Three Pennsylvania sources tie the Fish and Boat Commission's drawdown permit to fish: the Fish and Boat Code bars drawing off dam waters inhabited by fish without first applying for the Commission's written permission; the Commission's regulations require a Commission permit to draw down impounded waters inhabited by fish; and DEP's Chapter 105 rules say such waters may not be drawn down without the Commission's written approval. The Commission's own web pages state the trigger differently: a drawdown permit is required for water bodies with a surface area greater than one acre, and for water bodies of any size that need another state permit (see Conflicts). [1][2][3][4][5]

A Commission regulation (58 Pa. Code § 51.89) serves as a general permit, so no individual application is needed, when both of these are true: the water area drawn down is 1 acre or less, and the drawdown is of a type that does not require other State permits, such as erosion and sedimentation control permits and Dams and Waterways Management permits. Where an individual drawdown permit is needed, the permit has no fee, and the application is reviewed by both the Commission and DEP and must be submitted at least 30 days before the drawdown. [4][6][7]

For sealing or lining, DEP's Chapter 105 rules define "fill" to include material used to change the bottom elevation of a regulated water. Chapter 105 waives its permit requirement for maintaining an artificial pond to its original storage capacity where the contributory drainage area is 100 acres or less, the greatest water depth at maximum storage elevation is 15 feet or less and the impounding capacity at that elevation is 50 acre-feet or less (25 Pa. Code § 105.12(a)(14)). DEP's pond guidance for artificial ponds with non-jurisdictional dams reads that waiver as covering maintenance limited to the original storage capacity in which only accumulated sediment is removed. That guidance says any activity that changes a pond's cross-section and does not qualify as maintenance needs a Water Obstruction and Encroachment Permit from the appropriate DEP regional office. None of these provisions names sealing or lining; how they apply to a sealing layer on a drained pond bed is listed below as not confirmed. [8][9][10]

For products added to a pond that still holds water, DEP's Chapter 91 rule on algicides, herbicides and fish-control chemicals does not mention sealants or flocculants, and DEP's list of alternative E&S BMPs addresses polyacrylamide (PAM) flocculants for stormwater treatment. Separately, the Fish and Boat Code bars allowing any substance deleterious, destructive or poisonous to fish to run, flow, wash or be emptied into any waters within or bordering on the Commonwealth. [11][12][13]

Whether or not Chapter 105 authorization is needed, DEP's pond guidance says Chapter 102 requires an erosion and sedimentation control plan and E&S best management practices for the pond activities it describes, and 25 Pa. Code § 102.4(b)(1) requires E&S BMPs for earth disturbance activities other than agricultural plowing or tilling or animal heavy use areas, including disturbance of less than 5,000 square feet. DEP also says federal Clean Water Act Section 404 authorization is required for the discharge of fill into waters of the United States, which may include those pond activities. [10][14]

For the water released while draining, Pennsylvania's Clean Streams Law makes it unlawful for any person to put into waters of the Commonwealth (which expressly include ponds), or allow to be discharged into them from property the person owns or occupies, any substance resulting in pollution, and 25 Pa. Code § 93.6 lists substances that produce turbidity or settle to form deposits among those to be controlled. No DEP source was found that applies the Clean Streams Law prohibition specifically to draining a pond, or that says whether draining a pond through a pipe, siphon or pump is a point-source discharge needing NPDES coverage. [15][16][17]

Key points

Official sources disagree

  • Which drawdowns need a Fish and Boat Commission permit. The Fish and Boat Code (30 Pa.C.S. § 3506(a)), the Commission's regulation (58 Pa. Code § 51.81) and DEP's Chapter 105 rule (25 Pa. Code § 105.122) are triggered by dam or impounded waters "inhabited by fish"; § 51.81 has no area threshold of its own, and the 1-acre figure appears in the § 51.89 general permit for drawdowns of 1 acre or less that need no other State permit. The Commission's service page and Pond Management page instead say drawdown permits are required for water bodies with a surface area greater than one acre and for water bodies of any size that need another state permit, without referring to fish; the service page adds that the owner of a pond larger than 1 acre must apply for the joint DEP/Commission permit "because release of larger amounts of water is a regulated activity". The Code defines "fish" to include amphibians, reptiles and aquatic organisms, but no source was found applying that definition to the drawdown trigger. [1][2][3][4][5][6][18]
  • Which DEP office reviews drawdown applications. 58 Pa. Code § 51.84 says applications are reviewed by DEP's Bureau of Dams and Waterways Management; the Commission's application form (PFBC-DD01, updated March 2026) names DEP's Bureau of Waterways Engineering; and the Commission's service page names DEP's Division of Dam Safety. [4][19][20]
  • Requirement30 Pa.C.S. § 3506(a) (Fish and Boat Code): no person may draw off dam waters inhabited by fish without first applying for written permission from the Fish and Boat Commission. No person may obstruct the flow of water through such a dam without allowing a minimum flow, set by the Commission, sufficient at all times to flow in the natural stream on which the dam is located to enable the fish to live. A violation is a summary offense of the first degree. The statute's trigger is "dam waters inhabited by fish", not a surface-area threshold.

    Applies when: Drawing off dam waters inhabited by fish 30 Pa.C.S. § 3506(a) [1]
    Show the source text
    (a) Drawing off or obstructing dams.--No person shall draw off dam waters inhabited by fish without first applying for written permission from the commission, nor shall any person obstruct the flow of water through any such dam without allowing a minimum flow of water determined by the commission to be sufficient at all times to flow in the natural stream on which the dam is located to enable the fish to live. Any person violating the provisions of this subsection commits a summary offense of the first degree.
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • Requirement58 Pa. Code § 51.81: a Commission permit under 30 Pa.C.S. § 3506 is required for (1) drawing down impounded waters inhabited by fish, and (2) destroying, removing, breaching or disturbing a dam, deflector, retard or similar device in waters inhabited by fish. The regulation's trigger is "impounded waters inhabited by fish". It has no area threshold of its own (the 1-acre figure appears in the § 51.89 general permit and on PFBC's web pages).

    Applies when: Drawing down impounded waters inhabited by fish 58 Pa. Code § 51.81 [2]
    Show the source text
    A permit from the Commission is required under section 3506 of the code (relating to drawing off or interference with dams or devices) for the following activities: (1) Drawing down impounded waters inhabited by fish. (2) Destruction, removal, breach or disturbance of a dam, deflector, retard or similar device in waters inhabited by fish.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • RequirementChapter 105 bars drawing down impounded waters inhabited by fish except with the written approval of the Fish and Boat Commission under 30 Pa.C.S. § 3506.

    Applies when: Draining a fish-inhabited pond, for example to dry and seal the bed 25 Pa. Code § 105.122 [3]
    Show the source text
    Impounded waters which are inhabited by fish may not be drawn down except with the written approval of the Fish and Boat Commission under 30 Pa.C.S. § 3506 (relating to drawing off or interference with dams or devices).
    Open Pennsylvania Code & Bulletin (opens in a new tab)
  • Size cutoffPFBC's service page describes the drawdown permit (formally, Permit to Draw Off Water From Impoundments) as regulating the release of water from dams, ponds or impoundments "in certain situations". It is jointly reviewed by DEP's Division of Dam Safety and by PFBC, which reviews environmental and recreational impacts. There is no fee. The page says drawdown permits are required for water bodies with a surface area greater than one acre, and for water bodies of any size that need another state permit. The application must be submitted at least 30 days before the drawdown. The page's stated triggers do not refer to whether the water body holds fish.

    Applies when: Drawing down a pond, dam or impoundment PFBC, "Apply to Draw Off Water from Impoundments" (pa.gov), About the Permit [4]
    Show the source text
    regulates release of water from dams, ponds or impoundments in certain situations. ... jointly reviewed by the Department of Environmental Protection - Division of Dam Safety ... and the Fish and Boat Commission, which reviews environmental and recreational impacts ... The permit has no fee associated with it. Draw down permits are required for: Water bodies with a surface area that is greater than one acre; and Water bodies of any size that require another state permit ... A draw down permit application is to be submitted at least 30 days before a draw down event is to occur.
    Open Pennsylvania Fish and Boat Commission (pa.gov) (opens in a new tab)
  • Exemption58 Pa. Code § 51.89(a) is itself a general permit, so no individual application is needed, to draw down impounded waters when both of these are true: (1) the water area to be drawn down is 1 acre or less, and (2) the drawdown is of a type that does not require other State permits, such as erosion and sedimentation control permits and Dams and Waterways Management permits.

    Applies when: Drawdowns of 1 acre or less that need no other State permit 58 Pa. Code § 51.89(a) [6]
    Show the source text
    (a) Notwithstanding the other provisions of this subchapter, this section constitutes a general permit for persons to draw down impounded waters without applying for an individual permit when the following circumstances exist: (1) The water area to be drawn down is 1 acre or less. (2) The draw down operations are of a type that do not require other State permits, such as erosion and sedimentation control permits and Dams and Waterways Management permits.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • DefinitionChapter 105 definitions relevant to sealing a pond: a 'body of water' includes a natural or artificial pond; an 'encroachment' is a structure or activity that changes, expands or diminishes the course, current or cross section of a watercourse, floodway or body of water; and 'fill' is sand, gravel, earth or other material placed or deposited to form an embankment or raise the elevation of the land surface, including material used to replace an area with aquatic life with dry land or to change the bottom elevation of a regulated water of the Commonwealth.

    Applies when: Deciding whether placing material on a pond bottom is regulated under Chapter 105 25 Pa. Code § 105.1 (definitions of "Body of water", "Encroachment", "Fill") [8]
    Show the source text
    Body of water—A natural or artificial lake, pond, reservoir, swamp, marsh or wetland. ... Encroachment—A structure or activity which changes, expands or diminishes the course, current or cross section of a watercourse, floodway or body of water. ... Fill—Sand, gravel, earth or other material placed or deposited to form an embankment or raise the elevation of the land surface. The term includes material used to replace an area with aquatic life with dry land or to change the bottom elevation of a regulated water of this Commonwealth.
    Open Pennsylvania Code & Bulletin (opens in a new tab)
  • ExemptionDEP's pond guidance reads the § 105.12(a)(14) waiver as covering maintenance of the reservoir area limited to the original storage capacity where only accumulated sediment is removed, and says DEP's rules do not regulate repair and maintenance of non-jurisdictional dams. It adds that any activity that changes the cross-section of a pond and does not qualify as maintenance requires a Water Obstruction and Encroachment Permit from the appropriate DEP regional office.

    Applies when: Maintenance work in an artificial pond with a non-jurisdictional dam DEP, "Introduction to Ponds and Chapter 105" (pa.gov), Common Pond Maintenance Activities and Permit Requirements - Artificial Ponds with Non-Jurisdictional Dams [10]
    Show the source text
    Section 105.12(a)(14) of the Department’s Rules and Regulations provides for waiver of Water Obstruction and Encroachment Permit requirements for the maintenance of the reservoir area if this maintenance is limited to the impoundment’s original storage capacity and only accumulated sediment is removed. ... do not regulate the repair and maintenance of non-jurisdictional dams ... Note: Any activity which changes the cross-section of a pond and does not qualify as maintenance requires a Water Obstruction and Encroachment Permit from the appropriate DEP Regional Office.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementDEP's Chapter 91 rule authorizes the use of an algicide, herbicide or fish control chemical only (1) as copper sulfate to control algae in a public water supply source with DEP approval, or (2) for chemicals required to control aquatic plants in surface waters or to manage fish populations, under joint approval of DEP and the Fish and Boat Commission. Its text is limited to those purposes and does not mention sealants or flocculants.

    Applies when: Use of an algicide, herbicide or fish-control chemical in surface waters; cited here to show the rule's scope does not reach sealants 25 Pa. Code § 91.38 [11]
    Show the source text
    Except when the use of an algicide, herbicide or fish control chemical would be in violation of a specific order or permit, the use is authorized only in the following instances: (1) Copper sulfate required to control algae in a source of public water supply when the use is under and in accordance with approval given by the Department. (2) Chemicals required to control aquatic plants in surface waters and chemicals required for the management of fish populations where the use is under and in accordance with joint approval given by the Department and the Fish and Boat Commission.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • RequirementThe Fish and Boat Code bars anyone, regardless of intent, from putting any electricity, explosives or poisonous substances into waters within or on the boundaries of the Commonwealth (except that, for research and fish management, agents of or persons authorized by PFBC's executive director may use any method to collect, eradicate or control fish), or allowing any substance deleterious, destructive or poisonous to fish to run, flow, wash or be emptied into any waters within or bordering on the Commonwealth. In a criminal prosecution for water pollution known to be injurious to fish, proof that the violation actually caused the death of, or damage to, any particular fish is not needed; a violation is a third-degree misdemeanor, and the section does not repeal or supersede the Clean Streams Law.

    Applies when: Any product added to a pond or reaching a stream, including sealants or flocculants 30 Pa.C.S. § 2504(a)-(d) [13]
    Show the source text
    any electricity, explosives or any poisonous substances except that, for the purposes of research and fish management, agents of or persons authorized by the executive director may use any method or means to collect, eradicate or control fish. (2) Allow any substance, deleterious, destructive or poisonous to fish, to be turned into or allowed to run, flow, wash or be emptied into any waters ... it is not necessary to prove that the violation has actually caused the death of, or damage to, any particular fish. ... does not repeal or supersede ... misdemeanor of the third degree.
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • RequirementDEP's pond guidance notes that, whether or not a pond activity needs Chapter 105 authorization, developing an erosion and sedimentation control plan and implementing and maintaining E&S best management practices is required under Chapter 102. It also says federal Clean Water Act Section 404 authorization is required for the discharge of fill into waters of the United States, which may include the pond activities it describes.

    Applies when: Earth disturbance in or around a pond, including draining, grading and mixing a liner DEP, "Introduction to Ponds and Chapter 105" (pa.gov), Frequently Asked Questions (Note) and FAQ on federal authorization [10]
    Show the source text
    Note: While the activities described below may or may not require Chapter 105 authorization, the development of an erosion and sedimentation control plan and the implementation and maintenance of erosion and sedimentation control Best Management Practices is required under Chapter 102. ... Answer: Federal authorization under Section 404 of the Clean Water Act is required for the discharge of fill into Waters of the US. This may include any of the activities discussed above.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • Requirement25 Pa. Code § 102.4(b)(1): for earth disturbance activities other than agricultural plowing or tilling or animal heavy use areas, E&S BMPs must be implemented and maintained to minimize the potential for accelerated erosion and sedimentation, including for activities that disturb less than 5,000 square feet. What counts as an earth disturbance activity is defined in 25 Pa. Code § 102.1 (next claim).

    Applies when: Earth disturbance of any size (e.g., excavating a pond or dredging a drained pond bed) 25 Pa. Code § 102.4(b)(1) [14]
    Show the source text
    (b) For earth disturbance activities other than agricultural plowing or tilling or animal heavy use areas, the following erosion and sediment control requirements apply: (1) The implementation and maintenance of E&S BMPs are required to minimize the potential for accelerated erosion and sedimentation, including those activities which disturb less than 5,000 square feet (464.5 square meters).
    Open Pennsylvania Code & Bulletin (opens in a new tab)
  • RequirementClean Streams Law § 401: it is unlawful for any person to put into waters of the Commonwealth, or allow or permit to be discharged into them from property the person owns or occupies, any substance of any kind resulting in pollution, and any such discharge is declared a nuisance. The section contains no size threshold. No DEP source was found that applies it specifically to draining a pond.

    Applies when: Any discharge from private property to waters of the Commonwealth Clean Streams Law § 401, 35 P.S. § 691.401 [15]
    Show the source text
    Section 401. Prohibition Against Other Pollutions.--It shall be unlawful for any person or municipality to put or place into any of the waters of the Commonwealth, or allow or permit to be discharged from property owned or occupied by such person or municipality into any of the waters of the Commonwealth, any substance of any kind or character resulting in pollution as herein defined. Any such discharge is hereby declared to be a nuisance.
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • Requirement25 Pa. Code § 92a.1(b): a person may not discharge pollutants from a point source into surface waters except as authorized under an NPDES permit. No DEP regulation or guidance was found that says whether draining a pond through a pipe, siphon or pump is a point-source discharge of pollutants that needs NPDES coverage.

