a separate NPDES or E&S Permit under this Chapter.
Open PA DEP / Environmental Quality Board (opens in a new tab) -
ExemptionSection 102.5(i) text: a person doing earth disturbance associated with discharging dredged or fill material to waters of the United States who must obtain a Clean Water Act section 404 permit, or coverage under one, need not obtain an additional E&S Permit or NPDES construction stormwater permit "for the area of disturbance covered by the Clean Water Act section 404 permit".
25 Pa. Code § 102.5(i) [4]Show the source text
(i) A person proposing or conducting an earth disturbance activity associated with discharging dredged or fill material to waters of the United States which is required to obtain a permit or coverage under a permit under section 404 of the Federal Clean Water Act (33 U.S.C.A. § 1344) need not obtain an additional E&S Permit or NPDES Permit for Stormwater Discharges Associated With Construction Activities for the area of disturbance covered by the Clean Water Act section 404 permit.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ExemptionThe 2010 preamble on § 102.5(i): an activity authorized under section 404 does not require a separate E&S or NPDES permit for the activity covered by the 404 permit, so long as the project is a single and complete project, includes an E&S Plan meeting Chapter 102, and its earth disturbance does not exceed the footprint of the activities authorized by the 404 permit. The E&S Plan would also be approved as part of the section 401 water quality certification, and other activities would need E&S or NPDES coverage.
40 Pa.B. 4861 (Aug. 21, 2010), preamble, § 102.5 Permit requirements (subsection (i)) [48]Show the source text
When an activity is authorized under Chapter 404 of the Clean Water Act for example, that activity does not require a separate E&S or NPDES permit for the activity covered by the 404 Permit so long as the project is a single and complete project, includes an E&S Plan meeting the requirements of this chapter and the earth disturbance work does not exceed the footprint of the activities authorized by the 404 Permit. In addition, the E&S Plan would also be approved as part of the 401 Water Quality Certification. Other activities would need E&S or NPDES permit coverage.
Open Pennsylvania Bulletin (opens in a new tab) -
ProcessA permittee may not start a new discharge under PAG-02 until, among other conditions, it has obtained all other state and local permits and approvals arising from the earth disturbance in the NOI. DEP notes these may include Chapter 105 permits.
DEP, PAG-02 General Permit Fact Sheet (3800-PM-BCW0405g Rev. 8/2024) [19]Show the source text
A permittee may not commence a new discharge under the PAG-02 General Permit until the following conditions have been met: ... The applicant has obtained all other state and local permits and approvals arising out of the earth disturbance activities reported in the NOI, including sewage planning approval required by the Pennsylvania Sewage Facilities Act ... Note this may also include local building permits, highway occupancy permits, and Chapter 105 permits, as applicable.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
StatusThe Pennsylvania Code website reflects code changes effective through 56 Pa.B. 4026 (July 4, 2026). As shown there, § 102.5 was last amended August 20, 2010, effective November 19, 2010 (40 Pa.B. 4861), so § 102.5 had not been amended since 2010 as of that currency date.
25 Pa. Code § 102.5 (Source note); Pa. Code currency statement [4]Show the source text
The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 56 Pa.B. 4026 (July 4, 2026). ... amended August 20, 2010, effective November 19, 2010, 40 Pa.B. 4861.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
ProcessFor permitted earth disturbance, a preconstruction meeting is required unless DEP or the conservation district notifies otherwise in writing; the permittee must invite DEP or the district and give all invitees at least 7 days' notice. Operators who are not the permittee must be co-permittees. A Preparedness, Prevention and Contingency (PPC) Plan is required when fuels, chemicals, solvents, pesticides, fertilizers, lime, petrochemicals or other listed materials are stored, used or transported on the site during earth disturbance.