    Applies when: Point-source discharges of pollutants to surface waters 25 Pa. Code § 92a.1(b) [17]
    Show the source text
    (b) Scope. A person may not discharge pollutants from a point source into surface waters except as authorized under an NPDES permit.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)

Drawing down or draining: the Fish and Boat Commission permit and DEP's role

The Fish and Boat Code's definitions, which apply throughout Title 30 unless the context clearly indicates otherwise, say "fish" includes game fish, fish bait, bait fish, amphibians, reptiles and aquatic organisms; no source was found applying that definition to the drawdown trigger. Section 102 of the Code does not define "dam", "dam waters" or "impounded waters". [18]

The Commission's application (PFBC-DD01, updated March 2026) asks whether the impoundment contains fish or other aquatic organisms, the proposed dates, the impoundment area, maximum depth, depth of drawdown below normal pool and the method (valve, gate, stoplog, siphon, pump or other), and, if fish are to be transferred, the destination water and transfer method. The form contains no drawdown-rate limit, sediment-control requirement, seasonal restriction or fish-salvage requirement. [20]

A DEP Supplement must be completed when the drawdown's purpose includes any of the form's items 1-7: dam or spillway repairs; dam, spillway or outfall structure repair or modification; dredging; pond elimination and backfill; bulkheads, retaining walls or other shoreline structures; beach renovation; or dock construction or maintenance. None of items 1-7 names pond sealing or lining; the form's "Other (explain)" choice is item 10, in a separate group (items 8-10) outside the items that trigger the Supplement. The form says many drawdown-related activities need separate DEP and/or U.S. Army Corps of Engineers approvals before they begin, and for dredging the Supplement asks for color photos, a dredging plan and a disposal plan. [20]

A drawdown permit does not waive other State, local or Federal permits. The permittee is solely responsible for the consequences of the drawdown, must ensure compliance with laws and regulations governing downstream flooding, must acquire any property rights, flowage easements or other interests needed, and must allow at all times, including while refilling, a Commission-determined minimum flow in the natural stream on which the impoundment is located. Unless the purpose is to remove or eliminate the impoundment, the permittee must refill it when the permit expires or the work is completed, whichever comes first. [21][22][23]

The permit lets the permittee take, catch, kill or possess fish from the drawn-down water regardless of seasons, sizes, creel limits or manner of taking; disposal of fish and aquatic life must follow applicable State and local laws and regulations, and salvaged fish may not be stocked into waters without the owners' permission or into waters the Commission designates as inappropriate for salvaged fish. The regulation does not require a fish salvage. [24]

Under 58 Pa. Code § 51.84, applications are reviewed by the Commission's Division of Environmental Services and by DEP, and the Division of Environmental Services issues the permits. For jurisdictional dams, Chapter 105 says that under normal conditions reservoirs impounded by earthfill dams should not be drawn down faster than 1 foot per day without DEP's prior approval. It also says that, for the owner or permittee of a dam or reservoir, routine maintenance of the dam and the reservoir's design storage capacity needs no further Chapter 105 authorization except as provided in its rule on drawing down impounded waters inhabited by fish. [3][19][25][26]

In a 2025 Environmental Hearing Board appeal of the High Point Lake drawdown permit, DEP took the position that its own permission is needed only where a drawdown will exceed one foot per day; the Board, in denying DEP's motion to dismiss, noted that DEP's regulations say routine maintenance, including drawdown of water in an impoundment, does not require DEP approval, but said it was not clear that a long-term, full drainage of an impoundment used as a lake is routine maintenance. The permit in that case, signed by DEP's Chief of the Division of Dam Safety on August 13, 2025, required the permittee to follow DEP's best management practices for "Minimizing Sediment Pollution to Downstream Channels During Impoundment Dewatering"; the opinion does not describe what those practices contain. [27]

The Commission's advisory guidance notes that a drawdown can dry out and partly control plants in the dewatered area and is particularly effective with freezing weather, but that exposing the mud after turtles, frogs and salamanders begin hibernating in it will likely kill them. [4]

  • DefinitionFish and Boat Code definitions (30 Pa.C.S. § 102), which apply throughout Title 30 unless the context clearly indicates otherwise: "fish" as a noun includes all game fish, fish bait, bait fish, amphibians, reptiles and aquatic organisms, which is broader than the everyday meaning of fish; no source was found applying this definition to the § 3506 drawdown trigger. "Inland waters" includes any nontidal stream, river, lake, or artificial or natural body of water in the Commonwealth. Section 102 defines neither "dam", "dam waters" nor "impounded waters".

    Applies when: Interpreting 30 Pa.C.S. § 3506 and 58 Pa. Code §§ 51.81-51.89 30 Pa.C.S. § 102 ("Fish"; "Inland waters") [18]
    Show the source text
    the following words and phrases when used in this title shall have, unless the context clearly indicates otherwise, the meanings given to them in this section: ... "Fish." (1) When used as a noun, includes all game fish, fish bait, bait fish, amphibians, reptiles and aquatic organisms. ... "Inland waters." Any nontidal stream, river, lake, artificial or natural body of water within this Commonwealth.
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • ProcessPFBC's drawdown application (PFBC-DD01, updated March 2026) is reviewed jointly by PFBC and DEP's Bureau of Waterways Engineering. The form asks whether the impoundment contains fish or other aquatic organisms, the proposed dates, the impoundment area (acres), maximum depth, depth of drawdown below normal pool, and method (valve, gate, stoplog, siphon, pump or other). If fish are to be transferred, it asks for the destination water and transfer method. The form contains no drawdown-rate limit, sediment-control requirement, seasonal restriction or fish-salvage requirement.

    Applies when: Applying for a PFBC/DEP drawdown permit PFBC-DD01, Application to Draw Off Water from Impoundments (updated March 2026), header and Sections B-C [20]
    Show the source text
    This application will be reviewed jointly by the Pennsylvania Fish and Boat Commission (PFBC) and the Department of Environmental Protection (DEP) Bureau of Waterways Engineering ... Does the impoundment contain fish or other aquatic organisms? ☐ Yes ☐ No C. DRAW DOWN INFORMATION Proposed Dates From: To: Impoundment Area (acres): Maximum Depth (feet): Depth of draw down (feet below normal pool): Method: ☐ Valve ☐ Gate ☐ Stoplog ☐ Siphon ☐ Pump ☐ Other: If fish are to be transferred, provide the destination water: and transfer method:
    Open Pennsylvania Fish and Boat Commission (opens in a new tab)
  • ProcessPFBC-DD01 Section E (DEP Supplement) must be completed when the drawdown purpose includes any of items 1-7, the construction, maintenance or elimination purposes listed in Section D (such as dredging, and pond elimination and backfill). It states that many activities related to reservoir drawdowns need separate DEP and/or U.S. Army Corps of Engineers approvals before work begins, and DEP uses the supplement to decide on additional permitting. For dredging or disposal of accumulated sediment it asks for color photos, a dredging plan and a disposal plan. For pond elimination and backfill it asks for a site plan with dimensions of the dam and pond, and the drainage area.

    Applies when: Drawdowns for construction, maintenance, dredging or pond elimination PFBC-DD01 (updated March 2026), Sections D-E [20]
    Show the source text
    Construction, maintenance or elimination - *Complete Section E. DEP Supplement if project purpose includes any of items 1 through 7. ... Many activities related to reservoir draw downs require separate DEP and/or U.S. Army Corps of Engineers approval(s) prior to beginning the activity(s). The information ... will be used by DEP to determine any additional permitting requirements. ... Dredging/Disposal of Accumulated Sediment ... Color photos ... Dredging plan ... Disposal plan ... Pond Elimination and Backfill Site plan & dimensions of dam & pond ... Drainage area
    Open Pennsylvania Fish and Boat Commission (opens in a new tab)
  • Process58 Pa. Code § 51.83: issuing a drawdown permit does not waive the need for other State, local or Federal permits for the proposed activity.

    Applies when: PFBC drawdown permits 58 Pa. Code § 51.83 [21]
    Show the source text
    The issuance of a draw down permit under section 3506 of the code (relating to drawing off or interference with dams or devices) does not constitute a waiver of the requirement for applicants to obtain other State, local or Federal permits for the proposed activity.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • Requirement58 Pa. Code § 51.86: a drawdown permittee is solely responsible for the consequences of drawing down the impounded waters. The permittee must ensure compliance with laws and regulations on downstream flooding and must acquire any property rights, flowage easements or other interests needed for the drawdown. It must also allow at all times a minimum flow, determined by the Commission, in the natural stream on which the impoundment is located, to protect and conserve fish downstream. Neither this section nor the rest of Subchapter I (§§ 51.81-51.89) sets a numeric drawdown rate or a sediment standard.

    Applies when: Holders of PFBC drawdown permits 58 Pa. Code § 51.86 [22]
    Show the source text
    A permittee is solely responsible for the consequences of drawing down the impounded waters. A permittee is responsible to ensure compliance with laws and regulations governing downstream flooding. A permittee is responsible for acquiring property rights, flowage easements or other interests required to accomplish the draw down. A permittee is responsible to allow a minimum flow of water determined by the Commission to be sufficient at all times to flow in a natural stream on which the impoundment is located to provide for the protection and conservation of fish downstream from the site.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • Requirement58 Pa. Code § 51.87: unless the purpose of the permitted drawdown is to remove or eliminate the impoundment, the permittee must refill it when the permit expires or the work is completed, whichever comes first. While refilling, the permittee must keep the Commission-determined minimum flow in the natural stream to protect fish downstream.

    Applies when: Holders of PFBC drawdown permits (other than pond elimination) 58 Pa. Code § 51.87 [23]
    Show the source text
    Except when the purpose of the permitted draw down is to remove or eliminate the impoundment, the permittee shall refill the impoundment when the permit expires or the work is completed, whichever occurs first. In refilling the impoundment, the permittee is responsible to allow a minimum flow of water determined by the Commission to be sufficient at all times to flow in a natural stream on which the impoundment is located to provide for the protection and conservation of fish downstream from the site.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • Requirement58 Pa. Code § 51.85 (fish handling under a drawdown permit): the permit authorizes the permittee to take, catch, kill or possess fish from the drawn-down waters regardless of seasons, sizes, creel limits or manner of taking. Fish and aquatic life must be disposed of under applicable State and local law. Salvaged fish may not be stocked into waters without the owners' permission, or into any waters the Commission designates as inappropriate for salvaged fish. The regulation does not require a fish salvage.

    Applies when: Holders of PFBC drawdown permits 58 Pa. Code § 51.85(a)-(c) [24]
    Show the source text
    authorizes the permittee to take, catch, kill or possess fish taken from the drawn down waters regardless of seasons, sizes and creel limits or manner of taking. ... Disposal of fish and aquatic life shall be done in conformance with applicable State and local laws and regulations. ... It is unlawful to stock fish salvaged as a result of draw down operations in waters without the permission of the owners ... It is unlawful to stock fish salvaged as a result of draw down operations in any waters of this Commonwealth designated by the Commission as inappropriate for stocking of salvaged fish.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • Agency58 Pa. Code § 51.84: drawdown permit applications are reviewed by the Commission's Division of Environmental Services and by DEP's Bureau of Dams and Waterways Management, and the Division of Environmental Services issues the permits for the Commission. (The March 2026 PFBC-DD01 form names DEP's Bureau of Waterways Engineering, and PFBC's service page names DEP's Division of Dam Safety, as the DEP reviewer; the regulation names a different DEP bureau.)

    Applies when: PFBC drawdown permits 58 Pa. Code § 51.84 [19]
    Show the source text
    A permit application will be reviewed by the Commission’s Division of Environmental Services and by the Department of Environmental Protection, Bureau of Dams and Waterways Management. The Division of Environmental Services will issue permits for the Commission.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • RequirementFor the owner or permittee of a dam or reservoir, routine maintenance of the dam and of the reservoir's design storage capacity does not require further Chapter 105 authorization, except as provided in § 105.122 (drawdown of impounded waters). A permittee or owner may not modify the approved operation or monitoring plans without prior DEP approval.

    Applies when: Draining a pond behind a permitted dam (e.g., to dry the bed for sealing) 25 Pa. Code § 105.131(b)-(c) [26]
    Show the source text
    A permittee or owner of a dam or reservoir may not modify or cease implementation of all or part of the approved plans and methods of operation or monitoring without the prior approval of the Department ... The permittee or owner of a dam or reservoir shall operate and maintain the dam in accordance with the authorized plans and specifications. Routine maintenance of the dam and the reservoir’s design storage capacity will not require further authorization under this chapter except as provided in § 105.122 (relating to drawdown of impounded waters).
    Open Pennsylvania Code & Bulletin (opens in a new tab)
  • PFBC's service page gives advisory timing guidance, not permit conditions. A drawdown can dry out and partly control plants in the dewatered area and is particularly effective with freezing weather. If a pond is drawn down after turtles, frogs and salamanders begin hibernating in the mud and the mud is exposed, those animals will likely be killed. If the pond is larger than 1 acre, the owner must apply for the joint DEP/PFBC permit "because release of larger amounts of water is a regulated activity". The page states no drawdown-rate or sediment-control requirement.

    Applies when: Planning the timing of a pond drawdown PFBC, "Apply to Draw Off Water from Impoundments" (pa.gov), Drawdown Considerations [4]
    Show the source text
    This practice, termed "draw down," can dry out and provide partial control of plants in the dewatered area. It is particularly effective when done in association with freezing weather. If you draw a pond down after turtles, frogs and salamanders begin hibernation in the mud and this mud is exposed, chances are that these hibernating creatures will be killed. If your pond is larger than 1 acre, you must apply for a Pennsylvania DEP/Fish and Boat Commission Permit to Draw Off Water From Impoundments because release of larger amounts of water is a regulated activity.
    Open Pennsylvania Fish and Boat Commission (pa.gov) (opens in a new tab)

Handling the water and sediment released while draining

Pennsylvania's NPDES rule says a person may not discharge pollutants from a point source into surface waters, which are defined to include ponds, except as authorized under an NPDES permit; a point source includes any pipe, ditch or channel from which pollutants are or may be discharged. No DEP regulation or guidance was found that says whether draining a pond through a pipe, siphon or pump is such a discharge. [17][28]

If, because of an accident or other activity or incident, a substance that would otherwise result in pollution or create a danger of pollution is discharged into waters of the Commonwealth, 25 Pa. Code § 91.33 requires the person in charge of the substance, or owning or possessing the premises, to immediately notify DEP by telephone and, if reasonably possible, known downstream users, to immediately take the steps needed to prevent injury, and to remove residual substances from the ground and affected waters within 15 days of the incident, to the extent required. The Clean Streams Law also lets DEP, where it finds that an activity not otherwise requiring a permit under that law creates a danger of pollution, or that regulating the activity is necessary to avoid pollution, require a permit for it by rule or regulation, otherwise set the conditions for it, or issue an order regulating it; no DEP rule was found under that authority that specifically requires a permit or sets conditions for draining a pond. [15][29]

On construction projects covered by the PAG-02 general permit (earth disturbance of 1 acre or more, or disturbance within a larger common plan of development or sale of 1 acre or more; effective December 8, 2024, expiring December 7, 2029), discharges from dewatering activities are prohibited unless managed as the permit requires: dewatering water must be infiltrated in upland vegetated areas to the extent feasible, and water that cannot be infiltrated must be treated by an approved series of two or more BMPs before discharge to surface waters, unless the permittee documents that the outflow from a single BMP will reach a turbidity of 50 NTU or less and receives written approval from DEP or the conservation district. PAG-02 defines dewatering as draining accumulated stormwater and/or groundwater from building foundations, vaults, trenches or other similar points of accumulation, and does not say whether pumping out a pond's standing water counts. [30]

The current PAG-01 general permit (earth disturbance of less than 5 acres; effective March 1, 2022, expiring February 28, 2027) says construction dewatering water may not be discharged directly to surface waters and must be infiltrated in upland vegetated areas to the extent feasible, and sets no two-BMP or 50 NTU standard. A draft reissued PAG-01, noticed August 22, 2026 and not yet in effect, proposes treatment by an approved series of at least two E&S BMPs, or one BMP producing outflow turbidity of no more than 50 NTU, where discharges to surface waters are proposed; written comments were accepted through September 21, 2026. [31][32]

DEP's Erosion and Sediment Pollution Control Program Manual (386-2134-001, effective March 31, 2012), which DEP says is guidance and not a regulation, says water pumped from a disturbed area must be treated for sediment removal before discharge to a surface water unless it can be shown to already meet discharge standards, and may not be discharged directly to detention ponds; straw bale and filter fabric structures are not acceptable filters for pumped water. For pumped-water filter bags it specifies a pumping rate no greater than 750 gpm or half the manufacturer's maximum, whichever is less, floating and screened pump intakes, daily inspection, and replacement when a bag is half full of sediment. [33]

As an enforcement example, DEP reported in June 2025 that tons of sediment built up behind Dunmore No. 7 Dam (Lackawanna County) were unexpectedly released into Roaring Brook and the Lackawanna River during dam improvements in February 2024; in lieu of a civil penalty, the owner agreed in a settlement with DEP to perform a Community Environmental Project projected at $350,000. [34]

  • Definition25 Pa. Code § 92a.2 definitions: "surface waters" include lakes, reservoirs and ponds, except water at facilities approved for wastewater treatment. A "point source" is any discernible, confined and discrete conveyance, including any pipe, ditch or channel, from which pollutants are or may be discharged. A "discharge" is an addition of any pollutant to surface waters from a point source.

    25 Pa. Code § 92a.2 ("Discharge", "Point source", "Surface waters") [28]
    Show the source text
    Discharge—An addition of any pollutant to surface waters of this Commonwealth from a point source. ... Point source—A discernible, confined and discrete conveyance, including, but not limited to, any pipe, ditch, channel ... Surface waters—Perennial and intermittent streams, rivers, lakes, reservoirs, ponds, wetlands, springs, natural seeps and estuaries, excluding water at facilities approved for wastewater treatment
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • Requirement25 Pa. Code § 91.33 applies when, because of an accident or other activity or incident, a substance that would otherwise result in pollution or create a danger of pollution is discharged into waters of the Commonwealth. The person in charge of the substance, or owning or possessing the premises, must immediately notify DEP by telephone and, if reasonably possible, notify known downstream users. That person must also immediately take the steps needed to prevent injury, and within 15 days remove the residual substances from the ground and affected waters to the extent required.

    Applies when: Any incident that discharges a polluting substance into waters of the Commonwealth 25 Pa. Code § 91.33(a)-(b) [29]
    Show the source text
    If, because of an accident or other activity or incident ... another substance which ... would otherwise result in pollution or create a danger of pollution of the waters ... is discharged into these waters ... it is the responsibility of the person at the time in charge of the substance or owning or in possession of the premises ... to immediately notify the Department by telephone ... to notify known downstream users of the waters. ... a person shall immediately take or cause to be taken steps necessary to prevent injury ... within 15 days from the incident, shall remove
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • RequirementClean Streams Law § 402(a): where DEP finds that an activity not otherwise requiring a permit under the Act, including the impounding or handling of materials or substances, creates a danger of pollution of waters of the Commonwealth, or that regulating the activity is necessary to avoid such pollution, DEP may by rule or regulation require a permit, may otherwise set the conditions for the activity, or may issue an order to a person regulating that particular activity. No DEP rule was found under this authority that specifically requires a permit or sets conditions for draining a pond.

    Applies when: Activities DEP finds create a danger of pollution Clean Streams Law § 402(a), 35 P.S. § 691.402(a) [15]
    Show the source text
    Whenever the department finds that any activity, not otherwise requiring a permit under this act, including but not limited to the impounding, handling ... of materials or substances, creates a danger of pollution of the waters of the Commonwealth or that regulation of the activity is necessary to avoid such pollution, the department may, by rule or regulation, require that such activity be conducted only pursuant to a permit ... or may otherwise establish the conditions under which such activity shall be conducted, or the department may issue an order ... regulating a particular activity.
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • StatusThe currently effective PAG-02 NPDES General Permit (stormwater from construction activities) took effect December 8, 2024 and expires December 7, 2029. It authorizes stormwater discharges from construction with earth disturbance of 1 acre or more, or disturbance within a larger common plan of development or sale of 1 acre or more. It does not apply to agricultural plowing and tilling, animal heavy use areas, timber harvesting, oil and gas activities, or road maintenance.

    Applies when: Earth disturbance of 1 acre or more (including a larger common plan) PAG-02 General Permit (3800-PM-BCW0405d Rev. 1/2026), pp. 1, 5 [30]
    Show the source text
    the discharge of stormwater associated with construction activities from earth disturbances greater than or equal to one (1) acre, or earth disturbances on any portion, part, or during any stage of, a larger common plan of development or sale that is greater than or equal to one (1) acre. This General Permit does not apply to earth disturbance activities involving agricultural plowing and tilling, animal heavy use areas, timber harvesting activities, oil and gas exploration ... or road maintenance activities. ... Effective: December 8, 2024 ... Expires: December 7, 2029
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementPAG-02 Part A I.B.3 (verbatim substance): discharges from dewatering activities, including dewatering of trenches and excavations, are prohibited unless managed as follows. (a) The permittee must use upland vegetated areas of the site to infiltrate construction dewatering water before discharge, to the extent feasible. (b) Dewatering water that cannot be infiltrated must be treated by an approved series of two or more BMPs before discharge to surface waters to reduce discharges with visual turbidity. The exception is where the permittee documents that the outflow from a single BMP will reach a turbidity of 50 NTU or less and receives written approval from DEP or the conservation district.

    Applies when: Projects covered by PAG-02 (1 acre or more of earth disturbance) that pump construction dewatering water PAG-02 General Permit, Part A § I.B.3(a)-(b) (citing 25 Pa. Code § 102.11(c) and 40 CFR § 450.22(e)) [30]
    Show the source text
    Discharges from dewatering activities, including discharges from dewatering of trenches and excavations, are prohibited ... utilize upland vegetated areas of the project site to infiltrate construction dewatering water prior to discharge, to the extent feasible. ... must be treated by an approved series of two or more BMPs prior to discharge to surface waters to reduce discharges with visual turbidity, unless the permittee can document that the outflow from a single BMP will achieve a turbidity of 50 Nephelometric Turbidity Units (NTUs) or less and receives written approval from DEP/CCD.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • DefinitionPAG-02 defines "dewatering" as draining accumulated stormwater and/or groundwater from building foundations, vaults, trenches, or other similar points of accumulation. The definition does not mention draining an existing pond or lake, and the permit does not say whether pumping out a pond's standing water counts as "dewatering".

    Applies when: PAG-02 projects PAG-02 General Permit, Part A § II (Definitions), "Dewatering" [30]
    Show the source text
    Dewatering means the act of draining accumulated stormwater and/or groundwater from building foundations, vaults, and trenches, or other similar points of accumulation.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementThe currently effective 2022 PAG-01 does contain a dewatering requirement, in Part A I.B.3. Discharges from dewatering activities, including dewatering of trenches and excavations, are prohibited unless managed as follows. (a) Construction dewatering water may not be discharged directly to surface waters, and the permittee must notify DEP or the conservation district if it has reason to believe the water may contain toxic pollutants. (b) An oil-water separator or suitable filtration device is required if the water contains oil, grease or other products. (c) Upland vegetated areas of the site must be used to infiltrate dewatering water before discharge, to the extent feasible. (d) Materials collected by filtration devices must be disposed of off-site unless DEP or the conservation district authorizes otherwise. Unlike PAG-02, the 2022 text sets no two-BMP or 50 NTU treatment standard (the draft reissued PAG-01 would add one; see the next claim).

    Applies when: Projects covered by PAG-01 (less than 5 acres) that pump construction dewatering water PAG-01 General Permit (2022), Part A § I.B.3(a)-(d) [31]
    Show the source text
    Discharges from dewatering activities, including discharges from dewatering of trenches and excavations, are prohibited ... may not be discharged directly to surface waters. The permittee shall notify DEP or CCD if the permittee has reason to believe that dewatering water may contain toxic pollutants. ... oil-water separator ... if dewatering water is found to contain those materials. ... utilize upland vegetated areas of the project site to infiltrate construction dewatering water ... collect and dispose of materials ... off-site unless otherwise authorized by DEP or CCD.
    Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (DEP eLibrary) (opens in a new tab)
  • StatusDRAFT ONLY, not yet in effect: DEP's August 22, 2026 notice of a draft reissued PAG-01 proposes "additional requirements" for construction dewatering water compared with the 2022 permit. Where discharges to surface waters are proposed, dewatering water would have to be treated by an approved series of at least two E&S BMPs, or by one BMP if it produces outflow turbidity of no more than 50 NTU, similar to PAG-02. Written comments were accepted through September 21, 2026.

    Applies when: Future PAG-01 (less than 5 acres) projects, if the draft is finalized DEP notice, 56 Pa.B. 5629 (Aug. 22, 2026) (draft PAG-01) [32]
    Show the source text
    The Department is proposing additional requirements for construction dewatering water. Dewatering water would need to be treated by an approved series of at least two E&S BMPs or one BMP if it would produce an outflow turbidity concentration of no greater than 50 Nephelometric Turbidity Units, where discharges are proposed to surface waters, similar to PAG-02. ... Interested persons are invited to submit written comments regarding the Draft PAG-01 General Permit and associated documents through Monday, September 21, 2026.
    Open Pennsylvania Bulletin (DEP notice) (opens in a new tab)
  • RequirementE&S Manual, "Dewatering Work Areas": wherever water is pumped from a disturbed area, it must be treated for sediment removal before it is discharged to a surface water, unless the water being pumped can be shown to already meet discharge standards. The pump discharge may be routed through a properly functioning sediment basin or sediment trap. Pumped water may not be discharged directly to detention ponds. Straw bale and filter fabric structures are not acceptable filters for pumped water. Sump pits (Standard Construction Detail #3-17) may be used to filter pumped water; the manual also allows pumped water filter bags (Detail #3-16, next claims).

    Applies when: Pumping water from disturbed areas or excavations (E&S Plan guidance) E&S Manual 386-2134-001, ch. 3, "Dewatering Work Areas", p. 53 [33]
    Show the source text
    Wherever water is pumped from a disturbed area, it must be treated for sediment removal prior to discharging to a surface water unless it can be shown that the quality of the water being pumped already meets discharge standards. ... the pump discharge may be routed through the trap or basin. ... may not be discharged directly to detention ponds ... Straw bale structures and filter fabric structures are not acceptable ... Sump Pits, as shown in Standard Construction Detail #3-17, may be used to filter pumped water
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementE&S Manual, additional notes to Detail #3-16: the pumping rate into a filter bag must be no greater than 750 gpm or half the manufacturer's maximum, whichever is less. Pump intakes must be floating and screened. Filter bags must be inspected daily, and if any problem is detected, pumping must stop immediately and not resume until the problem is corrected.

    Applies when: Use of pumped water filter bags (E&S Plan guidance) E&S Manual 386-2134-001, Standard Construction Detail #3-16 (additional notes), p. 55 [33]
    Show the source text
    The pumping rate shall be no greater than 750 gpm or ½ the maximum specified by the manufacturer, whichever is less. Pump intakes shall be floating and screened. Filter bags shall be inspected daily. If any problem is detected, pumping shall cease immediately and not resume until the problem is corrected.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • DEP enforcement example: in February 2024, during improvements to Dunmore No. 7 Dam (Lackawanna County), tons of sediment that had built up behind the dam were unexpectedly released into Roaring Brook and the Lackawanna River. DEP Dam Safety staff had the contractor close one drawdown and nearly close another to cut the flow downstream. In lieu of a civil penalty, the dam owner (PA American Water) agreed in a settlement with DEP to perform a Community Environmental Project, projected at $350,000, to mitigate the impacts of the sediment release.

    Applies when: Enforcement context for sediment released downstream during dam work or drawdown DEP news release, June 27, 2025 (Dunmore No. 7 Dam Sediment Release Response) [34]
    Show the source text
    During improvements to the Dunmore No. 7 Dam in Lackawanna County in February 2024, there was an unexpected release of tons of sediment that had built up behind the dam into the Roaring Brook and Lackawanna River. ... Dam Safety staff communicated with contractors to close one drawdown and nearly close another to minimize the flow downstream ... As part of a settlement that DEP reached with PA American Water, in lieu of a civil penalty, the company agreed to perform a Community Environmental Project (CEP) ... The value of the project is projected at $350,000
    Open Pennsylvania Department of Environmental Protection (pa.gov) (opens in a new tab)

Maintenance dredging and E&S duties for in-pond earthwork

Chapter 102 defines an earth disturbance activity as a construction or other human activity that disturbs the surface of the land. Its listed examples include grading, excavations, embankments and the moving, depositing, stockpiling or storing of soil, rock or earth materials; because they follow the word "including", the list is not exhaustive. Simply releasing water from a pond is not among the listed examples, and the definition does not say whether a drawdown by itself is an earth disturbance activity. [35]

For maintenance dredging of an artificial pond behind a non-jurisdictional dam, DEP says the Water Obstruction and Encroachment Permit is waived when the work is limited to the original storage capacity and removes only accumulated sediment, and the drainage area is 100 acres or less, the greatest depth at maximum storage is 15 feet or less and the impounding capacity is 50 acre-feet or less. DEP adds that pond and dam owners should still obtain E&S Plan approval from their County Conservation District. [10]

DEP's FAQ tells the owner of a silted-in non-jurisdictional dam that no Chapter 105 authorization is needed to remove accumulated sediment, but that federal authorization may be required from the U.S. Army Corps of Engineers and the Fish and Boat Commission may require a Drawdown Permit. [10]

The E&S Manual's guidance on earthwork within lakes and ponds says the appropriate Chapter 105 permits must be obtained from DEP wherever the structures it describes are installed. It says that because pond water usually has no appreciable flow velocity, a cofferdam is usually enough to protect impounded water from construction turbidity. It adds that a turbidity barrier (silt curtain) is generally used for relatively short periods, usually less than 1 month, and that for ponds and other still water the barrier fabric should be relatively impermeable. [33]

  • Definition25 Pa. Code § 102.1 defines "earth disturbance activity" as a construction or other human activity that disturbs the surface of the land. It lists, among others, land clearing and grubbing, grading, excavations, embankments, and the moving, depositing, stockpiling or storing of soil, rock or earth materials. Simply releasing water from a pond is not among the listed examples; the list follows the word "including", so it is not exhaustive, and the definition does not say whether a drawdown by itself is an earth disturbance activity.

    25 Pa. Code § 102.1 ("Earth disturbance activity") [35]
    Show the source text
    Earth disturbance activity—A construction or other human activity which disturbs the surface of the land, including land clearing and grubbing, grading, excavations, embankments, land development, agricultural plowing or tilling, operation of animal heavy use areas, timber harvesting activities, road maintenance activities, oil and gas activities, well drilling, mineral extraction, and the moving, depositing, stockpiling, or storing of soil, rock or earth materials.
    Open Pennsylvania Code & Bulletin (opens in a new tab)
  • ProcessDEP's pond guidance for artificial ponds behind non-jurisdictional dams addresses maintenance dredging; it does not address draining the pond as such. Maintenance dredging limited to the original storage capacity, removing only accumulated sediment, is waived from a Water Obstruction and Encroachment Permit where the drainage area is 100 acres or less, the greatest depth at maximum storage is 15 feet or less, and the impounding capacity is 50 acre-feet or less. Pond and dam owners should still obtain E&S Plan approval from their County Conservation District.

    Applies when: Artificial ponds with non-jurisdictional dams DEP, "Introduction to Ponds and Chapter 105", Common Pond Maintenance Activities - Artificial Ponds with Non-Jurisdictional Dams [10]
    Show the source text
    waiver of Water Obstruction and Encroachment Permit requirements ... if this maintenance is limited to the impoundment’s original storage capacity and only accumulated sediment is removed. This waiver only applies when: The contributory drainage area is less than or equal to 100 acres. The greatest depth of water at maximum storage elevation is less than or equal to 15 feet. The impounding capacity at maximum storage elevation is less than or equal to 50- acre feet. Pond and dam owners should still obtain Erosion and Sediment Control Plan approval from their County Conservation District.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • ProcessDEP's pond FAQ answers the owner of a silted-in non-jurisdictional dam who wants to clean it out: no Chapter 105 authorization is needed to remove accumulated sediment, but federal authorization may be required from the U.S. Army Corps of Engineers and PFBC may require a Drawdown Permit. The FAQ section also notes that, whether or not Chapter 105 authorization is needed, Chapter 102 requires an E&S plan and E&S BMPs. The page does not otherwise address how pond water released during a drawdown must be handled.

    Applies when: Cleaning out a pond behind a non-jurisdictional dam DEP, "Introduction to Ponds and Chapter 105", Frequently Asked Questions [10]
    Show the source text
    the development of an erosion and sedimentation control plan and the implementation and maintenance of erosion and sedimentation control Best Management Practices is required under Chapter 102. ... I own a non-jurisdictional dam and it has silted in. What kind of permit do I need to clean it out? ... no Chapter 105 authorization is needed from the state to remove accumulated sediment. However, federal authorization may be required from US Army Corps of Engineers and the PA Fish and Boat Commission may require a Drawdown Permit.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementE&S Manual, "Earthwork within Lakes and Ponds": wherever the structures in this section are installed, the appropriate Chapter 105 permits must be obtained from DEP. Because pond water usually has no appreciable flow velocity, a cofferdam is usually enough to protect impounded water from construction turbidity. A turbidity barrier (silt curtain) is generally used for relatively short periods, usually less than 1 month. It should never be placed across flowing watercourses. For ponds and other still water, the curtain fabric should be relatively impermeable.

    Applies when: Earthwork inside an existing pond or lake, or along its shoreline (E&S Plan guidance) E&S Manual 386-2134-001, ch. 3, "Earthwork within Lakes and Ponds", p. 49 [33]
    Show the source text
    NOTE: Wherever the structures described in this section are installed, the appropriate Chapter 105 permits must be obtained from the Department. ... Since the water within a lake or pond typically has no appreciable flow velocity, a cofferdam is usually sufficient to protect impounded water from the turbidity caused by construction activity. ... for relatively short periods of time, usually less than 1 month. ... should never be placed across flowing watercourses. ... For ponds and other relatively still water bodies, the fabric should be relatively impermeable
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)

Sealing or lining the pond bed: what DEP's Chapter 105 rules say

Chapter 105 defines a "body of water" to include a natural or artificial pond, an "encroachment" as a structure or activity that changes, expands or diminishes the course, current or cross section of a watercourse, floodway or body of water, and "fill" to include material used to replace an area with aquatic life with dry land or to change the bottom elevation of a regulated water. A "water obstruction" includes fill or an embankment located in, along or across or projecting into a body of water; for ponds, a water obstruction is considered in or along the water if, at normal pool elevation, it is in the water or adjacent to and abutting the water's edge. [8]

Under 25 Pa. Code § 105.11, a person may not construct, operate, maintain, modify, enlarge or abandon a dam, water obstruction or encroachment without first obtaining a written DEP permit; a DEP permit issued after July 1, 1979 for the construction and operation of a water obstruction or encroachment includes authorization for normal repairs and maintenance within the original specifications, but a modification from those specifications and a repair or reconstruction involving a substantial portion of the structure require DEP's prior written permit. [36]

Section 105.12(a)(14) waives the permit requirement for maintenance of an artificial pond or reservoir to its original storage capacity where the contributory drainage area is 100 acres or less, the greatest water depth at maximum storage elevation is 15 feet or less and the impounding capacity at maximum storage elevation is 50 acre-feet or less. DEP may still require a permit if, on complaint or investigation, a waived activity has a significant effect on safety or the protection of life, health, property or the environment. [9]

DEP's pond guidance says its rules do not regulate the repair and maintenance of non-jurisdictional dams. For a leaking dam or failing outlet pipe, DEP's FAQ says repair work on a non-jurisdictional dam is not regulated under Chapter 105, and that the owner of a jurisdictional dam should contact DEP's Division of Dam Safety to determine regulatory requirements; DEP's guidance adds that any repair or modification of any kind to a jurisdictional dam should be presented to that Division for a determination of regulatory requirements. [10]

DEP's Chapter 105 General Permits page lists 12 general permits. GP-9 (Agricultural Activities, Rev. 6/2013) covers grassed or lined waterways, terraces, diversions, waste storage facilities, spring development and supporting minor drainage, may be used only as part of a conservation plan approved by the county conservation district, and does not list ponds or pond liners. GP-11 (Rev. 6/2013) covers maintenance, testing, repair, rehabilitation or replacement of existing, currently serviceable water obstructions or encroachments, may not be used for the maintenance, repair, modification, removal or replacement of dams, and requires the acknowledged Registration Form from DEP before work begins. [37][38][39]

  • DefinitionChapter 105 defines a 'water obstruction' as a dike, bridge, culvert, wall, wingwall, fill, pier, wharf, embankment, abutment or other structure located in, along or across or projecting into a watercourse, floodway or body of water; for ponds, lakes and reservoirs, a water obstruction is in or along the body of water if, at normal pool elevation, it is either in the water or adjacent to and abutting the water's edge.