25 Pa. Code § 102.5(e), (h), (l) [4]Show the source text
a preconstruction meeting is required unless the permittee has been notified otherwise in writing by the Department or conservation district. The permittee shall invite the Department or conservation district to attend the preconstruction meeting and provide at least 7 days notice of the preconstruction meeting to all invited attendees. ... (h) Operators who are not the permittee shall be co-permittees. ... (l) A person shall prepare and implement a PPC Plan when storing, using or transporting materials including: fuels, chemicals, solvents, pesticides, fertilizers, lime, petrochemicals,
Open Pennsylvania Code & Bulletin (opens in a new tab) -
FeePAG-02 fees as published by DEP: a $500 administrative filing fee payable to the county conservation district's Clean Water Fund (or, in Forest or Philadelphia counties, to the Commonwealth Clean Water Fund); a disturbed-acreage fee of $100 per disturbed acre (rounded to the nearest whole acre) payable to the Commonwealth Clean Water Fund; and any additional fees the conservation district has set for NOI review.
54 Pa.B. 5536 (Aug. 31, 2024) [18]Show the source text
The fees for the PAG-02 General Permit include: 1) a $500 administrative filing fee that is payable to the appropriate CCD Clean Water Fund or, if earth disturbance will occur in Forest or Philadelphia counties, payable to the Commonwealth Clean Water Fund; 2) a disturbed acreage fee calculated by multiplying the number of disturbed acres (rounded to the nearest whole acre) by $100, payable to the Commonwealth Clean Water Fund; and 3) any additional fees that the CCD has established for review of the NOI for PAG-02 coverage.
Open Pennsylvania Bulletin / DEP (opens in a new tab) -
RequirementPAG-02 permittees must submit a complete Annual Report on DEP's template to the DEP/conservation district office that approved coverage by December 7 each year, covering the October 1 - September 30 reporting period.
Applies when: Projects with PAG-02 coverage PAG-02 General Permit (sample, 3800-PM-BCW0405d Rev. 1/2026), Part A III.D.1.a (citing 25 Pa. Code § 92a.61(g)) [31]Show the source text
The permittee must submit a complete Annual Report to the office of DEP/CCD that approved General ... Permit coverage by December 7 each year using DEP’s Annual Report template ... The Annual Report must address activities under this General Permit for the reporting period of October 1 – September 30.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
RequirementIndividual-permit modules for sensitive waters: Antidegradation Analysis Module 3 is required when stormwater will be discharged to surface waters with a designated or existing HQ or EV use (including EV wetlands); Riparian Buffer Module 4 is required when the project site will be within 150 feet of a perennial or intermittent river, stream, creek, lake, pond or reservoir with an HQ or EV designated use.
DEP, Individual NPDES Permit Application Instructions (Rev. 7/2026), items 11-12 [12]Show the source text
Module 3 must be attached when stormwater will be discharged (during or following earth disturbance activities) to surface waters ... that either: 1) have a designated or existing use under 25 Pa. Code Chapter 93 of High Quality Waters (HQ) or ... Exceptional Value Waters (EV), including EV wetlands ... Module 4 must be attached ... when the project site will be within 150 feet of a perennial or intermittent river, stream, or creek, lake, pond or ... reservoir with a designated use of HQ or EV.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
StatusThe current PAG-01 small-construction general permit was issued for a five-year term, effective March 1, 2022 and expiring February 28, 2027.
DEP, PAG-01 General Permit Fact Sheet (3800-PM-BCW0404e Rev. 4/2025) [28]Show the source text
DEP has decided to issue the PAG-01 General Permit for a five-year term, effective March 1, 2022 and expiring February 28, 2027.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
StatusProposed PAG-01 PCSM changes (draft): the site-restoration (Alternative 1) and sheet/concentrated-flow (Alternative 2) routes would remain. The impervious limits, no more than 30,000 square feet of new impervious surface within the disturbed area and no more than 12% total impervious surface on the site after construction, would apply only to Alternative 2. A new Alternative 3 would allow any amount of impervious surface less than 5 acres.
56 Pa.B. 5629 (Aug. 22, 2026), PCSM Alternatives [29]Show the source text
The existing two alternatives—implementing site restoration (Alternative 1) and implementing the sheet flow or concentrated, or both, flow standards (Alternative 2)—would remain. The impervious surface criteria of: (1) new impervious within the area of earth disturbance may not exceed 30,000 square feet; and (2) total impervious on the project site following construction may not exceed 12%, would apply only to Alternative 2. As a third alternative, any amount of impervious surface that is less than 5 acres may be proposed (Alternative 3).