    Applies when: Deciding whether material or structures placed in a pond are water obstructions 25 Pa. Code § 105.1 (definition of "Water obstruction") [8]
    Show the source text
    (i) A dike, bridge, culvert, wall, wingwall, fill, pier, wharf, embankment, abutment or other structure located in, along or across or projecting into a watercourse, floodway or body of water. (ii) In the case of ponds, lakes and reservoirs, a water obstruction is considered to be in or along the body of water if, at normal pool elevation, the water obstruction is either in the water or adjacent to and abutting the water’s edge.
    Open Pennsylvania Code & Bulletin (opens in a new tab)
  • RequirementChapter 105's basic rule: a person may not construct, operate, maintain, modify, enlarge or abandon a dam, water obstruction or encroachment without first obtaining a written DEP permit. A DEP permit issued after July 1, 1979 for the construction and operation of a water obstruction or encroachment incorporates authorization for normal repairs and maintenance within the original specifications, but a repair or maintenance that modifies the structure from its original specifications, and a repair or reconstruction involving a substantial portion of the structure, require DEP's prior written permit.

    Applies when: Any work on a dam, water obstruction or encroachment not covered by a waiver or general permit 25 Pa. Code § 105.11(a), (d) [36]
    Show the source text
    A person may not construct, operate, maintain, modify, enlarge or abandon a dam, water obstruction or encroachment without first obtaining a written permit ... after July 1, 1979, for the construction and operation of a water obstruction or encroachment will incorporate authorization for normal repairs and maintenance of permitted structures conducted within the original specifications ... modification of the water obstruction or encroachment from its original specifications and a repair or reconstruction involving a substantial portion of the structure shall require the prior written permit
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • ExemptionChapter 105's waiver for pond maintenance is § 105.12(a)(14): the permit requirement is waived for maintenance of an artificial pond or reservoir to its original storage capacity where the contributory drainage area is 100 acres or less, the greatest water depth at maximum storage elevation is 15 feet or less, and the impounding capacity at maximum storage elevation is 50 acre-feet or less. DEP may still require a permit if, on complaint or investigation, a waived activity has a significant effect on safety or the protection of life, health, property or the environment.

    Applies when: Maintenance of a small artificial pond 25 Pa. Code § 105.12(a) (introductory text), (a)(14) [9]
    Show the source text
    has a significant effect upon safety or the protection of life, health, property or the environment, the Department may require the owner ... to apply for and obtain a permit ... (14) The maintenance of an artificial pond or reservoir to its original storage capacity where: (i) The contributory drainage area is less than or equal to 100 acres. (ii) The greatest depth of water at maximum storage elevation is less than or equal to 15 feet. (iii) The impounding capacity at maximum storage elevation is less than or equal to 50 acre feet.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • RequirementFor a leaking dam or failing outlet pipe, DEP's pond FAQ says: if the dam is jurisdictional, contact DEP's Division of Dam Safety to determine regulatory requirements; if it is non-jurisdictional, repair work is not regulated under Chapter 105. For jurisdictional dams, the guidance says any dam repair or modification of any kind should be presented to the Division of Dam Safety for a determination of regulatory requirements.

    Applies when: Leaking pond or dam repair DEP, "Introduction to Ponds and Chapter 105" (pa.gov), Jurisdictional Dams - Dam/Outlet Repair; FAQ "My dam is leaking/my outlet pipe is failing" [10]
    Show the source text
    Dam/Outlet Repair - Any dam repair or modification of any kind to a jurisdictional dam should be presented to DEP’s Division of Dam Safety for a determination of regulatory requirements. ... Question: My dam is leaking/my outlet pipe is failing. What authorization do I need to conduct repairs? Answer: If your dam is jurisdictional, contact DEP’s Division of Dam Safety to determine regulatory requirements. If your dam is non-jurisdictional, repair work is not regulated under Chapter 105.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • StatusDEP's Chapter 105 General Permits page describes 12 general permits: GP-1 Fish Habitat Enhancement Structures; GP-2 Small Docks and Boat Launching Ramps; GP-3 Bank Rehabilitation, Bank Protection, and Gravel Bar Removal; GP-4 Intake and Outfall Structures; GP-5 Utility Line Stream Crossings; GP-6 Agricultural Crossings and Ramps; GP-7 Minor Road Crossings; GP-8 Temporary Road Crossings; GP-9 Agricultural Activities; GP-10 Abandoned Mine Reclamation; GP-11 Maintenance, Testing, Repair, Rehabilitation or Replacement of Water Obstructions and Encroachments; and GP-15 Private Residential Construction in Wetlands.

    Applies when: Checking whether a Chapter 105 general permit covers sealing or lining a pond DEP, "Chapter 105 General Permits" (pa.gov), Chapter 105 General Permit Types [37]
    Show the source text
    GP-1 Fish Habitat Enhancement Structures ... GP-2 Small Docks and Boat Launching Ramps ... GP-3 Bank Rehabilitation, Bank Protection, and Gravel Bar Removal ... GP-4 Intake and Outfall Structures ... GP-5 Utility Line Stream Crossings ... GP-6 Agricultural Crossings and Ramps ... GP-7 Minor Road Crossings ... GP-8 Temporary Road Crossings ... GP-9 Agricultural Activities ... GP-10 Abandoned Mine Reclamation ... GP-11 Maintenance, Testing, Repair, Rehabilitation or Replacement of Water Obstructions and Encroachments ... GP-15 Private Residential Construction in Wetlands
    Open PA Department of Environmental Protection (opens in a new tab)
  • RequirementGP-9 (Agricultural Activities, Rev. 6/2013) covers these agricultural activities: grassed or lined waterways, terraces, diversions, waste storage facilities, spring development and supporting minor drainage. It may be used only as part of a conservation plan approved by the county conservation district; those activities must be built and maintained to 25 Pa. Code § 101.8 and the design standards in the NRCS technical guide for Pennsylvania. Ponds and pond liners are not among the listed activities.

    Applies when: Farm projects considering GP-9 DEP General Permit BWEW-GP-9, Agricultural Activities (3150-PM-BWEW0509, Rev. 6/2013), §§ 1, 12.a-12.b [38]
    Show the source text
    These agricultural activities are grassed or lined waterways, terraces, diversions, waste storage facilities, spring development and minor drainage that supports these activities ... The use of this General Permit is only authorized as part of a conservation plan approved by a County Conservation District ... must be constructed and maintained according to 25 Pa. Code Chapter 101.8 and the design standards and specifications found in the technical guide for Pennsylvania available through the U.S. Department of Agriculture, Natural Resources Conservation Service
    Open PA Department of Environmental Protection, Bureau of Waterways Engineering and Wetlands (opens in a new tab)
  • ExemptionGP-11 (Rev. 6/2013; effective August 10, 2004 and in effect unless specifically modified, suspended or revoked by DEP) authorizes maintenance, testing, repair, rehabilitation or replacement of existing, currently serviceable water obstructions or encroachments. Minor deviations in the structure's configuration or filled area needed to repair, modify or replace the structure are permitted only if the environmental impacts are minimal, those minimal impacts fall within the GP's terms and conditions, and there is no adverse impact on public health and safety. GP-11 may not be used for the maintenance, repair, modification, removal or replacement of dams. The owner may not begin work until receiving the acknowledged Registration Form from DEP.

    Applies when: Repair of existing structures in or along a pond (not the dam itself) DEP General Permit BWEW-GP-11 (3150-PM-BWEW0511, Rev. 6/2013), §§ 1, 2, 4, 5 [39]
    Show the source text
    the maintenance, testing, repair, rehabilitation or replacement of existing currently serviceable, water obstructions or encroachments ... are minimal, those minimal impacts fall within the terms and conditions of this General Permit, and there is no adverse impact on public health and safety. ... may not be used for the maintenance, repair, modification, removal, or replacement of dams. ... becomes effective August 10, 2004 and will remain in effect unless specifically modified, suspended, or revoked ... may not begin work until he has received the acknowledged “Registration Form”
    Open PA Department of Environmental Protection, Bureau of Waterways Engineering and Wetlands (opens in a new tab)

Products added to pond water, and fish-protection rules

DEP's Chapter 91 rule authorizes an algicide, herbicide or fish-control chemical only as copper sulfate to control algae in a public water supply source with DEP approval, or for chemicals required to control aquatic plants or manage fish populations under joint approval of DEP and the Fish and Boat Commission; its text does not mention sealants or flocculants. DEP's pesticide FAQ says chemicals applied to water for purposes other than controlling pests are not pesticides and are not subject to the NPDES pesticide requirements, but that using alum or other chemicals to control algae or other pests requires a joint Chapter 91 permit. [11][40]

DEP's list of alternative E&S BMPs (revised February 11, 2026) says anionic polyacrylamide (PAM) uses where treated stormwater flows into a sediment trap or basin need no Bureau of Clean Water approval, that anionic PAM uses where treated stormwater flows directly to surface waters or storm sewers without settling, or application directly to traps or basins, need that approval first, and that any flocculant or material containing cationic PAM is prohibited for stormwater treatment. The E&S Manual adds that anionic PAM mixtures used as a temporary soil binder must be non-toxic to fish and other aquatic species and may not be applied within the floodway of a receiving stream channel or within 25 feet of other water bodies. [12][33]

DEP's chemical-additives process is implemented through industrial waste NPDES permits and covers chemical products introduced into a waste stream for cleaning, disinfecting or maintenance that may be detected in effluent discharged to waters of the Commonwealth. [41]

The Fish and Boat Code bars anyone, regardless of intent, from putting electricity, explosives or poisonous substances into waters within or on the boundaries of the Commonwealth (except for research and fish management by agents of, or persons authorized by, the Commission's executive director), or allowing any substance deleterious, destructive or poisonous to fish to run, flow, wash or be emptied into any waters within or bordering on the Commonwealth; a violation is a third-degree misdemeanor. It is also a third-degree misdemeanor to alter or disturb any stream, stream bed, fish habitat, water or watershed in any manner that might cause damage to, or loss of, fish without the necessary permits. [13]

For that prohibition on altering or disturbing waters (30 Pa.C.S. § 2502), Commission rules deem a permit "necessary" if the activity would violate statutes or regulations administered by the Commission, DEP, the U.S. Environmental Protection Agency, the U.S. Army Corps of Engineers or local municipalities if done without a permit; the listed examples include Chapter 105 dam, water obstruction or encroachment permits, the algicide, herbicide or fish-control-chemical permit, and the permit to draw off impounded water. [7]

  • DEP's pesticide FAQ says chemicals applied to water for purposes other than controlling pests are not pesticides and so are not subject to the NPDES pesticide requirements (its example is alum, which controls phosphorus to inhibit algae but is not itself an algicide); however, use of alum or other chemicals to control algae or other pests requires a joint Chapter 91 permit.

    Applies when: Non-pesticide products applied to pond water DEP, Water Quality Permitting for Pesticide Applications in Pennsylvania - FAQ (rev. Feb. 21, 2025), FAQ #23 [40]
    Show the source text
    Chemicals that are applied to water for purposes other than controlling pests are not considered pesticides, and therefore are not subject to the NPDES requirements for pesticide applications. For example, alum is a product used to control concentrations of phosphorus in water to inhibit algae growth, but itself is not an algicide. However, use of alum or other chemicals to control algae or other pests are subject to the requirement to obtain a joint Chapter 91 permit.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementDEP's Alternative E&S BMPs and PCSM SCMs list (revised February 11, 2026) states that anionic polyacrylamide (PAM) uses where treated stormwater flows into a sediment trap or basin need no Bureau of Clean Water approval; Bureau of Clean Water approval is required before any anionic PAM use where treated stormwater will flow directly to surface waters or storm sewers without settling in a trap or basin, or before applying it directly to sediment traps or basins; and any flocculant or material containing cationic PAM is prohibited for stormwater treatment.

    Applies when: Polyacrylamide flocculants/soil binders on Chapter 102 earth-disturbance projects DEP, Alternative E&S BMPs and PCSM SCMs (rev. Feb. 11, 2026), Introduction and "Soil Binders and Flocculants with Polyacrylamides" [12]
    Show the source text
    The following uses do not require Bureau of Clean Water approval before use: Any use of anionic PAMs where treated stormwater will flow into a sediment trap ... The following uses require Bureau of Clean Water ... approval before use: Any use of anionic PAMs where ... treated stormwater will flow directly to surface waters or ... storm sewers without settlement in a sediment trap or basin, or application directly to sediment traps or basins. The following uses are prohibited: The use of any flocculant or material containing cationic PAMs for stormwater treatment.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementDEP's Erosion and Sediment Pollution Control Program Manual (effective March 31, 2012, p. 276) sets specifications for water-soluble anionic PAM used as a temporary soil-binding agent: application must comply with all federal, state and local laws governing anionic PAM; mixtures must be non-toxic to fish and other aquatic species; cationic PAM may not be used due to toxicity to aquatic species; anionic PAM mixtures must have less than 0.05% free acrylamide monomer by weight; and anionic PAM may not be applied within the floodway of a receiving stream channel or within 25 feet of other water bodies.

    Applies when: Anionic PAM used as an E&S soil binder (construction context) DEP, Erosion and Sediment Pollution Control Program Manual (technical guidance, effective March 31, 2012), pp. 276-277, "Soil Binders", "PAM Specifications" and "Application" [33]
    Show the source text
    Water-soluble anionic polyacrylamide (PAM) may be applied to a disturbed area as a temporary soil-binding agent ... must comply with all federal, state and local laws and regulations governing anionic PAM. ... non-toxic to fish and other aquatic species ... Cationic PAM may not be used due to its toxicity to aquatic species. ... Anionic PAM mixtures must have < 0.05% free acrylamide monomer by weight ... Anionic PAM may not be applied within the floodway of a receiving stream channel or within 25 feet of other water bodies.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • DefinitionDEP's chemical-additives process is implemented through industrial waste NPDES permits. A 'chemical additive' is a chemical product introduced into a waste stream for cleaning, disinfecting or maintenance that may be detected in effluent discharged to waters of the Commonwealth; the term generally excludes chemicals used for neutralization of waste streams, production of goods, and treatment of wastewater. The process uses a Chemical Additives Notification Form (3800-FM-BCW0487) and a New Chemical Additives Request Form (3800-FM-BCW0486).

    Applies when: Industrial NPDES permittees (not direct application to a pond) DEP, "Chemical Additives" (pa.gov, Wastewater Management) [41]
    Show the source text
    The term "chemical additive" means a chemical product ... introduced into a waste stream that is used for cleaning, disinfecting, or maintenance and which may be detected in effluent discharged to waters of the Commonwealth. The term generally excludes chemicals used for neutralization of waste streams, the production of goods, and treatment of wastewater. ... their industrial waste NPDES permits will include language that implements the following process: ... Chemical Additives Notification Form (3800-FM-BCW0487) ... New Chemical Additives Request Form (3800-FM-BCW0486)
    Open PA Department of Environmental Protection, Bureau of Clean Water (opens in a new tab)
  • RequirementThe Fish and Boat Code makes it a third-degree misdemeanor to alter or disturb any stream, stream bed, fish habitat, water or watershed in any manner that might cause damage to, or loss of, fish without the necessary permits.

    Applies when: Pond work that could affect fish 30 Pa.C.S. § 2502 [13]
    Show the source text
    (a) General rule.--No person shall alter or disturb any stream, stream bed, fish habitat, water or watershed in any manner that might cause damage to, or loss of, fish without the necessary permits. (b) Penalty.--Any person violating the provisions of this section commits a misdemeanor of the third degree.
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • RequirementPFBC's regulation deems a permit 'necessary' under 30 Pa.C.S. § 2502 if the activity would violate statutes or regulations administered by PFBC, DEP, U.S. EPA, the Army Corps of Engineers or local municipalities if done without a permit; its examples include Chapter 105 dam, water obstruction or encroachment permits, the algicide/herbicide/fish-control-chemical permit and the permit to draw off impounded water.