Open Pennsylvania Bulletin (DEP notice) (opens in a new tab) -
ProcessProposed PAG-01 Alternative 3 conditions (draft): the applicant would prepare a PCSM Plan for municipal review and submit a new Municipal PCSM Plan Approval Form (3800-FM-BCW0404f) to DEP or the delegated conservation district. The form would be signed by a licensed professional employed or contracted by the municipality, who would attest that (1) the municipality has an ordinance requiring PCSM that is at least as stringent as DEP's PCSM requirements and (2) the applicant's PCSM Plan satisfies that ordinance. Alternative 3 would be available to projects in municipalities operating under an NPDES MS4 permit and in municipalities that have adopted an ordinance consistent with a current, DEP-approved stormwater management plan under the Storm Water Management Act.
56 Pa.B. 5629 (Aug. 22, 2026), PCSM Alternatives [29]Show the source text
Under Alternative 3, the applicant would prepare a PCSM Plan for municipal review ... signed by a licensed professional employed or contracted by the municipality and the licensed professional would need to attest that: (1) the municipality has an ordinance that requires PCSM and is at least as stringent as the Department's PCSM requirements; and (2) the applicant's PCSM Plan satisfies the requirements of the ordinance. This alternative would be available to applicants of projects within municipalities operating under an NPDES Municipal Separate Storm Sewer System (MS4) permit
Open Pennsylvania Bulletin (DEP notice) (opens in a new tab) -
TimelineDEP's timeline for the PAG-01 reissuance, as presented to the Water Resources Advisory Committee on September 9, 2026: draft published August 22, 2026; comment period ended September 21, 2026; estimated issuance January 2027; estimated effective date March 1, 2027. These are DEP estimates. DEP reported about 30 PAG-01 NOIs versus about 9,000 PAG-02 NOIs during 2023-2025.
DEP Bureau of Clean Water, Draft PAG-01 presentation to WRAC (Sept. 9, 2026), Background and Timeline slides [30]Show the source text
~ 9,000 PAG-02 NOIs received during 2023-2025 ... ~ 30 PAG-01 NOIs received during 2023-2025 ... Draft PAG-01 published in Pennsylvania Bulletin: August 22, 2026 ... End of public comment period: September 21, 2026 ... Estimated PAG-01 issuance date: January 2027 ... Estimated PAG-01 effective date: March 1, 2027
Open PA DEP Bureau of Clean Water (opens in a new tab) -
RequirementPCSM stormwater analysis standards for permitted projects: either meet the volume-reduction, water-quality and rate requirements of an applicable DEP-approved, current Act 167 stormwater management watershed plan, or (i) manage the net change in runoff volume and water quality for storms up to and including the 2-year/24-hour storm compared to pre-construction, treating existing non-forested pervious areas as meadow in good condition or its equivalent; and (ii) manage the net change in peak rate for the 2-, 10-, 50- and 100-year/24-hour storms so rates do not exceed pre-construction rates, demonstrated by hydrologic computations or a routing analysis.
25 Pa. Code § 102.8(g)(2)-(3) [35]Show the source text
requirements specified in an applicable Department approved and current Act 167 stormwater management watershed plan; or manage the net change for storms up to and including the 2-year/24-hour storm event when compared to preconstruction runoff volume and water quality. ... nonforested pervious areas must be considered meadow in good condition or its equivalent ... manage the net change in peak rate for the 2-, 10-, 50-, and 100-year/24-hour storm events in a manner not to exceed preconstruction rates. ... Hydrologic computations or a routing analysis are required
Open Pennsylvania Code & Bulletin (opens in a new tab) -
RequirementUnder Clean Streams Law § 402(c)(2), a project in a special protection watershed (a drainage list in 25 Pa. Code § 93.9) that proposes any earth disturbance within 100 feet of a surface water must offset any reduction in the total square footage of the buffer zone with a replacement buffer elsewhere along special protection waters in the same drainage list, as close as feasible to the disturbance, at a 1:1 ratio; any project incorporating such an alternative must also include other BMPs to manage post-construction stormwater.
35 P.S. § 691.402(c)(2) (Clean Streams Law § 402(c)(2), added by Act 162 of 2014) [7]Show the source text
A project located in a special protection watershed in a drainage list specified in 25 Pa. Code § 93.9 ... that proposes any earth disturbance within 100 feet of a surface water shall offset any reduction in the total square footage of the buffer zone ... with a replacement buffer elsewhere along special protection waters in the same drainage list and as close as feasible to the area of disturbance at a ratio of one-to-one. Any project incorporating such an alternative shall also include other best management practices to manage postconstruction storm water
Open Pennsylvania General Assembly (opens in a new tab) -
StatusDEP states that Act 162 of 2014 (signed October 22, 2014, effective December 21, 2014) addresses the Chapter 102 buffer requirements and pertains to individual NPDES permit applications for stormwater discharges associated with construction activities.
DEP, Act 162 (web page) [9]Show the source text
was signed into law on October 22, 2014, as Act 162 of 2014. Act 162 addresses buffer requirements in Pennsylvania regulations found in 25 Pa Code Chapter 102. The amendment pertains to individual NPDES permit applications for Stormwater Discharges Associated with Construction Activities, administered by DEP. Act 162 became effective December 21, 2014.
Open Pennsylvania Department of Environmental Protection (opens in a new tab) -
In 2010 the Pennsylvania Chamber of Business and Industry (commentator 1241) asked DEP to limit the PCSM Plan requirement to earth disturbance requiring an NPDES permit. DEP declined, saying § 102.8 applies whenever a permit is required under Chapter 102 "or another Chapter administered by the Department authorizing earth disturbance activities", all of which must comply with Chapter 93 because they have the potential to cause pollution through changes in stormwater runoff volume, rate, quality and temperature.
Chapter 102 Comment-Response Document (2010 final rulemaking), § 102.8(a), response to comment 50 [25]Show the source text
The Chamber requests that the wording of this section be changed limiting the requirement for a PCSM plan only to earth disturbances that require an NPDES permit. ... This section applies whenever a permit is required either under Chapter 102 or another Chapter administered by the Department authorizing earth disturbance activities, all of which must comply with the requirements of Chapters 93 because they have the potential to cause pollution due to changes in stormwater runoff volume, rate, quality and temperature
Open PA DEP / Environmental Quality Board (opens in a new tab) -
A commenter said a small repair within a stream channel requires a Chapter 105 permit, that all Chapter 105 permits require Chapter 102 compliance, and that a PCSM Plan would not be appropriate for such work. DEP disagreed with limiting PCSM but said that on minor projects with little or no change in site runoff, the PCSM plan may be only a sentence or two describing the situation.
Chapter 102 Comment-Response Document (2010 final rulemaking), § 102.8(a), comment and response 49 [25]Show the source text
a small repair to a pipeline or other structure within a stream channel requires a Chapter 105 permit. All Chapter 105 permits require compliance with Chapter 102 ... The Department disagrees. On minor projects where there is little or no change in the runoff characteristics from the site, the PCSM plan may only be a sentence or two describing the situation.
Open PA DEP / Environmental Quality Board (opens in a new tab) -
ExemptionPCSM relief in § 102.8(n) applies to site restoration or reclamation activities and small earth disturbance. For listed categories, including "Department permitted activities involving less than 1 acre of earth disturbance" that must comply with Chapter 102, the part of a site restoration or reclamation plan identifying PCSM BMPs may satisfy § 102.8. It must meet subsections (b), (c), (e), (f), (h), (i) and (l), and (m) when applicable. Such activities are also excluded from the detailed stormwater analysis in § 102.8(g).
25 Pa. Code § 102.8(n), (g) [35]Show the source text
Except for regulated activities that require site restoration or reclamation, and small earth disturbance activities identified in subsection (n) ... The portion of a site reclamation or restoration plan that identifies PCSM BMPs to manage stormwater from ... Department permitted activities involving less than 1 acre of earth disturbance ... that require compliance with this chapter, may be used to satisfy the requirements of this section if the PCSM, reclamation or restoration plan meets the requirements of subsections (b), (c), (e), (f), (h), (i) and (l) and, when applicable, subsection (m).
Open Pennsylvania Code & Bulletin (opens in a new tab) -
The 2010 preamble explains § 102.8(n): when a site is fully restored or reclaimed, or the permitted activity disturbs less than 1 acre, long-term PCSM operation and maintenance may not be necessary. The long-term O&M obligation is met if the site is restored with no permanent structures or impervious surfaces.