    Applies when: Pond work that could affect fish without all required permits 58 Pa. Code § 51.61(a), (b)(8), (10), (11), (18), (19) [7]
    Show the source text
    (a) A permit shall be deemed necessary under 30 Pa.C.S. § 2502 ... if the activity would be a violation of statutes or regulations administered by the Commission, the Department of Environmental Resources, the United States Environmental Protection Agency, the United States Army Corps of Engineers or local municipalities if the activity were performed without a permit. ... (11) Dam, water obstruction or encroachment permits ... (18) Permit for use of an algicide, herbicide or fish control chemical in waters of this Commonwealth. (19) Permit to draw off impounded water.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)

NRCS Pennsylvania design standards for sealing and lining (520 and 521)

As of September 28, 2026, NRCS Pennsylvania's technical guide lists its standard for Pond Sealing or Lining - Compacted Soil Treatment (520) with five 2016 documents, and its standard for Pond Sealing or Lining - Geomembrane or Geosynthetic Clay Liner (521) with four documents, each with a revision date of October 1, 2024. PA 520 covers liners of compacted soil, with or without amendments, where in-place soils have excessive seepage rates and suitable soil is available either for a compacted liner or for treatment with a soil dispersant or bentonite; for a clean water pond the liner must be designed to reduce seepage to a rate that will allow the pond to function as intended. [42][43][44]

Under PA 520, bentonite must be sodium bentonite with a free swell of at least 22 milliliters (ASTM D5890) unless laboratory tests using other bentonite types are used for design. For clean water ponds without laboratory tests or field performance data on similar soils, minimum bentonite rates per 1 inch of lift are 0.375 lb/sq ft for silts (ML, CL-ML), 0.5 lb/sq ft for silty sands (SM, SC-SM, SP-SM) and 0.625 lb/sq ft for clean sand (SP, SW), with lifts no thicker than 6 inches. [44]

The finished PA 520 liner must be at least the greatest of the thickness needed to meet a specific-discharge design value, a thickness required by State regulations, or the Table 1 minimum: 12 inches for a design storage depth of 16 ft or less, 18 inches for 16.1-24 ft and 24 inches for 24.1-30 ft. [44]

The PA 520 practice specification calls for amendments to be applied uniformly in dry form on the soil surface, not when the temperature is below 40°F or expected to drop below 40°F within 24 hours, with mixing, placement and compaction completed within the same workday and curing for at least 72 hours unless otherwise specified; standing water or mud may not be present during placement, and the Engineer must inspect and approve the foundation before bentonite or earth fill is placed. The standard says side slopes should be 3H:1V or flatter for "bathtub" construction, while slopes as steep as 2H:1V can be considered with the "stair-step" method. [44][45]

PA 521 lists minimum clear-water geomembrane thicknesses including 30 mil for HDPE and PVC and 45 mil for EPDM, and lists 0.75 lbs./square foot for a geosynthetic clay liner; PVC liners and geosynthetic clay liners must be covered with at least 12 inches of soil. As a consideration, it says PVC geomembranes are not recommended for aquatic production because stabilizers in PVC liner material leach out and may be harmful to aquatic species. [46]

PA 521 requires the liner to be planned, designed and constructed to comply with all Federal, State, Tribal and local laws, and NRCS's statements of work for both standards include, as deliverables, a list of required permits to be obtained by the client and verification that the client obtained them. PA 520's design and construction data requirements list documenting PA One-Call compliance before digging and an erosion and sediment control plan referring to DEP's E&S Manual, say additional details may be needed if a DEP permit is required, and say the O&M plan should include drawdown restrictions, especially if the liner is covered with soil. [46][47][48][49]

The NRCS Pennsylvania Pond (378) practice specification (October 2023) directs that any use of soil dispersants or bentonite in a pond soil liner conform to Specification 520, and that other liners, such as flexible membranes, be installed under Specification 521. [50]

  • DefinitionPA NRCS 520 defines Pond Sealing or Lining - Compacted Soil Treatment as a liner for an impoundment built of compacted soil with or without soil amendments, installed to reduce seepage losses from impoundments constructed for water conservation and environmental protection. It applies where in-place natural soils have excessive seepage rates and either enough suitable soil is available for a compacted liner without amendments, or enough soil suitable for treatment with a soil dispersant or bentonite amendment is available for an amended liner.

    Applies when: Deciding whether the 520 practice fits a leaking or proposed pond NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Definition; Purpose; Conditions Where Practice Applies (p. 520-CPS-1) [44]
    Show the source text
    A liner for an impoundment constructed using compacted soil with or without soil amendments. ... To reduce seepage losses from impoundments constructed for water conservation and environmental protection ... In-place natural soils have excessive seepage rates, and ... An adequate quantity and type of soil suitable for constructing a compacted soil liner without amendments is available, or ... An adequate quantity and type of soil suitable for treatment with a soil dispersant or bentonite amendment is available for an amended soil liner.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementBentonite used under PA 520 must be sodium bentonite with a free swell of at least 22 milliliters measured by ASTM D5890, unless laboratory tests using other bentonite types are used for design. Personnel must wear masks and goggles against bentonite dust during handling, application and mixing.

    Applies when: Bentonite-amended soil liners NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Additional Criteria for Bentonite Treatment - Bentonite Material; Safety (p. 520-CPS-3) [44]
    Show the source text
    The bentonite must be a sodium bentonite with a free swell of at least 22 milliliters as measured by ASTM Standard Test Method D5890, unless laboratory tests using other bentonite types are used for design. ... During bentonite handling, application and mixing, personnel on site must wear masks and goggles for protection against bentonite dust.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • Size cutoffFor clean water ponds, absent laboratory tests or field performance data on similar soils, PA 520 sets minimum bentonite application rates per 1-inch of lift thickness: 0.375 lb/sq ft for silts (ML, CL-ML), 0.5 lb/sq ft for silty sands (SM, SC-SM, SP-SM) and 0.625 lb/sq ft for clean sand (SP, SW), with a maximum 6-inch lift.

    Applies when: Bentonite-amended liner for a clean water pond (no site-specific lab data) NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Additional Criteria for Bentonite Treatment - Application Rate, Table 3 (p. 520-CPS-3) [44]
    Show the source text
    For clean water ponds, in the absence of laboratory tests or field performance data on soils similar to those to be treated, apply the bentonite at a rate equal to or greater to the amount listed in table 3. Install the liner with a maximum of 6-inch-lift thickness. ... Silts (ML, CL-ML) 0.375 ... Silty Sands (SM, SC- SM, SP-SM) 0.5 ... Clean Sand (SP, SW) 0.625
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • Size cutoffMinimum finished compacted liner thickness under PA 520 is the greatest of (a) the thickness needed to achieve a specific-discharge design value, (b) a thickness required by State regulations, or (c) Table 1: 12 inches for a design storage depth of 16 ft or less, 18 inches for 16.1-24 ft, and 24 inches for 24.1-30 ft.

    Applies when: Any 520 compacted soil liner, including bentonite-amended liners NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Criteria - Liner Thickness, Table 1 (p. 520-CPS-2) [44]
    Show the source text
    The minimum thickness of the finished compacted liner must be the greater of— ... The liner thickness required to achieve a specific discharge (unit seepage) design value, or ... A liner thickness required by State regulations, or ... The minimum liner thickness as shown in table 1. ... ≤16 12 ... 16.1–24 18 ... 24.1–30 24
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 520 Practice Specification (equipment and application): disks must be at least 24 inches in diameter, and rotary mixers must be able to mix lifts at least 9 inches thick while traveling at a minimum of 4 mph and covering a width of at least 6 feet. Amendments may not be applied when the temperature is below 40°F or is expected to drop below 40°F within 24 hours, or during high wind conditions that hinder effective application or cause pollution by drift off site, and must be applied uniformly in dry form on the soil surface at a rate that will attain the specified proportioning.

    Applies when: Applying and mixing bentonite or dispersant on a pond bed NRCS Pennsylvania Practice Specification, Pond Sealing or Lining - Compacted Soil Treatment (Code 520) (NRCS, PA, June 2016), Sections 3 (Equipment) and 6 (Amendment Application) [45]
    Show the source text
    Disks shall be at least 24-inches in diameter and rotary mixers shall be capable of mixing lifts at least nine (9) inches thick traveling at a minimum speed of four (4) mph and covering a minimum width of six (6) feet. ... Amendments shall not be applied when the temperature is below 40°F or is expected to drop below 40°F within 24-hours. Amendments will not be applied during high wind conditions that hinder effective application or causes pollution by drift off site. Amendments shall be uniformly applied in dry form on the soil surface at a rate that will attain the specified proportioning.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 520 Practice Specification (compaction and curing): mixing, placement and compaction of the soil-amendment mixture must be completed within the same workday it is started, and the top surface is sealed by rolling with pneumatic-tired equipment or a smooth steel roller. The mixture must be cured at least 72 hours unless otherwise specified in Section 10, with its water content kept at or above standard optimum water content by sprinkling the sealed surface or by covering it with a 6-inch layer of moist soil or another approved cover.

    Applies when: Compaction and curing of a bentonite-amended liner NRCS Pennsylvania Practice Specification, Pond Sealing or Lining - Compacted Soil Treatment (Code 520) (NRCS, PA, June 2016), Sections 8 (Placement and Compaction) and 9 (Curing and Protection) [45]
    Show the source text
    The mixing, placement and compaction of the mixture shall be completed within the same workday it is started. ... The top surface of the completed soil- amendment mixture shall be sealed by rolling with a pneumatic tired equipment or a smooth steel roller. ... The compacted soil-amendment mixture shall be cured a minimum of 72-hours ... The water content of the mixture shall be maintained at or above standard optimum water content during the curing period by sprinkling the sealed surface with water or by covering it with a 6 inch layer of moist soil or another approved cover.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 520 Practice Specification (materials and site preparation): rock particles larger than 4 inches in diameter must be removed from the liner soil before treatment; bentonite, where required, must be sodium bentonite with a free swell of at least 22 mL (ASTM D5890) unless otherwise detailed in the drawings or Section 10 of the specification; the foundation is stripped of topsoil and graded to a relatively smooth, uniform surface; in addition to the treated liner, at least 2 feet of compacted fine-grained soil is placed over fractured rock or other highly permeable material; no standing water or mud may be present during placement; and the Engineer must inspect and approve the foundation before bentonite or earth fill is placed.

    Applies when: Construction of a bentonite- or dispersant-amended soil liner to NRCS PA specifications NRCS Pennsylvania Practice Specification, Pond Sealing or Lining - Compacted Soil Treatment (Code 520) (NRCS, PA, June 2016), Sections 2 (Materials) and 4 (Site Preparation) [45]
    Show the source text
    Rock particles larger than 4 inches in diameter shall be removed ... sodium bentonite with a free swell of at least 22 milliliters as measured by ASTM Standard Test Method D5890, unless otherwise detailed in the drawings or Section 10 of this specification. ... stripped of topsoil and graded to a relatively smooth and uniform surface. ... at least 2 feet of compacted fine grained soil shall be placed over fractured rock ... Standing water or mud shall not be present during placement operations. The foundation shall be inspected and approved by the Engineer prior to the placement of bentonite
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • Size cutoffPA 521 Table 1 minimum liner thickness for clear (clean) water ponds: HDPE 30 mil; LLDPE 30 mil; reinforced LLDPE (LLDPE-R) 24 mil; PVC 30 mil; EPDM 45 mil; flexible polypropylene (FPP) 30 mil; reinforced FPP (FPP-R) 36 mil; reinforced slit-film woven polyethylene (PE-R) 36 mil. For a geosynthetic clay liner (GCL), the table lists 0.75 lbs./square foot. Geomembranes must meet NRCS Material Specification 594 and GCLs Material Specification 595 (NEH Part 642, Chapter 3). (1 mil = 1/1000 inch.)

    Applies when: Selecting a geomembrane or GCL for a clean water pond NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 521-CPS (NRCS, PA, September 2024), Materials, Table 1 and notes (p. 521-CPS-2) [46]
    Show the source text
    Wastewater Clear Water ... HDPE Polyethylene 60 30 ... LLDPE Polyethylene 60 30 ... LLDPE-R Polyethylene 45 24 ... PVC Polyvinyl Chloride 40 30 ... EPDM Diene Terpolymer 45 45 ... FPP Polypropylene 45 30 ... FPP-R Polypropylene 45 3 36 ... PE-R Polyethylene NR 3 36 ... GCL Liner 0.75 lbs./square foot ... “Material Specification 594 – Geomembrane Liner.” GCL materials must meet the criteria in NRCS NEH, Part 642, Chapter 3, “Material Specification 595 – Geosynthetic Clay Liner.”
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 521 cover soil: PVC liners and GCLs must be covered with at least 12 inches of soil (measured perpendicular to the surface); cover soil is optional on other liners unless essential. Maximum cover particle size is 3/8 inch (geomembranes) and 1/2 inch (GCLs); cover must be placed within 24 hours after placement and anchorage of the liner; the section states side slopes shall be no steeper than 5:1. No drainage layer or venting system may be installed beneath a GCL.

    Applies when: Covering a PVC or GCL pond liner NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 521-CPS (NRCS, PA, September 2024), Cover soil (p. 521-CPS-4) [46]
    Show the source text
    Cover PVC liners and GCLs with a minimum of 12 inches of soil measured perpendicular to the finished surface. Cover soil may be used on other liners but is not required unless essential ... The maximum allowable particle size of soil cover material is 3/8 inch for geomembrane liners and 1/2 inch for GCLs. ... Place cover soil within 24 hours after placement and anchorage of the liner ... Side slopes shall be no steeper than 5:1. ... Do not install a drainage layer or venting system beneath a GCL
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • As a consideration, PA 521 states that PVC geomembranes are not recommended for aquatic production because stabilizers in PVC liner material leach out and may be harmful to aquatic species, and advises consulting manufacturers before selecting a geomembrane for aquatic production. For GCLs, the standard requires analysis of wastewater, subgrade soil and cover soil so that undesirable cation exchange (calcium and magnesium for sodium) will not occur in the GCL.

    Applies when: Lining a pond that will hold fish; GCL (bentonite) liners NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 521-CPS (NRCS, PA, September 2024), Liner protection (p. 521-CPS-4); Considerations (p. 521-CPS-5) [46]
    Show the source text
    For GCL liners, analyze the wastewater, subgrade soil, and cover soil to ensure that undesirable cation exchange (calcium and magnesium for sodium) will not occur in the GCL. ... PVC geomembranes are not recommended for aquatic production. The stabilizers in the PVC liner material leach out and may be harmful to aquatic species. Consult with manufacturers before selecting a geomembrane material used for aquatic production.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA NRCS 521 defines the practice as a liner for a water, wastewater, salt, manure or similar agricultural by-product impoundment built with a geomembrane or geosynthetic clay material, applied (among other purposes) to reduce seepage losses for water conservation, including irrigation and livestock water. Its general criteria require the liner to be planned, designed and constructed to comply with all Federal, State, Tribal and local laws and regulations, designed and installed per manufacturer recommendations, with the installer or manufacturer certifying that the installation meets the plans and specifications.

    Applies when: Geomembrane or GCL pond liners NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 521-CPS (NRCS, PA, September 2024), Definition; Purpose; General Criteria (p. 521-CPS-1) [46]
    Show the source text
    A liner for a water, wastewater, salt, manure, or similar agricultural by-product impoundment constructed using a geomembrane or a geosynthetic clay material. ... Reduce seepage losses from an impoundment for water conservation, including for irrigation or for providing water for livestock. ... Plan, design, and construct the liner to comply with all Federal, State, Tribal, and local laws and regulations. ... Design and install the liner in accordance with manufacturer recommendations. The installer or manufacturer must certify that the liner installation meets
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • ProcessPA 520 Statement of Work: NRCS design deliverables include a list of required permits to be obtained by the client and plans/specifications adequate to install the practice and obtain necessary permits, plus certification that the design complies with applicable laws and regulations. Installation deliverables include verification that the client has obtained required permits, advising the client/NRCS on compliance with all federal, state, tribal and local laws during installation, and certification that installation meets design and permit requirements.

    Applies when: NRCS-assisted pond sealing projects NRCS Pennsylvania Statement of Work, Pond Sealing or Lining - Compacted Soil Treatment (520) (June 2016), Design deliverables 1.b, 2, 5; Installation deliverables 2, 6, 7 [47]
    Show the source text
    List of required permits to be obtained by the client ... obtain necessary permits. ... Certification that the design meets practice standard criteria and comply with applicable laws and regulations ... Verification that client has obtained required permits ... Advise client/NRCS on compliance issues with all federal, state, tribal, and local laws, regulations and NRCS policies during installation ... Certification that the installation process and materials meets design and permit requirements
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • ProcessThe PA 520 Design and Construction Data Requirements list items that must be addressed in the design folder. They state that a bentonite soil liner design requires approval by a person with the appropriate Engineering job approval authority, and that if a DEP permit is required, additional details may be needed. The listed design items include documenting PA One-Call compliance before digging and an erosion and sediment control plan that refers to DEP's Erosion and Sediment Pollution Control Program Manual. The quality assurance plan must include, as applicable, an onsite visit before construction of the bentonite-treated soil liner to check the subgrade condition, and the O&M plan should include drawdown restrictions, especially if the liner is covered with soil.