40 Pa.B. 4861 (Aug. 21, 2010), preamble, § 102.8 PCSM requirements (subsection (n)) [48]Show the source text
When a site is fully restored or reclaimed, or the permitted activity involves earth disturbance of less than 1 acre, the obligation of long-term PCSM operation and management may not be necessary. The revisions to the final-form rulemaking were included for this reason. The obligation for long-term operation and maintenance has been met if the site is restored and there are no permanent structures or impervious surfaces.
Open Pennsylvania Bulletin (opens in a new tab) -
Definition"Normal pool elevation", used to measure buffers from ponds, means for a structurally regulated water body the elevation of the spillway, outlet control or dam crest that holds the water at a set height. For water bodies without such structures, it means the height of water at ordinary low-water stages unaffected by drought. It does not apply to wetlands.
25 Pa. Code § 102.1 (definition of "Normal pool elevation") [1]Show the source text
Normal pool elevation— ... (i) For bodies of water which have no structural measures to regulate height of water, the height of water at ordinary stages of low water unaffected by drought. ... (ii) For structurally regulated bodies of water, the elevation of the spillway, outlet control, or dam crest which maintains the body of water at a specified height. ... (iii) The term does not apply to wetlands.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
Farm-pond comment in 2010: a commenter asked whether any permitted project on a property with a farm pond would automatically need buffers built around the pond. DEP answered that the 150-foot riparian forest buffer requirement (establishing a new buffer or protecting an existing one) applies if the waters, "including ponds", are in a designated HQ or EV watershed and fail to attain their designated use at the time of permit application.
Chapter 102 Comment-Response Document (2010 final rulemaking), § 102.14, comment and response 36 [25]Show the source text
it appears to require mandatory buffers for any project that "contains" ponds; does this mean that any permitted project that happens to occur on a property with a farm pond automatically requires buffers to be constructed around the pond? ... Response: The requirement to establish a new riparian forest buffer or protect an existing riparian forest buffer that is 150 feet wide applies if the waters, including ponds, are within a designated HQ or EV watershed and fail to attain their designated use at the time of permit application.
Open PA DEP / Environmental Quality Board (opens in a new tab) -
ProcessDEP's SPEED program, created in July 2024, lets applicants for select permits - including Chapter 102 earth disturbance permits and Chapter 105 dam safety permits - use DEP-approved Qualified Professionals to conduct initial reviews for expedited review; DEP staff still decide whether to approve or deny, and Permit Decision Guarantee and PAyback review timeframes still apply.
DEP, Streamlining Permits for Economic Expansion and Development (SPEED) (web page) [49]Show the source text
The Streamlining Permits for Economic Expansion and Development (SPEED) Program was created in July 2024 ... Applicants for select permits will be able to use DEP-approved Qualified Professionals to conduct initial reviews of applications for expedited review. DEP staff will review recommendations from the Qualified Professional and make the decision to approve or deny the permit ... Earth Disturbance permits (Ch. 102) ... Dam Safety permits (Ch. 105)* ... Permit Decision Guarantee and PAyback review timeframes will still apply to SPEED permits.
Open Pennsylvania Department of Environmental Protection (pa.gov services) (opens in a new tab) -
AgencyDEP may delegate administration and enforcement of Chapter 102 to county conservation districts by written agreement if they have adequate and qualified staff; an acceptable district program requires the concurrence and approval of the county's governing body; and DEP retains projects that cross conservation district boundaries unless it authorizes otherwise.
25 Pa. Code § 102.41(a)-(c) [50]Show the source text
(a) The Department may delegate by written agreement the administration and enforcement of this chapter to conservation districts if they have adequate and qualified staff ... (b) An acceptable program shall have the concurrence and approval of the governing body of the county in which the conservation district operates. ... (c) The Department will retain program administration and enforcement over projects which cross the political boundaries of conservation districts unless otherwise authorized by the Department.
Open Pennsylvania Code & Bulletin (opens in a new tab) -
StatusFee rulemaking status: in its three-year Chapter 102 fee report to the EQB (July 14, 2026 meeting), DEP said it plans to evaluate increasing Chapter 102 permit fees. Depending on that evaluation, DEP "may draft a proposed rulemaking".