    Applies when: Design review of a bentonite liner with NRCS assistance NRCS Pennsylvania, PA520 Pond Sealing or Lining - Compacted Soil Treatment, Design and Construction Data Requirements (Technical Guide Section IV, September 2016), pp. PA520-i to -iii [49]
    Show the source text
    A bentonite soil liner design requires approval by ... a person with the appropriate Engineering job ... Document compliance with PA One-Call ... If a DEP ... permit is required, additional details may be ... Refer to DEP Erosion and Sediment Pollution ... onsite visits PRIOR to ... Construction of the bentonite treated soil ... liner to check the subgrade condition ... Drawdown restrictions, especially if
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementThe PA NRCS Pond (378) Practice Specification (October 2023) directs that any use of soil dispersants or bentonite in a pond soil liner conform to Specification 520, and that other liners (e.g., flexible membranes) be installed per Specification 521.

    Applies when: NRCS-designed ponds in Pennsylvania NRCS Pennsylvania Practice Specification, Pond (Code 378) (October 2023), "Soil Liners" and "Other Liners" [50]
    Show the source text
    The use of soil dispersants or bentonite shall conform to Specification 520. ... Other liners, e.g., flexible membrane, shall be installed in accordance with Specification 521.
    Open USDA NRCS Pennsylvania (opens in a new tab)

More detail

More detail: 32 more verified statements on Pennsylvania pond drawdown, dewatering and sealing
  • RequirementPAG-02 Part A I.B.3(c)-(e): if the permittee has reason to believe dewatering water may contain pollutants other than sediment, it must notify DEP or the conservation district in writing at least 7 days before discharging, and must sample and analyze for the pollutants DEP/CCD specifies when notified in writing. If the water exceeds Chapter 93 numeric water quality criteria or may otherwise harm surface waters, DEP/CCD may require the permittee to stop discharging and apply for an individual permit. An oil-water separator or suitable filtration device is required if the water contains oil, grease or other products. Material and backwash collected by filtration devices must be disposed of off-site unless DEP/CCD authorizes otherwise.

    Applies when: PAG-02 projects discharging construction dewatering water PAG-02 General Permit, Part A § I.B.3(c)-(e) [30]
    Show the source text
    The permittee must notify in writing DEP/CCD at least seven (7) days prior to discharges if the permittee has reason to believe that dewatering water may contain pollutants other than sediment. The permittee must collect sample(s) of the dewatering water ... DEP/CCD may require the permittee to cease discharging and submit an application for an individual permit. d. The permittee must use an oil-water separator or suitable filtration device ... e. The permittee must collect and dispose of materials and substances collected by filtration devices and backwash from these devices off-site
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementPAG-02 Part C I.B allows certain non-stormwater discharges from construction sites. These include uncontaminated groundwater or spring water, and construction dewatering water that complies with the Part A I.B.3 dewatering requirements. Two conditions apply: except for water used to control dust and to irrigate vegetation in stabilized areas, these discharges must not be routed to areas of exposed soil on the site, and the permittee must comply with any applicable requirements for these discharges under the General Permit.

    Applies when: PAG-02 projects PAG-02 General Permit, Part C § I.B [30]
    Show the source text
    authorized under this General Permit provided that, with the exception of water used to control dust and to irrigate vegetation in stabilized areas, these discharges are not routed to areas of exposed soil on the project site and that the permittee complies with any applicable requirements for these discharges under the General Permit ... Uncontaminated ground water or spring water; ... Construction dewatering water that complies with the construction dewatering discharge requirements of Part A I.B.3
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • ProcessDEP's PAG-02 Fact Sheet explains the dewatering rule. Where infiltration is infeasible, the water may go to surface waters unless there is reason to believe it holds pollutants other than sediment, but only after passing through at least two BMPs in series. DEP's examples are a filter bag followed by a sediment trap or basin, or a manufactured device using flocculation or coagulation and settling. The two-BMP requirement may be waived if the permittee demonstrates that a single BMP can achieve a turbidity of 50 NTU or less. DEP notes that EPA uses 50 NTU as a benchmark for dewatering discharges in its construction general permit.

    Applies when: PAG-02 projects PAG-02 Fact Sheet (3800-PM-BCW0405g Rev. 8/2024), p. 6 (Part A - Effluent Limitations, "Discharges from dewatering activities") [51]
    Show the source text
    Where infeasible, the permittee may discharge such water to surface waters unless the permittee has reason to believe the water contains pollutants other than sediment. ... the dewatering water must be treated by a series of at least two BMPs. ... a filter bag followed by a sediment trap or basin, or a manufactured device that uses flocculation or coagulation and settling ... may be waived if the permittee is able to demonstrate that a single BMP is capable of achieving a turbidity of 50 Nephelometric Turbidity Units (NTUs) or less. EPA uses 50 NTUs as a benchmark
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • StatusThe currently effective PAG-01 NPDES General Permit (stormwater from small construction activities) took effect March 1, 2022 and expires February 28, 2027. It covers earth disturbance of less than 5 acres, including a larger common plan of development or sale of less than 5 acres. One eligibility requirement is that stormwater from the site will not discharge to surface waters, including wetlands, classified as High Quality (HQ) or Exceptional Value (EV) under 25 Pa. Code Chapter 93.

    Applies when: Earth disturbance of less than 5 acres that needs NPDES coverage PAG-01 General Permit (3800-PM-BCW0404d Rev. 4/2025), cover page, § II.A.1 and 3, and signature page [31]
    Show the source text
    earth disturbance activity that involves earth disturbance less than five acres, or an earth disturbance on any portion, part, or during any stage of a larger common plan of development or sale where the larger common plan of development or sale involves earth disturbance less than five acres ... 3. Stormwater runoff from the project site will not discharge to surface waters, including wetlands, with a designated or existing use classified as High Quality Waters (HQ) or Exceptional Value Waters (EV) ... Effective: March 1, 2022 ... Expires: February 28, 2027
    Open Pennsylvania Department of Environmental Protection, Bureau of Clean Water (DEP eLibrary) (opens in a new tab)
  • StatusDEP's Erosion and Sediment (E&S) Resources page currently lists the "Erosion and Sediment Pollution Control Program Manual" as document 386-2134-001, March 2012 (the edition DEP currently lists), together with a separate "Corrections" sheet.

    DEP, Erosion and Sediment (E&S) Resources web page (Guidance list) [52]
    Show the source text
    Erosion and Sediment Pollution Control Program Manual (PDF) (386-2134-001, March 2012) Corrections for Erosion and Sediment Pollution Control Program Manual (PDF)
    Open Pennsylvania Department of Environmental Protection (pa.gov) (opens in a new tab)
  • StatusThe E&S Manual (Technical Guidance No. 386-2134-001, issued by DEP's Bureau of Clean Water, effective March 31, 2012) is guidance on complying with 25 Pa. Code Chapter 102 for anyone preparing E&S Plans for earth disturbance activities. DEP states that it is not an adjudication or a regulation.

    Applies when: Preparation of E&S Plans for earth disturbance activities E&S Manual 386-2134-001, p. i [33]
    Show the source text
    DOCUMENT NUMBER: 386-2134-001 TITLE: Erosion and Sediment Pollution Control Program Manual EFFECTIVE DATE: March 31, 2012 ... APPLICABILITY: This guidance applies to all those engaged in the preparation of E&S Plans for earth disturbance activities in the Commonwealth of Pennsylvania. ... The policies and procedures herein are not an adjudication or a regulation.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementE&S Manual: the ground between the pump discharge point and the receiving surface water should be checked for potential erosion and stabilized where needed. No filtering device is required for water pumped directly from a stream channel as part of a pump-around bypass system.

    Applies when: Pumped-water discharges (E&S Plan guidance) E&S Manual 386-2134-001, ch. 3, "Dewatering Work Areas", p. 53 [33]
    Show the source text
    The topography and conditions of the ground cover between the discharge point and the receiving surface water should be evaluated for potential erosion. Appropriate stabilization measures should be incorporated where needed to prevent erosion. No filtering device is required for water pumped directly from a stream channel as part of a pump-around bypass system.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementE&S Manual, "Pumped Water Filter Bag": the manual rates its sediment removal efficiency LOW. A filter bag is not an ABACT (antidegradation best available combination of technologies) for special protection watersheds unless it is surrounded by a compost sock ring or used with a sump pit. Filter bags may be used to filter water pumped from disturbed areas before discharge to surface waters. The maximum pumping rate for every bag in use or proposed should be available on site at all times during pumping.

    Applies when: Use of pumped water filter bags (E&S Plan guidance) E&S Manual 386-2134-001, ch. 3, "Pumped Water Filter Bag", p. 53 [33]
    Show the source text
    PUMPED WATER FILTER BAG - Sediment Removal Efficiency: LOW. This device is not an ABACT for special protection watersheds unless surrounded by a compost sock ring or operated in conjunction with a sump pit. Filter bags may be used to filter water pumped from disturbed areas prior to discharging to surface waters. ... The maximum pumping rate for any bag in use or proposed for use on a site should be available at the site at all times during pumping operations.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementE&S Manual Standard Construction Detail #3-16 (Pumped Water Filter Bag) specifications: low-volume bags are non-woven geotextile and must trap particles larger than 150 microns. Bags are replaced when half full of sediment. Bags go in a well-vegetated (grassy) area; where that is not possible, a geotextile underlayment and flow path must be provided. Bags must not be placed on slopes greater than 5%; for steeper slopes, clean rock or other non-erodible material may be placed under the bag. A compost berm or compost filter sock must be installed below bags located in HQ or EV watersheds, within 50 feet of any receiving surface water, or where no grassy area is available.

    Applies when: Use of pumped water filter bags (E&S Plan guidance) E&S Manual 386-2134-001, Standard Construction Detail #3-16, p. 54 [33]
    Show the source text
    Low volume filter bags shall be made from non-woven geotextile ... 150 microns. ... replaced when they become ½ full of sediment. ... located in well-vegetated (grassy) area ... Where this is not possible, a geotextile underlayment and flow path shall be provided. ... not be placed on slopes greater than 5%. For slopes exceeding 5%, clean rock or other non-erodible ... material may be placed under the bag ... Compost berm or compost filter sock shall be installed below bags located in HQ or EV watersheds, within 50 feet of any receiving surface water or where grassy area is not available.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • RequirementE&S Manual, "Sump Pit": the manual rates sediment removal efficiency LOW. A sump pit is not an ABACT for special protection watersheds unless used with a pumped water filter bag. Sump pits are described for sites where large volumes of water of low to moderate turbidity (not flowing from or through work areas) must be pumped from work areas and many filter bags would be required. They may also be used with filter bags to reduce the sediment pumped into the bags, but should not be used alone where highly turbid water is being pumped.

    Applies when: Pumping large volumes of water from work areas (E&S Plan guidance) E&S Manual 386-2134-001, ch. 3, "Sump Pit", p. 55 [33]
    Show the source text
    SUMP PIT - Sediment Removal Efficiency: LOW. This device is not an ABACT for special protection watersheds unless used in conjunction with a pumped water filter bag. For sites where large volumes of water of low to moderate turbidity (i.e. not flowing from or through work areas) must be pumped from work areas, and many filter bags would be required, sump pits (Standard Construction Detail #3-17) can provide a means of filtering the water. ... Sump pits should not be used alone where highly turbid waters are being pumped
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • DefinitionClean Streams Law § 1 definitions. "Pollution" means contamination of waters of the Commonwealth that creates or is likely to create a nuisance or to render the waters harmful, detrimental or injurious to public health, safety or welfare, to legitimate beneficial uses (the definition lists domestic, municipal, commercial, industrial, agricultural, recreational and other uses), or to livestock, wild animals, birds, fish or other aquatic life. It includes contamination by altering the physical, chemical or biological properties of the waters, by changing their temperature (or taste, color or odor), or by discharging liquid, gaseous, radioactive, solid or other substances into them. "Waters of the Commonwealth" expressly include impoundments, ditches, water courses, storm sewers, lakes, dammed water, ponds and springs.

    Clean Streams Law § 1, 35 P.S. § 691.1 ("Pollution"; "Waters of the Commonwealth") [15]
    Show the source text
    "Pollution" shall be construed to mean contamination of any waters of the Commonwealth such as will create or is likely to create a nuisance or to render such waters harmful, detrimental or injurious to public health, safety or welfare, or to ... other legitimate beneficial uses, or to livestock, wild animals, birds, fish or other aquatic life ... alteration of the physical, chemical or biological properties ... change in temperature ... discharge of any liquid, gaseous, radioactive, solid ... impoundments, ditches, water courses, storm sewers, lakes, dammed water, ponds, springs
    Open Pennsylvania General Assembly (palegis.us) (opens in a new tab)
  • Requirement25 Pa. Code § 93.6 general water quality criteria: water may not contain substances from point or nonpoint source discharges in amounts harmful to protected water uses or to human, animal, plant or aquatic life. The specific substances to be controlled include substances that produce turbidity or that settle to form deposits.

    Applies when: All surface waters 25 Pa. Code § 93.6(a)-(b) [16]
    Show the source text
    (a) Water may not contain substances attributable to point or nonpoint source discharges in concentration or amounts sufficient to be inimical or harmful to the water uses to be protected or to human, animal, plant or aquatic life. (b) In addition to other substances listed within or addressed by this chapter, specific substances to be controlled include, but are not limited to, floating materials, oil, grease, scum and substances that produce color, tastes, odors, turbidity or settle to form deposits.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • DEP's pond guidance warns that pond discharges can have dramatic thermal impacts on receiving streams: in summer, water leaving a pond can be as much as 8-10 degrees warmer than the stream water entering it. A pond proponent may be required to show that the thermal influence will not harm the aquatic community.

    Applies when: Ponds that discharge to streams DEP, "Introduction to Ponds and Chapter 105", Impacts to Water Resources [10]
    Show the source text
    Thermal impacts to streams receiving discharges from ponds can be dramatic. The temperature of water exiting a pond in the summer can be as much as 8-10 degrees warmer than the stream water entering the pond. A proponent for building a pond may be required to demonstrate that a thermal influence will not adversely impact the aquatic community.
    Open Pennsylvania Department of Environmental Protection (opens in a new tab)
  • StatusThe Pennsylvania eFOTG folder for Pond Sealing or Lining, Compacted Soil Treatment (520) currently lists five 2016 documents: the Conservation Practice Standard (revision date 2016-09-01), the Statement of Work (2016-06-01), the Practice Specification (2016-06-01), and two design guides - Design and Check (2016-09-01) and Instructions for Use of the Specification (2016-09-01).

    Applies when: Identifying the current PA NRCS standard for compacted-soil, bentonite or dispersant pond liners NRCS Pennsylvania eFOTG, Section 4, Conservation Practice Standards & Support Documents, "Pond Sealing or Lining, Compacted Soil Treatment (520)" folder listing [42]
    Show the source text
    2016-09-01T00:00:00 ... 520 PA CPS Pond Sealing or Lining-Compacted Soil Treatment 2016 ... 2016-06-01T00:00:00 ... 520 PA SOW Pond Sealing or Lining-Compacted Soil Treatment 2016 ... 2016-06-01T00:00:00 ... 520 PA PS Pond Sealing or Lining-Compacted Soil Treatment 2016 ... 2016-09-01T00:00:00 ... 520 PA GD Pond Sealing or Lining-Compacted Soil Treatment-Design and Check 2016 ... 2016-09-01T00:00:00 ... 520 PA GD Pond Sealing or Lining-Compated Soil Treatment-Instructions for Use of Spec 2016
    Open USDA NRCS (eFOTG) (opens in a new tab)
  • RequirementFor a clean water pond, PA 520 requires the compacted soil liner to be designed to reduce seepage to a rate that will allow the pond to function as intended. By contrast, a liner for a waste storage impoundment must meet specific discharge rates in NRCS's National Engineering Handbook Part 651 (AWMFH) or more restrictive rates mandated in State regulations, and laboratory testing of the liner material is required.

    Applies when: Design of a compacted/amended soil liner under PA 520 NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Criteria - Design Seepage Requirements (p. 520-CPS-1) [44]
    Show the source text
    Design a compacted soil liner for a waste storage impoundment to reduce specific discharge (unit seepage) to rates specified in the National Engineering Handbook (NEH), Part 651 ... or rates mandated in State regulations, if they are more restrictive. ... Laboratory testing of compacted soil liner material for a waste storage impoundment is required ... Design a compacted soil liner for a clean water pond to reduce seepage to a rate that will allow the pond to function as intended.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 520 requires the soil liner to be protected against damage, including from water-surface fluctuation, desiccation and cracking, and wave action, and all protrusions through the liner, such as pipes, must be properly sealed. A protective soil cover 'may be used' against desiccation or erosion; under severe conditions, additional design measures such as installation of a geomembrane in conjunction with the soil cover may be required. As a consideration (not a requirement), NRCS suggests a 12-inch protective soil cover over the compacted liner.

    Applies when: Protection and cover of a compacted/bentonite soil liner NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Criteria - Liner Construction; Liner Protection (p. 520-CPS-2); Considerations (p. 520-CPS-4) [44]
    Show the source text
    Properly seal all protrusions through the liner, such as pipes. ... Protect the soil liner against damage caused by the effects of water surface fluctuations, desiccation and cracking, wave action ... A protective soil cover may be used to protect the soil liner from desiccation or erosion. ... additional design measures such as installation of a geomembrane in conjunction with the soil cover may be required. ... Consider installing a 12-inch protective soil cover over the compacted soil liner.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 520 says impoundment side slopes should be 3H:1V or flatter to allow compaction on the slopes with the 'bathtub' construction method; slopes as steep as 2H:1V can be considered if the 'stair-step' method is used, and steeper slopes can be designed for isolated areas if protected. The foundation must be evaluated for karstic bedrock, joints and other bedrock discontinuities to decide whether a compacted soil liner is appropriate.