DEP, 3-Year Regulatory Fee and Program Cost Analysis Report to the EQB - Chapter 102 Erosion and Sediment Control Permit Fees (EQB meeting materials, July 14, 2026), Recommendations [37]Show the source text
Based on the analysis in this report, DEP plans to evaluate the potential for increasing Chapter 102 permit fees. Depending on this evaluation, DEP may draft a proposed rulemaking to address the disparity between program costs and sustainable funding sources including fee revenues.
Open Pennsylvania Department of Environmental Protection (opens in a new tab)
Open questions to ask the agency
Not confirmed from a primary source
We could not confirm the following from an official source. Ask the agency listed before relying on any of it.
- Whether building a farm, livestock-watering, irrigation or NRCS-designed (Pond 378) pond on an agricultural operation counts as exempt agricultural activity or as construction that needs NPDES coverage at 1 acre or more. No Chapter 102 text, DEP guidance or district page located classifies ponds. — ask: DEP Bureau of Clean Water, Chapter 102 program (RA-EPChapter102@pa.gov), and the county conservation district
- Whether pond construction included in an Agricultural E&S Plan, NRCS conservation plan or district-approved plan can be treated as a water-quality BMP for plowing, tilling or animal heavy use areas and so be exempt from permit coverage. — ask: DEP Bureau of Clean Water; county conservation district; NRCS Pennsylvania field office
- Whether a Chapter 105 dam permit, water obstruction and encroachment permit, or general permit registration for a pond counts as a permit that includes Chapter 92 and 102 requirements under § 102.5(g), so that no separate NPDES coverage is needed. The guidance list of qualifying permits that DEP said in 2010 could be provided was not located. — ask: DEP Bureau of Clean Water and the DEP regional Waterways & Wetlands Program or Division of Dam Safety
- How § 102.5(i) applies to a pond that needs a state Chapter 105 authorization but no federal section 404 permit, and whether a Chapter 105 general permit registration counts as coverage under a section 404 permit. — ask: DEP Bureau of Clean Water; DEP regional Waterways & Wetlands Program; the U.S. Army Corps of Engineers district (Baltimore, Philadelphia or Pittsburgh)
- Whether a Chapter 105-authorized pond disturbing less than 1 acre must prepare a § 102.8 PCSM Plan, and whether the § 102.8(n) restoration-plan route is accepted for ponds, whose embankments and spillways are permanent structures. — ask: DEP Bureau of Clean Water; DEP regional Waterways & Wetlands Program; county conservation district
- Final terms and effective date of the reissued 2027 PAG-01, including whether the current bar on sediment basins and most sediment traps is kept. — ask: DEP Bureau of Clean Water, NPDES Permitting Division (717-787-2137)
- DEP's review time commitment for PAG-01 NOIs, and review timeframes for Chapter 102 submissions handled by conservation districts. — ask: DEP Bureau of Clean Water; county conservation district
- How DEP currently applies the codified mandatory buffer text of § 102.14(a) alongside the Act 162 equivalency alternative; DEP's 2014-2015 Act 162 implementation, equivalency and offsetting guidance was not reviewed. — ask: DEP Bureau of Clean Water (RA-EPChapter102@pa.gov)
- County conservation district review fees for E&S plans, PAG-01/PAG-02 NOIs and individual permits (set by each district), and which Chapter 102 functions (for example full plan or PCSM reviews) a given district handles. — ask: The county conservation district where the pond is located; DEP Bureau of Watershed Restoration and Nonpoint Source Management
- Municipal or county stormwater and E&S ordinance requirements for pond projects under 1 acre. — ask: The municipality and the county conservation district
Sources
Every statement above links to one of these official sources. Expand “Show the source text” under any statement to read the exact passage it rests on.