    Applies when: Grading a pond basin to receive a compacted/bentonite liner NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Criteria - Side Slopes; Foundation (p. 520-CPS-2) [44]
    Show the source text
    The side slopes of the impoundment should be 3H (horizontal) to 1V (vertical) or flatter to facilitate compaction of soil on the slopes when the “bathtub” method of construction is used ... Slopes as steep as 2H to 1V can be considered if the “stair-step” method of construction ... is used. Steeper side slopes can be designed for isolated areas if the slope is protected. ... Evaluate the foundation for conditions such as karstic bedrock, joints, and other discontinuities of the underlying bedrock to determine the appropriateness for a compacted soil liner.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementSoil dispersants under PA 520 must be tetrasodium pyrophosphate (TSPP), sodium tripolyphosphate (STPP) or soda ash unless laboratory tests using other dispersants are used in the design. For clean water ponds without laboratory tests or field performance data on similar soils, the minimum rates per 6-inch lift are 7.5 lb/100 sq ft for polyphosphate (TSPP, STPP) and 15 lb/100 sq ft for soda ash, with a maximum 6-inch lift. Personnel must wear masks and goggles against dispersant dust.

    Applies when: Dispersant-treated soil liners NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Additional Criteria for Soil Dispersant Treatment, Table 2 (p. 520-CPS-3) [44]
    Show the source text
    The dispersant must be tetrasodium pyrophosphate (TSPP), sodium tripolyphosphate (STPP), or soda ash unless laboratory tests using other dispersant types are used in the design. ... For clean water ponds, in the absence of laboratory tests or field performance data on soils similar to those to be treated, apply dispersant at a rate equal to or greater to the amount lined in table 2. Install the liner with a maximum 6-inch-lift thickness. ... Polyphosphate (TSPP, STPP) 7.5 ... Soda Ash 15 ... personnel onsite must wear masks and goggles
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 520 considerations (advisory) suggest a composite liner (geomembrane and/or geosynthetic clay liner) for liquid depths over 24 feet or poor foundations such as karstic bedrock. Plans and specifications must include, among other items, soil amendment requirements and compaction requirements. Required O&M includes excluding animals and equipment from the treated area, repairing liner damage to its original thickness and condition, and removing tree and large shrub roots at first appearance.

    Applies when: Planning, specifying and maintaining a 520 liner NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), 520-CPS (NRCS, PA, September 2016), Considerations; Plans and Specifications; Operation and Maintenance (p. 520-CPS-4) [44]
    Show the source text
    Consider using a composite liner system, including a geomembrane and/or geosynthetic clay liner for sites that have liquid depths greater than 24 feet or poor foundation conditions such as karstic bedrock ... Soil amendment requirements, as needed. ... Compaction requirements. ... Excluding animals and equipment from the treated area. ... Repairing damage to the liner; restoring the liner to its original thickness and condition. ... Removing roots from trees and large shrubs at first appearance.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • StatusThe Pennsylvania eFOTG folder for Pond Sealing or Lining - Geomembrane or Geosynthetic Clay Liner (521) lists four documents, all with a revision date of 2024-10-01: the Conservation Practice Standard (521 PA CPS 2024), Statement of Work, Practice Specification, and Design and Check Data.

    Applies when: Identifying the current PA NRCS standard for geomembrane or geosynthetic clay (GCL) pond liners NRCS Pennsylvania eFOTG, Section 4, "Pond Sealing or Lining – Geomembrane or Geosynthetic Clay Liner (521)" folder listing [43]
    Show the source text
    2024-10-01T00:00:00 ... 521 PA CPS Pond Sealing or Lining+ Geomembrane or Geosynthetic Clay Liner 2024 ... 2024-10-01T00:00:00 ... 521 PA SOW Pond Sealing or Lining+ Geomembrane or Geosynthetic Clay Liner 2024 ... 2024-10-01T00:00:00 ... 521 PA PS Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner 2024 ... 2024-10-01T00:00:00 ... 521 PA OTH Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner-Design and Check Data 202
    Open USDA NRCS (eFOTG) (opens in a new tab)
  • RequirementPA 521 venting and drainage: all geomembrane pond liners require vents at the crest of the side slopes spaced no more than 20 feet apart; a minimum 2 percent bottom grade is required for ponds without a bottom gas-venting system (1 percent allowed with 20-oz non-woven geotextile under the liner and tight grade control). All geomembrane liners require a drainage system if the pond invert is within 2 feet of the seasonal high water table; the collection pipe must outlet to an accessible sump or to the ground surface at least 50 feet from a stream or other water body.

    Applies when: Geomembrane-lined ponds NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 521-CPS (NRCS, PA, September 2024), Gas venting; Groundwater drainage (pp. 521-CPS-2 to -3) [46]
    Show the source text
    All geomembrane pond liners require vents at the crest of the side slopes with a spacing not to exceed 20 feet. ... a minimum bottom grade of 2 percent is required for ponds without a bottom gas venting system. 1 percent is allowed when 20 oz. non-woven geotextile is under the liner and tight grade control is used. ... All geomembrane liners require a drainage system if the invert elevation of the pond is within 2 feet of the seasonal high water table. ... discharges into an accessible sump or at the ground surface at least 50 feet from a stream or other water body.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 521 subgrade, cushion and safety: a cushion is required between the liner and sharp angular stones (particles over 3/8 inch for geomembranes, 1/2 inch for GCLs) - either a 12-oz/sq yd or heavier nonwoven geotextile or at least 6 inches of suitable soil. No standing water, mud, vegetation, snow, frozen subgrade or excessive moisture may be present when the liner is placed. All facilities with exposed flexible membranes must have a means of emergency egress.

    Applies when: Installing a geomembrane or GCL pond liner NRCS Pennsylvania Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), 521-CPS (NRCS, PA, September 2024), Safety; Cushion; Subgrade preparation (pp. 521-CPS-2 to -3) [46]
    Show the source text
    All facilities with exposed flexible membranes shall be equipped with a means of emergency egress. ... Place a cushion layer between the liner and exposed sharp angular stones that could damage the liner. This includes angular particles and concretions greater than 3/8 inch for geomembrane liners and 1/2 inch for GCLs. The cushion may be a 12-ounce-per-square-yard or heavier nonwoven geotextile or a layer at least 6 inches thick of soil ... No standing water, mud, vegetation, snow, frozen subgrade, or excessive moisture may be present at the time of liner placement.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 521 Practice Specification (materials and subgrade): the liner manufacturer must meet NSF Standard 54 requirements for flexible membrane liners and have at least five years of continuous experience manufacturing polyethylene geomembrane and/or experience totaling 10,000,000 square feet of manufactured polyethylene geomembrane. The area to be lined must be drained and allowed to dry until the surface is firm; cut slopes and fills in the lined area must be no steeper than 2.5H:1V; the pond bottom must be built on a minimum 2 percent slope for gas venting (1 percent can be used if underlaid with 20-ounce non-woven and with good grade control); and an anchor trench 18 inches deep and at least 15 inches wide (or as shown in the design) is dug completely around the lined area.

    Applies when: Installing a geomembrane liner to NRCS PA specifications NRCS Pennsylvania Practice Specification, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521) (Technical Guide Section IV, October 2024), Sections 2 (Materials) and 3 (Subgrade Preparation), p. 1 of 6 [53]
    Show the source text
    National Sanitation Foundation Standard 54 ... at least five (5) years continuous experience in the manufacture of polyethylene geomembrane and/or experience totaling 10,000,000 square feet ... drained and allowed to dry until the surface is firm ... no steeper than 2.5 horizontal to 1 vertical. ... minimum two percent slope for gas venting out of the bottom. One percent can be used if underlaid with 20 ounce non-woven as well as with good grade control. ... The trench shall be 18 inches deep and at least 15 inches wide, or as shown in the design.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementPA 521 Practice Specification (placement, protection and acceptance): installation must be directed at all times by a manufacturer-certified installer; joints need minimum 4-inch laps; seaming is not attempted below 32°F or above 104°F. The specification states that all sites shall have leak detection systems as shown in the design. Facilities with exposed flexible membranes need emergency egress at two or more locations and a 5-foot fence. A written guarantee of not less than one year against defective workmanship and materials is required, and construction must keep erosion and air and water pollution minimized and 'within legal limits'.

    Applies when: Installing a geomembrane liner to NRCS PA specifications NRCS Pennsylvania Practice Specification, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521) (Technical Guide Section IV, October 2024), Sections 4, 6, 11, 12 and 14 (pp. 2-6 of 6) [53]
    Show the source text
    The installation of the liner shall be directed at all times by an installer certified by the manufacturer. ... Minimum laps of four inches shall be provided for all joints. ... below 32 degrees F or above 104 degrees F ... All sites shall have leak detection systems as shown in the design. ... emergency egress at two or more locations. ... Fence shall be five feet high. ... protects the owner against defective workmanship and materials for not less than one year ... erosion and air and water pollution are minimized and held within legal limits.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • ProcessPA 521 Statement of Work: design deliverables include a list of required permits to be obtained by the client and plans adequate to obtain necessary permits; installation deliverables include verification that the client obtained required permits and advice on compliance with all Federal, State, Tribal and local laws.

    Applies when: NRCS-assisted geomembrane/GCL pond lining NRCS Pennsylvania Statement of Work, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (521) (September 2024), Design deliverables 1.b, 2; Installation deliverables 2, 6 [48]
    Show the source text
    List of required permits to be obtained by the client. ... Written plans and specifications including sketches and drawings shall be provided to the client that adequately describes the requirements to install the practice and obtain necessary permits. ... Verification that client has obtained required permits. ... Advise client/NRCS on compliance issues with all Federal, State, Tribal, and local laws, regulations, and NRCS policies during installation.
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementThe PA 521 Design and Check Data Requirements (October 2024) list items to be addressed in the design folder, as appropriate: survey data including a soils investigation documenting soil permeability class, drainage characteristics and depth to high water table or bedrock; and design data including PA One Call, consideration of the need for permits, an E&S Control Plan, an O&M plan including monitoring documentation, and a construction quality assurance plan.

    Applies when: NRCS-assisted geomembrane/GCL pond lining NRCS Pennsylvania, Design and Check Data Requirements, Pond Sealing or Lining - Geomembrane or Geosynthetic Clay Liner (Code 521) (Technical Guide Section IV, October 2024) [54]
    Show the source text
    The following items shall be addressed in the design folder for pond sealing or lining, geomembrane or geosynthetic clay liners as appropriate. ... Soils investigation documenting soil permeability class, drainage characteristics, depth to high water table or bedrock, etc. ... PA One Call ... Consider need for permits ... E&S Control Plan ... O&M Plan, including monitoring documentation ... Construction quality assurance plan
    Open USDA NRCS Pennsylvania (opens in a new tab)
  • RequirementThe PA NRCS Pond (378) standard (October 2023) requires that, where surface runoff is a pond's primary water source, the soils be impervious enough to prevent excessive seepage losses or be of a type that sealing is practicable.

    Applies when: Siting an NRCS-designed pond fed mainly by runoff NRCS Pennsylvania Conservation Practice Standard, Pond (Code 378), 378-CPS (October 2023), Site conditions / Reservoir [55]
    Show the source text
    If surface runoff is the primary source of water for a pond, the soils shall be impervious enough to prevent excessive seepage losses or shall be of a type that sealing is practicable.
    Open USDA NRCS Pennsylvania (eFOTG) (opens in a new tab)
  • StatusDEP's Erosion and Sediment Control FAQ (Version 1.8, revised August 12, 2026), FAQ #11, answers whether soil binders and flocculants containing polyacrylamide may be used during construction by referring to DEP's list of Alternative E&S and PCSM BMPs, which describes when such products may be approved without DEP review, are subject to DEP review, or are prohibited.

    Applies when: Polyacrylamide use during construction DEP, Erosion and Sediment Control FAQ (rev. Aug. 12, 2026), FAQ #11 [56]
    Show the source text
    FAQ #11: May I use soil binders and flocculants containing polyacrylamide during construction? The use of soil binders and flocculants containing polyacrylamide is addressed in DEP’s list of Alternative E&S and PCSM BMPs. The list describes the circumstances under which soil binders and flocculants containing polyacrylamide may be approved without DEP review, are subject to DEP review, and are prohibited.
    Open PA Department of Environmental Protection, Bureau of Clean Water (opens in a new tab)
  • RequirementA PFBC permit is required under 30 Pa.C.S. § 3506 to draw down impounded waters inhabited by fish; the application must be submitted no later than 30 days before drawdown begins. Applications are reviewed by PFBC and DEP, and a drawdown permit does not waive other State, local or Federal permits.

    Applies when: Draining a fish-inhabited pond (for example, to dry and seal the bed) 58 Pa. Code §§ 51.81(1), 51.82(b), 51.83, 51.84 [7]
    Show the source text
    A permit from the Commission is required under section 3506 of the code ... for the following activities: (1) Drawing down impounded waters inhabited by fish. ... (b) A completed permit application shall be submitted ... no later than 30 days prior to proposed commencement of draw down operations. ... does not constitute a waiver of the requirement for applicants to obtain other State, local or Federal permits for the proposed activity. ... A permit application will be reviewed by the Commission’s Division of Environmental Services and by the Department of Environmental Protection
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • Exemption58 Pa. Code § 51.89(a) is itself a general permit (no individual application) to draw down impounded waters when the water area to be drawn down is 1 acre or less AND the drawdown is of a type that does not require other State permits, such as erosion and sedimentation control permits and Dams and Waterways Management permits.

    Applies when: Draining a small pond of 1 acre or less 58 Pa. Code § 51.89(a) [7]
    Show the source text
    (a) Notwithstanding the other provisions of this subchapter, this section constitutes a general permit for persons to draw down impounded waters without applying for an individual permit when the following circumstances exist: (1) The water area to be drawn down is 1 acre or less. (2) The draw down operations are of a type that do not require other State permits, such as erosion and sedimentation control permits and Dams and Waterways Management permits.
    Open Pennsylvania Code & Bulletin (Legislative Reference Bureau) (opens in a new tab)
  • ProcessPFBC's Application to Draw Off Water from Impoundments (PFBC-DD01, updated March 2026) groups drawdown purposes. Items 1-7 are 'Construction, maintenance or elimination' purposes, including 1. dam or spillway repairs; 2. dam, spillway, or outfall structure repair/modification; 3. dredging; and 4. pond elimination and backfill. Items 8-10 are a separate 'Construction or maintenance' group (ice damage prevention or control, fish habitat structures, and 10. 'Other (explain)'). Section E, a DEP Supplement, must be completed if the purpose includes any of items 1 through 7; the form says many activities related to reservoir drawdowns require separate DEP and/or U.S. Army Corps of Engineers approvals before they begin, and DEP uses the supplement to determine any additional permitting requirements.

    Applies when: Drawdown for construction or maintenance, including sealing PFBC, Application to Draw Off Water from Impoundments (PFBC-DD01, updated March 2026), Sections D and E [20]
    Show the source text
    Construction, maintenance or elimination - *Complete Section E. DEP Supplement if project purpose includes any of items 1 through 7. ... 1. Dam or spillway repairs ... 2. Dam, spillway, or outfall structure repair/modification ... 3. Dredging ... 4. Pond elimination and backfill ... 8. Ice damage prevention or control ... 10. Other (explain): ... Many activities related to reservoir draw downs require separate DEP and/or U.S. Army Corps of Engineers approval(s) ... will be used by DEP to determine any additional permitting requirements.
    Open Pennsylvania Fish and Boat Commission (opens in a new tab)
  • PFBC's Pond Management page says drawdown permits are required for water bodies with a surface area greater than one acre and for water bodies of any size that require another state permit, with the application due at least 30 days before the drawdown. For anyone considering dredging or activities that could affect wetlands or streams, it advises contacting the DEP regional office.

    Applies when: Pond owners planning a drawdown or in-pond work PFBC, "Pond Management" (pa.gov), FAQ "What is a draw down permit? When do I need one?" [5]
    Show the source text
    Draw down permits are required for: Water bodies with a surface area that is greater than one acre; and Water bodies of any size that require another state permit, for example a DEP Dam Permit or a Waterways Obstruction and Encroachment Permit for the proposed project. If you are considering dredging or activities that could affect wetlands or streams, it is important that you contact the Department of Environmental Protection Regional Office ... A draw down permit application is to be submitted at least 30 days before a draw down event is to occur.
    Open Pennsylvania Fish and Boat Commission (pa.gov) (opens in a new tab)

Open questions to ask the agency

Not confirmed from a primary source

We could not confirm the following from an official source. Ask the agency listed before relying on any of it.