- 25 Pa. Code § 102.1. Definitions (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 102.2. Scope and purpose (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 102.4. Erosion and sediment control requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 102.5. Permit requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- Introduction to Ponds and Chapter 105 (opens in a new tab) — Pennsylvania Department of Environmental Protection, retrieved September 28, 2026
- Erosion and Sediment Control Frequently Asked Questions (FAQ), Version 1.8 (opens in a new tab) — Pennsylvania Department of Environmental Protection, Bureau of Clean Water, document date Revised 2026-08-12, retrieved September 28, 2026
- The Clean Streams Law, Act of June 22, 1937, P.L. 1987, No. 394 (35 P.S. § 691.1 et seq.) (opens in a new tab) — Pennsylvania General Assembly, document date section 402(c) added Oct. 22, 2014 (Act 162), retrieved September 28, 2026
- 25 Pa. Code § 102.32. Compliance and enforcement provisions (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- Act 162 (DEP program page) (opens in a new tab) — Pennsylvania Department of Environmental Protection, retrieved September 28, 2026
- 25 Pa. Code § 102.14 Riparian buffer requirements - used in notes for currency (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date current through 56 Pa.B. 4026 (July 4, 2026), retrieved September 28, 2026
- 25 Pa. Code § 105.13 (Regulated activities—information and fees) (opens in a new tab) — Pennsylvania Code & Bulletin, document date last amended eff. Feb. 16, 2013 (43 Pa.B. 967), retrieved September 28, 2026
- Individual NPDES Permit for Discharges of Stormwater Associated with Construction Activities - Application Instructions (3800-PM-BCW0408a Rev. 7/2026) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 7/2026, retrieved September 28, 2026
- Ag Erosion & Sediment Control (York County Conservation District) (opens in a new tab) — York County Conservation District, retrieved September 28, 2026
- Building Ponds (Clinton County Conservation District) (opens in a new tab) — Clinton County, PA (Conservation District), retrieved September 28, 2026
- Chester County Conservation District - Frequently Asked Questions (opens in a new tab) — Chester County, PA (Conservation District), retrieved September 28, 2026
- PAG-01 NOI Instructions (3800-PM-BCW0404a) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 3/2025, retrieved September 28, 2026
- PAG-02 NOI Instructions (3800-PM-BCW0405a Rev. 3/2026) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 3/2026, retrieved September 29, 2026
- Availability of NPDES General Permit for Discharges of Stormwater Associated with Construction Activities (PAG-02), 54 Pa.B. 5536 (opens in a new tab) — Pennsylvania Bulletin / DEP, document date 2024-08-31, retrieved September 28, 2026
- PAG-02 General Permit Fact Sheet (3800-PM-BCW0405g Rev. 8/2024) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 8/2024, retrieved September 28, 2026
- Common Plan of Development or Sale FAQ (NPDES Permits for Stormwater Associated with Construction Activities), Version 1.5 (opens in a new tab) — Pennsylvania Department of Environmental Protection, Bureau of Clean Water, document date Revised 2026-09-23 (page footers read Nov. 14, 2025), retrieved September 28, 2026
- Availability of NPDES General Permit for Discharges of Stormwater Associated with Small Construction Activities (PAG-01), 51 Pa.B. 7128 (opens in a new tab) — Pennsylvania Bulletin / DEP, document date 2021-11-13, retrieved September 28, 2026
- Soil Erosion and Sediment Control Manual for Agricultural Operations (383-4200-002) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date effective 2019-10-05, retrieved September 28, 2026
- NRCS Pennsylvania Conservation Practice Standard, Pond (Code 378) (opens in a new tab) — USDA NRCS Pennsylvania (eFOTG), document date October 2023, retrieved September 28, 2026
- Instructions for Completing Dam Permit Application, 3140-PM-BWEW0001 Rev. 6/2018 (opens in a new tab) — Pennsylvania DEP, Bureau of Waterways Engineering and Wetlands, document date Rev. 6/2018, retrieved September 28, 2026
- Chapter 102. Erosion and Sediment Control and Stormwater Management - Comment-Response Document (2010 final rulemaking) (opens in a new tab) — PA DEP / Environmental Quality Board, document date Undated in document; accompanies the 2010 final-form rulemaking (40 Pa.B. 4861), retrieved September 28, 2026
- Construction Stormwater (DEP program page) (opens in a new tab) — Pennsylvania Department of Environmental Protection, retrieved September 28, 2026