  • Whether a Fish and Boat Commission drawdown permit is needed to draw down a pond larger than 1 acre that is not inhabited by fish (for example, to dry the bed for sealing). The statute and regulation use a fish trigger, the Commission's web pages use an area trigger, and the application form asks whether the impoundment contains fish or other aquatic organisms without saying what follows from a "No". — ask: PFBC Division of Environmental Services, 595 East Rolling Ridge Drive, Bellefonte, PA 16823 (814-359-5147)
  • Whether an excavated (dug-out) pond with no dam counts as "dam waters" or "impounded waters" for the drawdown permit. Neither the Fish and Boat Code nor the Commission's drawdown regulations define those terms, and no Commission or DEP source addresses excavated ponds specifically. — ask: PFBC Division of Environmental Services (Bellefonte)
  • Whether DEP publishes the "Minimizing Sediment Pollution to Downstream Channels During Impoundment Dewatering" best management practices as a document (its number, date, contents such as drawdown rate, sediment controls, monitoring and timing), and when DEP says it applies. Searches of DEP's eLibrary and Dam Safety pages on September 28, 2026 found no such document; it may be an attachment sent with individual drawdown permits. — ask: DEP Bureau of Waterways Engineering and Wetlands, Division of Dam Safety (Harrisburg), or PFBC Division of Environmental Services, 595 East Rolling Ridge Drive, Bellefonte, PA 16823; ask for a copy of the BMP document attached to drawdown permits
  • Whether drawdown permits issued to private pond owners routinely carry a drawdown-rate limit, the DEP sediment BMP condition, seasonal (timing) restrictions or a fish-salvage requirement. The Commission's regulations, the Fish and Boat Code, the March 2026 application form and the Commission's web pages state none of these as standard conditions. — ask: PFBC Division of Environmental Services (Bellefonte); DEP Division of Dam Safety
  • Whether draining an existing pond by pipe, siphon or pump, with no earth disturbance and no drawdown permit, needs any DEP authorization (such as NPDES coverage) or specific BMPs for the discharged water. Only general rules (the Clean Streams Law, 25 Pa. Code §§ 91.33, 92a.1-92a.2 and 93.6) were found. — ask: DEP regional office Clean Water program; county conservation district (E&S program)
  • Whether the PAG-02 or PAG-01 dewatering conditions apply to pumping out an existing pond's standing water as part of a covered pond construction, enlargement or dredging project. Neither permit, the PAG-02 Fact Sheet nor DEP's E&S FAQ mentions ponds or impoundments being drained. — ask: County conservation district or DEP regional office reviewing the Notice of Intent
  • The final form of the reissued PAG-01 dewatering requirements. Only the August 22, 2026 draft exists; the comment period closed September 21, 2026, and the 2022 PAG-01 expires February 28, 2027. — ask: DEP Bureau of Clean Water; Pennsylvania Bulletin
  • Whether sealing or lining a drained pond bed (bentonite spread, mixed into the top soil and compacted; compacted clay; a geosynthetic clay liner; or a geomembrane) is "fill", an "encroachment", a "water obstruction" or "maintenance" under 25 Pa. Code Chapter 105, and so whether it needs a Water Obstruction and Encroachment Permit, a general permit, a waiver or no DEP authorization. The Chapter 105 definitions and waivers, general permits GP-1 through GP-11, and DEP's pond guidance and FAQs were reviewed; none addresses pond sealing or lining. — ask: DEP regional office Waterways and Wetlands Program (or a delegated county conservation district); DEP Division of Dam Safety for ponds behind jurisdictional dams
  • Whether DEP or the Fish and Boat Commission requires any permit or approval to apply bentonite, a polymer or a flocculant sealant through the water column of a filled pond (no drawdown), including whether it is a "discharge" needing NPDES coverage or falls under the joint DEP/Commission Chapter 91 permit, which covers algicides, herbicides and fish-control chemicals. — ask: DEP Bureau of Clean Water (717-787-5017, RA-EPNPDES_Permits@pa.gov) and DEP regional Clean Water Program; PFBC Division of Environmental Services
  • Whether DEP's polyacrylamide rules (Bureau of Clean Water approval for certain anionic PAM uses; cationic PAM prohibited for stormwater treatment) apply to polymer pond sealants used outside construction stormwater control, and whether DEP has any list, form or criteria for flocculants or polymers applied directly to ponds or other surface waters. — ask: DEP Bureau of Clean Water, 717-787-5017
  • Any Fish and Boat Commission statement specific to bentonite, pond sealants or flocculants used in waters inhabited by fish (for example turbidity, gill irritation, timing restrictions or approval requirements). Only the general prohibitions on substances deleterious to fish and on disturbing waters without necessary permits were found. — ask: PFBC Division of Environmental Services, 595 East Rolling Ridge Drive, Bellefonte, PA 16823
  • Whether the Pennsylvania Department of Agriculture treats bentonite or polymer pond sealants as "pesticides" (requiring state registration and, for hire, certified application) or as "soil amendments". No Department page, form or regulation found mentions pond sealants. — ask: PA Department of Agriculture, Bureau of Plant Industry: Pesticide Registration (717-772-5211) and Agronomic Products (soil and plant amendments)
  • Whether any Pennsylvania regulation sets a liner thickness, seepage rate or liner type for clean water (non-waste) ponds, which PA NRCS 520 would apply if more restrictive. PA 520 refers only generally to requirements of State regulations. — ask: NRCS Pennsylvania State Conservation Engineer; DEP Bureau of Clean Water
  • Whether NRCS Pennsylvania will revise its 2016 Pond Sealing or Lining - Compacted Soil Treatment (520) standard to follow the national proposed revision of that standard (the proposed national text carries a September 2026 date). As of September 28, 2026 the Pennsylvania folder lists only 2016 documents. — ask: NRCS Pennsylvania State Conservation Engineer

Sources

Every statement above links to one of these official sources. Expand “Show the source text” under any statement to read the exact passage it rests on.

  1. 30 Pa.C.S. Chapter 35 (Dams, Bar Racks and Migration Devices) (opens in a new tab) — Pennsylvania General Assembly (palegis.us), document date Ch. 35 added 1980; § 3509 amended July 10, 2020 (Act 56), retrieved September 28, 2026
  2. 58 Pa. Code § 51.81. Permit required. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date adopted effective February 2, 1991 (21 Pa.B. 422), retrieved September 28, 2026
  3. 25 Pa. Code § 105.122 (Drawdown of impounded waters) (opens in a new tab) — Pennsylvania Code & Bulletin, document date last amended eff. Jan. 8, 2011, retrieved September 28, 2026
  4. Apply to Draw Off Water from Impoundments (opens in a new tab) — Pennsylvania Fish and Boat Commission (pa.gov), retrieved September 28, 2026
  5. Pond Management (opens in a new tab) — Pennsylvania Fish and Boat Commission (pa.gov), retrieved September 28, 2026
  6. 58 Pa. Code § 51.89. General permits. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date amended effective December 8, 2001 (31 Pa.B. 6669), retrieved September 28, 2026
  7. 58 Pa. Code Chapter 51, Subchapter I (Permits to Draw Off Impounded Waters, §§ 51.81-51.89) (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date Code current through 56 Pa.B. 4026 (July 4, 2026), retrieved September 28, 2026
  8. 25 Pa. Code § 105.1 (Definitions) (opens in a new tab) — Pennsylvania Code & Bulletin, document date last amended eff. Jan. 8, 2011 (41 Pa.B. 219), retrieved September 28, 2026
  9. 25 Pa. Code § 105.12 Waiver of permit requirements - used in notes for currency (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date current through 56 Pa.B. 4026 (July 4, 2026), retrieved September 28, 2026
  10. Introduction to Ponds and Chapter 105 (opens in a new tab) — Pennsylvania Department of Environmental Protection, retrieved September 28, 2026
  11. 25 Pa. Code Chapter 91. General Provisions (full chapter text, incl. §§ 91.22, 91.34, 91.38) (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date Code current through 56 Pa.B. 4026 (July 4, 2026), retrieved September 28, 2026
  12. Alternative E&S BMPs and PCSM SCMs (Bureau of Clean Water) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Revised February 11, 2026, retrieved September 28, 2026
  13. 30 Pa.C.S. Chapter 25 (Protection of Property and Waters) (opens in a new tab) — Pennsylvania General Assembly (palegis.us), document date Ch. 25 added 1980, retrieved September 28, 2026
  14. 25 Pa. Code § 102.4. Erosion and sediment control requirements (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
  15. The Clean Streams Law, Act of June 22, 1937, P.L. 1987, No. 394, as amended (35 P.S. § 691.1 et seq.) (opens in a new tab) — Pennsylvania General Assembly (palegis.us), retrieved September 28, 2026
  16. 25 Pa. Code § 93.6. General water quality criteria (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date Amended Feb. 11, 2005, eff. Feb. 12, 2005, 35 Pa.B. 1197, retrieved September 28, 2026
  17. 25 Pa. Code § 92a.1. Purpose and scope. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), retrieved September 28, 2026
  18. 30 Pa.C.S. Chapter 1 (General Provisions; § 102 Definitions) (opens in a new tab) — Pennsylvania General Assembly (palegis.us), retrieved September 28, 2026
  19. 58 Pa. Code § 51.84. Review of permit applications. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date amended effective November 22, 2003 (33 Pa.B. 5704), retrieved September 28, 2026
  20. Application to Draw Off Water from Impoundments (PFBC-DD01) (opens in a new tab) — Pennsylvania Fish and Boat Commission, document date Updated March 2026, retrieved September 28, 2026
  21. 58 Pa. Code § 51.83. Other permits required. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date adopted effective February 2, 1991 (21 Pa.B. 422), retrieved September 28, 2026
  22. 58 Pa. Code § 51.86. Responsibility of permittee. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date adopted effective February 2, 1991 (21 Pa.B. 422), retrieved September 28, 2026
  23. 58 Pa. Code § 51.87. Refilling of impoundments. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date adopted effective February 2, 1991 (21 Pa.B. 422), retrieved September 28, 2026
  24. 58 Pa. Code § 51.85. Taking and disposal of fish. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date adopted effective February 2, 1991 (21 Pa.B. 422), retrieved September 28, 2026
  25. 25 Pa. Code § 105.96 (Outlet works) (opens in a new tab) — Pennsylvania Code & Bulletin, document date last amended eff. Jan. 8, 2011, retrieved September 28, 2026
  26. 25 Pa. Code § 105.131 (Operation, maintenance and monitoring) (opens in a new tab) — Pennsylvania Code & Bulletin, document date last amended eff. Jan. 8, 2011, retrieved September 28, 2026
  27. Environmental Hearing Board Adjudications and Opinions, 2025, Vols. 1 & 2 (pp. 1-798) (opens in a new tab) — Pennsylvania Environmental Hearing Board (ehb.pa.gov), document date 2025, retrieved September 28, 2026
  28. 25 Pa. Code § 92a.2. Definitions (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), retrieved September 28, 2026
  29. 25 Pa. Code § 91.33. Incidents causing or threatening pollution. (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date amended effective January 29, 2000 (30 Pa.B. 521), retrieved September 28, 2026
  30. PAG-02 General Permit - SAMPLE (3800-PM-BCW0405d Rev. 1/2026) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 1/2026, retrieved September 28, 2026
  31. PAG-01 NPDES General Permit for Discharges of Stormwater Associated with Small Construction Activities - permit (3800-PM-BCW0404d Rev. 4/2025) (opens in a new tab) — Pennsylvania Department of Environmental Protection, Bureau of Clean Water (DEP eLibrary), document date Rev. 4/2025; General Permit effective March 1, 2022, expires February 28, 2027, retrieved September 28, 2026
  32. Draft NPDES General Permit for Stormwater Discharges from Small Construction Activities (PAG-01), 56 Pa.B. 5629, Doc. No. 26-1207 (opens in a new tab) — Pennsylvania Bulletin (DEP notice), document date Published Aug. 22, 2026 (DRAFT; comments through Sept. 21, 2026), retrieved September 28, 2026
  33. Erosion and Sediment Pollution Control Program Manual, Technical Guidance No. 386-2134-001 (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date effective 2012-03-31, retrieved September 28, 2026
  34. DEP Staff Recognized with Governor's Awards for Excellence for Responses to Mine Subsidence and Dam Sediment Release (DEP news release) (opens in a new tab) — Pennsylvania Department of Environmental Protection (pa.gov), document date 2025-06-27, retrieved September 28, 2026
  35. 25 Pa. Code § 102.1. Definitions (opens in a new tab) — Pennsylvania Code & Bulletin, document date amended eff. Nov. 19, 2010 (40 Pa.B. 4861), retrieved September 28, 2026
  36. 25 Pa. Code § 105.11. Permit requirements (opens in a new tab) — Pennsylvania Code & Bulletin (Legislative Reference Bureau), document date amended Jan. 7, 2011, effective Jan. 8, 2011, 41 Pa.B. 219, retrieved September 28, 2026
  37. Chapter 105 General Permits (opens in a new tab) — PA Department of Environmental Protection, retrieved September 28, 2026
  38. General Permit BWEW-GP-9, Agricultural Activities (3150-PM-BWEW0509) (opens in a new tab) — PA Department of Environmental Protection, Bureau of Waterways Engineering and Wetlands, document date Rev. 6/2013, retrieved September 28, 2026
  39. General Permit BWEW-GP-11, Maintenance, Testing, Repair, Rehabilitation, or Replacement of Water Obstructions and Encroachments (3150-PM-BWEW0511) (opens in a new tab) — PA Department of Environmental Protection, Bureau of Waterways Engineering and Wetlands, document date Rev. 6/2013; effective August 10, 2004, retrieved September 28, 2026
  40. Water Quality Permitting for Pesticide Applications in Pennsylvania - Frequently Asked Questions (Bureau of Clean Water) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Revised February 21, 2025 (Version 1.1), retrieved September 28, 2026
  41. Chemical Additives (Wastewater Management) (opens in a new tab) — PA Department of Environmental Protection, Bureau of Clean Water, retrieved September 28, 2026
  42. eFOTG Pennsylvania - Pond Sealing or Lining, Compacted Soil Treatment (520) folder listing (API listByFolderAll, folderId -178) (opens in a new tab) — USDA NRCS (eFOTG), document date retrieved 2026-09-28, retrieved September 28, 2026
  43. eFOTG Pennsylvania - Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (521) folder listing (API listByFolderAll, folderId -175) (opens in a new tab) — USDA NRCS (eFOTG), document date retrieved 2026-09-28, retrieved September 28, 2026
  44. Conservation Practice Standard, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), NRCS Pennsylvania (520 PA CPS 2016) (opens in a new tab) — USDA NRCS Pennsylvania, document date September 2016 (eFOTG revision date 2016-09-01), retrieved September 28, 2026
  45. Practice Specification, Pond Sealing or Lining - Compacted Soil Treatment (Code 520), NRCS Pennsylvania (520 PA PS 2016) (opens in a new tab) — USDA NRCS Pennsylvania, document date June 2016 (eFOTG revision date 2016-06-01), retrieved September 28, 2026
  46. Conservation Practice Standard, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), NRCS Pennsylvania (521 PA CPS 2024) (opens in a new tab) — USDA NRCS Pennsylvania, document date September 2024 (footer); eFOTG revision date 2024-10-01, retrieved September 28, 2026
  47. Statement of Work, Pond Sealing or Lining - Compacted Soil Treatment (520), Pennsylvania (520 PA SOW 2016) (opens in a new tab) — USDA NRCS Pennsylvania, document date June 2016 (eFOTG revision date 2016-06-01), retrieved September 28, 2026
  48. Statement of Work, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (521), Pennsylvania (521 PA SOW 2024) (opens in a new tab) — USDA NRCS Pennsylvania, document date September 2024 (eFOTG revision date 2024-10-01), retrieved September 28, 2026
  49. PA520 Pond Sealing or Lining - Compacted Soil Treatment, Design and Construction Data Requirements (520 PA GD Design and Check 2016) (opens in a new tab) — USDA NRCS Pennsylvania, document date September 2016 (eFOTG revision date 2016-09-01), retrieved September 28, 2026
  50. Practice Specification, Pond (Code 378), Pennsylvania (378 PA Practice Specification 2023) (opens in a new tab) — USDA NRCS Pennsylvania, document date October 2023, retrieved September 28, 2026
  51. PAG-02 General Permit Fact Sheet (3800-PM-BCW0405g Rev. 8/2024) (opens in a new tab) — Pennsylvania Department of Environmental Protection, document date Rev. 8/2024, retrieved September 28, 2026
  52. Erosion and Sediment (E&S) Resources (opens in a new tab) — Pennsylvania Department of Environmental Protection (pa.gov), retrieved September 28, 2026
  53. Practice Specification, Pond Sealing or Lining, Geomembrane or Geosynthetic Clay Liner (Code 521), Pennsylvania (521 PA PS 2024) (opens in a new tab) — USDA NRCS Pennsylvania, document date October 2024 (eFOTG revision date 2024-10-01), retrieved September 28, 2026
  54. Design and Check Data Requirements, Pond Sealing or Lining - Geomembrane or Geosynthetic Clay Liner (Code 521), Pennsylvania (521 PA OTH 2024) (opens in a new tab) — USDA NRCS Pennsylvania, document date October 2024 (eFOTG revision date 2024-10-01), retrieved September 28, 2026
  55. NRCS Pennsylvania Conservation Practice Standard, Pond (Code 378) (opens in a new tab) — USDA NRCS Pennsylvania (eFOTG), document date October 2023, retrieved September 28, 2026
  56. Erosion and Sediment Control Frequently Asked Questions (Version 1.8) (opens in a new tab) — PA Department of Environmental Protection, Bureau of Clean Water, document date Final October 16, 2020; revised August 12, 2026, retrieved September 28, 2026

This is not legal advice. It is a plain-English summary of official sources, checked September 28, 2026. Laws, permits and agency practice change, and how they apply depends on your exact site. Confirm with the agencies named here, and with a licensed professional engineer for any dam, before you build.