- 25 Pa. Code § 102.6. Permit applications and fees (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- PAG-01 General Permit Fact Sheet (3800-PM-BCW0404e Rev. 4/2025) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 4/2025, retrieved September 28, 2026
- Draft NPDES General Permit for Stormwater Discharges from Small Construction Activities (PAG-01), 56 Pa.B. 5629, Doc. No. 26-1207 (opens in a new tab) — Pennsylvania Bulletin (DEP notice), document date Published Aug. 22, 2026 (DRAFT; comments through Sept. 21, 2026), retrieved September 28, 2026
- Draft PAG-01 General Permit for Stormwater Discharges Associated with Small Construction Activities - presentation to the Water Resources Advisory Committee (opens in a new tab) — PA DEP Bureau of Clean Water, document date Sept. 9, 2026, retrieved September 28, 2026
- PAG-02 General Permit - SAMPLE (3800-PM-BCW0405d Rev. 1/2026) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 1/2026, retrieved September 28, 2026
- Erosion and Sediment Pollution Control Program Manual, Technical Guidance No. 386-2134-001 (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date effective 2012-03-31, retrieved September 28, 2026
- 25 Pa. Code § 102.11. General requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 102.22. Site stabilization (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 102.8. PCSM requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date adopted eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 92a.62. Annual fees (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Aug. 28, 2021 (51 Pa.B. 5361), retrieved September 28, 2026
- 3-Year Regulatory Fee and Program Cost Analysis Report to the EQB: Chapter 102 Erosion and Sediment Control Permit Fees (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date presented to EQB 2026-07-14, retrieved September 28, 2026
- Pennsylvania Bulletin, Vol. 56, No. 39 (Sept. 26, 2026), full issue — List of Pa. Code Chapters Affected (opens in a new tab) — Pennsylvania Bulletin (pacodeandbulletin.gov), document date 2026-09-26, retrieved September 28, 2026
- DEP Regulatory Update (Environmental Quality Board regulations status), September 28, 2026 (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date 2026-09-28, retrieved September 29, 2026
- SOP BCW-102-002: Review of PAG-02 General NPDES Permit NOIs, Version 1.6 (opens in a new tab) — Pennsylvania Department of Environmental Protection, Bureau of Clean Water, document date Revised 2025-06-11, retrieved September 28, 2026
- SOP BCW-102-003: Review of Individual NPDES Permit Applications (Construction Stormwater), Version 1.9 (opens in a new tab) — Pennsylvania Department of Environmental Protection, Bureau of Clean Water, document date Revised 2026-02-02, retrieved September 28, 2026
- 25 Pa. Code § 102.43. Withholding permits (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code § 102.7. Permit termination (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- 25 Pa. Code Chapter 102. Erosion and Sediment Control (table of contents, authority note) (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date Code current through 56 Pa.B. 4026 (July 4, 2026), retrieved September 28, 2026
- 25 Pa. Code § 102.42. Notification of application for permits (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
- The Pennsylvanian's Guide to Permitting for Watershed Improvement Projects (3300-BK-DEP5328) (opens in a new tab) — PA DEP, document date December 2020 (publication no. dated 10/2023), retrieved September 28, 2026
- 25 Pa. Code § 105.46. Implementation of erosion and sedimentation control plans (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Jan. 8, 2011 (41 Pa.B. 219), retrieved September 28, 2026
- Environmental Quality Board, Erosion and Sediment Control and Stormwater Management, final-form rulemaking (25 Pa. Code Ch. 102), 40 Pa.B. 4861, Doc. No. 10-1573 (opens in a new tab) — Pennsylvania Bulletin, document date Published Aug. 21, 2010; effective Nov. 19, 2010, retrieved September 28, 2026
- Streamlining Permits for Economic Expansion and Development (SPEED) (opens in a new tab) — Pennsylvania Department of Environmental Protection (pa.gov services), retrieved September 28, 2026
- 25 Pa. Code § 102.41. Administration by conservation districts (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
This is not legal advice. It is a plain-English summary of official sources, checked September 28, 2026. Laws, permits and agency practice change, and how they apply depends on your exact site. Confirm with the agencies named here, and with a licensed professional engineer for any dam, before you build.
Planning a pond?
Talk it through with a Natural Waterscapes pond expert before you break ground. We can help you size the project so it fits the permits you can realistically get.